HomeMy Public PortalAbout10 - Consolidated Department Report OctoberMEMORANDUM
Please find my highlights from the month of October below:
1. Streets LOT
Staff has met with many of the property owners on Commerce Street to obtain feedback of the
alternative sections previously shown to the Council. An update of these discussions will be
given to the Council on 3 November and selection of a street section alternative will be requested
of the Council during the 17 November Council meeting.
Staff has tentatively scheduled an introductory conversation for the downtown core feasibility
study to occur during the work session on 18 November. Following this meeting with the
Council, staff and engineers will engage with community members of the downtown core to
obtain feedback for this effort.
Staff is awaiting a quote from Horrocks Engineering to complete preliminary engineering of
Flynn, Conifer, and Chipmunk. This work will be funded through the Tourism LOT with
unanticipated funds from the 2016 funding year.
2. Sewer Disposal & JWAG Efforts
Staff will provide the next discussion related to sewer consolidation during this Council meeting.
The discussion will focus on land use planning and control measures related to consolidation.
Staff is focusing significant energy toward the completion of the sewer rate study, and working
with the District to provide information to FCS for completion of the study.
3. Sewer Pond Odor – Meeting with Property Owners
I am meeting with staff members during the first week of November to discuss this issue, and
will be planning a property owner meeting to occur this winter. As mentioned to Council, staff
plans to portray our ongoing sewer planning efforts as well as odor mitigating measures during
this meeting with property owners.
TO: City Council
FROM: Nate Coyle
DATE: 11/03/2016
RE: CITY MANAGER DEPARTMENT REPORT— OCTOBER
________________________________________________________________________________
Consolidated Department Report
November 3, 2016
Page 1 of 30
4. July 4th Community Discussions
During the survey process for the 4th of July in McCall I offered to meet with business owners
who had an interest in discussing the event with me. I will be working to schedule this meeting
in late November or early December. I had a brief conversation about this meeting with Sherry
Maupin and am hopeful that the Chamber of Commerce will be present in this discussion, and a
partner in the event moving forward. I will keep the Council informed with our progress on this
effort.
5. 5-Year CIP Updates
Staff will begin updating department CIPs in January of 2017. Many lessons were learned from
the first rendition of this process, and I anticipate that the CIP will grow in size and importance
during this year’s update process. Staff will, again, work to prioritize needs and bring a
comprehensive 5-year CIP to the Council for consideration prior to the budget season.
6. Campus Facility Planning
The two options provided to City Council from review during our last work session will be
presented again during this discussion in hopes of having the Council select a preferable option.
With the preferable library option in mind, staff will work to update the City campus plans which
were previously provided to the Council for consideration. Cost estimates for revised plans will
also be provided for consideration of the Council.
7. November 5 – Capital Tree Parade and Event
City staff will be providing significant assistance to the Capital Tree Parade and correlating
downtown event to occur on 5 November. The tree will be paraded South on Highway 55 and
showcased on Second Street in conjunction with an event street festival and the tree lighting in
Art Roberts Park on the same evening. Police, Parks and Recreation, and Public Works will be
the departments assisting this event.
8. Communications and Snow Management
Beginning in November and throughout snow season Communications and Public Works will be
releasing a community education series “Snow in the City.” The series consists of updated
informational cards, flyers, online communications via email and social media as well as weekly
snow tip ads in the Star News. New locations such as transit stops will be used to reach new
audiences. In addition, City staff with the collaboration of the Clerk’s office will be releasing
Licensed Snow Contractor Decals for display on snow removal equipment.
9. Contracting Private Entities
It was brought to our attention by Bill Nichols that the Assistant Attorney General’s office is
looking into the issue of city’s donating money to private entities. The Assistant AG stated
“This office remains concerned about the expenditure of public funds to benefit a private entity.
There are a number of legal concerns with regard to the allocation of public money to private
organizations. If asked for authorization of these expenditures, this office would take the
conservative approach and recommend not funding these types of request. But this office also
Consolidated Department Report
November 3, 2016
Page 2 of 30
recognizes that in the examples provided, the City is ostensibly contracting for services that you
can argue benefit the public. Recognizing the legality of these agreements is an open question
and this office will not substitute its judgment for that of yours as the City’s attorney.”
Keeping this in mind Bill has recommended that we have contracts with McPaws and Treasure
Valley Transit to show that the City is contracting for service. Staff is currently working with the
City Attorney to create these contracts. This would be true for any private entity that requests
and receives money from the city. We currently have contracts for those private entities who
receive the Tourism Local Option Tax; however, we may need to look at those contracts as they
have not been updated since 2006.
Consolidated Department Report
November 3, 2016
Page 3 of 30
CITY OF MCCALL
MONTHLY CONSOLIDATED DEPARTMENT REPORT
Department Project Comments Status
Airport AIP-21 Land
Acquisition
Providing background information to attorneys. Ongoing
Airport Hangar Lease
Rate Analysis
Analysis continues. Expect to begin discussions with
Council in November.
Ongoing
Airport AIP-22 Snow
Removal
Equipment
Factory visit did not change delivery date. Was able
to see model of truck we ordered under construction.
Appear to be well built and very capable. Larger than
expected.
Ongoing
Airport AIP-23 Ramp
Rehabilitation
Coordinating independent fee estimate (IFE) for
engineering/construction management of project as
required by FAA.
Ongoing
Airport Agency
Agreement
Began discussions on Agency Agreement for McCall
Aviation to collect airport fees.
New
Community
Development
Building See attached chart for building permit status and
comparison to previous years.
Updated
Community
Development
Building Library Expansion Committee continues the process.
Met with the consultants regarding the final 2
concepts, attended presentation to Council.
Updated
Community
Development
Geographic
Information
Systems (GIS)
Worked with the FEMA staff to use their data and our
data to create a web map to help people understand
there flood risks. Thanks to the Parks staff for
assisting with the instillation of our new pathway
signage. We will be installing the signs in the spring
so they aren’t damaged during the winter (see
pathways). Working with forest service, CIMBA and
Parks Dept on a large area recreation map for visitors
to our area that will be for sale at local retailer’s
proceeds will go towards the Parks and Rec Dept.
Continued to work on maps and analysis for the Comp
Plan update.
Updated
Community
Development
Grants See attached Grant Status Report for updates. Carol
and Cris Malvich attended LHTAC grant training on
10/13/16. Facilitated Valley Adams Planning
Partnership transportation meeting on 10/25/16.
Updated
Consolidated Department Report
November 3, 2016
Page 4 of 30
Department Project Comments Status
Community
Development
McCall In
Motion
Additional scope for development code update and
housing strategy was developed. The amendment to
the Logan Simpson contract with this scope of work
will be on the November 17 City Council meeting.
The first public outreach in Boise was held on October
22 at Boise’s Farmers Market. A survey for second
homeowners is being developed.
Updated
Community
Development
Planning &
Zoning
Commission
The November 1 meeting agenda includes 1 minor
Subdivision amendment, 1 Shoreline, 1 Design
Review, 1 Scenic Route, and 2 Record of Survey
applications. So far this calendar year, land use
applications are up more than 21% over last year (see
enclosed graph). Two P&Z City representative seats
or open for appointment– six letters of interest have
been received to fill the two positions.
Updated
Community
Development
Economic
Development
Michelle attended the Local Government ED Summit
on Oct. 11 with Mayor Aymon and Nate Coyle in
Boise. Working on department name change tasks and
job descriptions. Results of the ASAP Sector Analysis
presented at last meeting on October 25.
Updated
Community
Development
Pathways Wayfinding signage for the bike and pedestrian routes
arrived and plans to install this fall, weather and staff
dependent.
Updated
Community
Development
Public Art The Public Art Advisory Committee will meet next on
Nov. 10 to identify two new members to recommend
for appointment by City Council and to discuss next
projects now that both the Rotary Park Railings and
“Goats” projects are complete.
Updated
Community
Development
Payette River
Scenic Byway
(PRSB)
The Valley County Economic Development
Committee has signed an MOU with the byway to
accept the byway as a project of the VCEDC and
under the VCEDC fiscal umbrella.
Updated
Community
Development
McCall
Improvement
Committee
The McCall Improvement Committee met on October
20. Carolyn Trino and Carol Coyle represented
McCall at the 2016 America in Bloom Symposium in
Arroyo Grande, CA. Climate change was a main focus
of the Symposium.
Updated
Consolidated Department Report
November 3, 2016
Page 5 of 30
Department Project Comments Status
Community
Development
McCall
Redevelopment
Agency (MRA)
MRA received one Proposal for the parcel owned on
Pine Street and is moving forward with an appraisal.
No change
Community
Development
Housing Assisted developer with the identification of parcels
suitable for workforce housing.
New
Community
Development
Transit Center Staff reviewed the RFQ for design services for the
remodel and is refining the lease agreement. Staff met
on-site to look at infrastructure.
Updated
Community
Development
Recycling Met with Lake Shore to discuss status of recycling
center and a potential curbside recycling program.
Also met with County Commissioner Willey to about
the McCall Recycle Center.
New
Community
Development
Centennial
Committee
The Centennial Committee has received the plaques
for the monument and will install those this fall. The
Committee will be ending their work and will dissolve
as a City Committee this fall.
No change.
Community
Development
Historic Pres.
Commission
The HPC met 10/24/16. Work continues and McCall
History DVD and Rotary Park interpretive signs.
Updated
Community
Development
Outreach The Lardo Bridge won a Grow Smart Award from
Idaho Smart Growth!
Updated
Community
Development
Professional
Development/T
raining
Delta and Michelle attended the ID APA Conference
in Boise Oct. 12-14. Michelle presented on a panel on
‘Planning for Parks and Public Spaces.’
Updated
Golf Staffing At the end of the month of October there were 3 of us
working full time. 3 of our seasonal staff left for other
jobs the last of the month leaving us with 7 of which 2
are working part time.
Update
Golf Greens We did mid-month fungicide and fertilizer
applications to prep for winter. We have also raised
the cutting height to help with winter damage. We will
put on winter snow mold applications as soon as we
close.
Update
Golf Equipment We started steam cleaning equipment to prepare for
working on it during the winter.
Update
Consolidated Department Report
November 3, 2016
Page 6 of 30
Department Project Comments Status
Golf Vole Damage Our Vole Scram arrived the end of the month and we
will be doing two applications two weeks apart to
areas that we want to protect. Scram is a repellant and
not a poison and our hope is that we can push them
out into the wetlands.
Update
Golf Rounds Rounds this month seem to be down because of the
wet weather
New
Golf Club House The Club House will not be open this winter although
Allan says that he will be around some and have the
coffee on.
Update
Golf Irrigation The irrigation system was blown out and winterized
the last week of the month.
Update
Golf Tree Plantings The crew has been busy digging and transplanting 2 to
5 foot spruce and fir trees onto the golf course. We
have been thinning and taking them from areas along
the edges of the golf course. As of today we have
transplanted 175 trees. We also purchased 18 trees
from the Buffalo-Berry Farm which were Engelmann
Spruce and Western Larch
Update
Golf Chipper We had had the crew busy sense the wood chipper
arrived. We had a wind storm that took down 5 trees
which we cleaned up and chipped. These trees all had
areas of rot in them where they failed. We also have
taken down another 40 dead trees of various sizes and
species.
New
Golf Brush trimming Our crew has been busy cutting out dead brush and
cutting lower limbs on trees. We chipped a bunch of
the piles when the chipper arrived this month.
Update
Golf Practice Green We started the expansion of the practice green 1/3
larger to the west this month. We hope to finish in
November. We removed the cart path on the west side
for safety and will rough grade and add back a
sand/compost mix. We will then finish it with sod
removed from our nursery that matches the existing
green. The Practice green has always been too small
during tournaments.
New
Consolidated Department Report
November 3, 2016
Page 7 of 30
Department Project Comments Status
Golf Stumps Our crew has been using the backhoe to dig up stumps
that come out easily and have removed 60 of them.
The ones that are still pretty solid or near the cart path
we will use a stump grinder on next month. We will
back fill the holes using soil from our compost pile
then sod those areas using sod removed from around
the practice green during the expansion.
Update
Information
Systems
Staff Computers
Projects
Rollout of last round replacement staff computers
from FY16 budget is underway. Recipients include
Finance, Police, and Public Works.
Updated
Information
Systems
Virtual Desktop
Infrastructure
Virtual desktop infrastructure (VDI) hardware and
software have been acquired after vendor delays. Pilot
project for the Public Library is underway. Objectives
are cost savings in desktop hardware and less labor
intensive management of public access computing.
This has been a more challenging project – by far –
than anticipated.
Updated
Information
Systems
Cloud-Based
Email
In vendor discussion for cost and feasibility of moving
to cloud-based email and/or office productivity suite
services. Consulting with staff and other authorities
for security concerns and records manageability.
Updated
Information
Systems
Professional
Development
Professional development course work has been
completed, with focus on effective administration of
the City’s vendor-specific datacenter infrastructure.
Updated
Information
Systems
VCEDC
Conference
David Simmonds attended the VCEDC conference on
October 3 along with other City staff to explore
linkages between City planning, economic and
technology priorities, and regional economic
development efforts.
Updated
Information
Systems
Library
Expansion
Planning
Coordination with Library expansion planning parties
continues. A major challenge under “Option A” will
be planning and accommodating the displacement of
eight key staff offices and critical campus-wide fiber
infrastructure that now reside in the Annex building.
Broader campus planning integration and much
advance coordination will be required to move
forward with the more ambitious Library scenario.
Updated
Consolidated Department Report
November 3, 2016
Page 8 of 30
Department Project Comments Status
Information
Systems
Facilities A challenge is facilities planning efforts across
departments and funds, where IT coordination must
occur early in the process. Planned and opportunistic
projects to modernize data infrastructure in City
facilities will continue whenever possible. Some
facility networks have been operating over cabling
that is nearly 20 years old and in poor condition. Tie-
in to facilities planning and rehabilitation.
Updated
Information
Systems
Community-
Wide Data
Infrastructure
Planning of community-wide data infrastructure for
both City facilities and economic development
opportunities continues in several contexts: First, as
discrete CIP projects with finite operational objectives
for City government, and, second, as part of
Comprehensive and Regional planning efforts already
underway.
Updated
Library Upcoming
programs
Please see the calendar for your library’s upcoming
November programs included with this report.
Ongoing
Library Statistics September statistics included in this report. For the
next 2 months, Library statistics will come the
following months, due to the change in Council
meeting schedule.
Complete
Library Story Stop Every Wednesday, children ages 0-3. Makes for a
crowded but fun atmosphere for families.
Ongoing
Library Story Time Every Thursday 10:30-11:30 a.m. Reading and art
activities aid childhood development. Ages 3-5 with
adult.
Ongoing
Library Tech
Tuesday/Board
Games
Children are running from the school bus into the
library so as to be first in line! Staff are available to
help the public with their e-readers any day, but Tech
Tuesdays have been designated as a special time for
folks to bring in their devices so we can help them log
into OverDrive, our e-book application, or to print 3D
items. Tuesdays, 4-6 PM.
Complete
Consolidated Department Report
November 3, 2016
Page 9 of 30
Department Project Comments Status
Library Building
Expansion
Library design professionals Humphries Poli
presented draft proposals “Option A” and “Option B”
to Library Board and Committee on 10/20, and at the
Council Work Session on 10/21. Everyone is very
excited about the possibilities and the energy is good.
Committee is hoping to keep the project momentum
up and go forward with the next step. Final report
from the consultants will be received by early
November.
Ongoing
Library Friends Book
Sale
Friends of the Library sold hundreds of books on
Labor Day Weekend to earn money to support library
materials and programs.
Complete
Library Succession
Planting
Workshop
Master Gardener and U of I Extension partnered for
gardening planning workshop.
Complete
Library Pokémon Safari Children and chaperones discovered local Pokestops
and local history along the way.
Complete
Library Fall Mushroom
Program
Local enthusiast taught 2 programs about fall
mushrooms.
Complete
Library Film Society 62 people attended the film Oct.12th at the Alpine
Playhouse.
Complete
Library Fire Truck
Story Time
Local firefighters brought 3 trucks for National Fire
Prevention Week at the Library. Wide eyes as the kids
learned about fire and read books with the big guys
and gals. Big happy attendance.
Complete
Library Literacy
Workshops
Postponed, due to lack of registration. Complete
Library Job Fair Partnered with the ABC initiative—they provided
marketing for the job fair, and local employers came
to give on the spot interviews and applications.
Complete
Library ESL classes One of our most successful ESL series to date: energy
and numbers are high, students are learning a lot.
Child care is provided by volunteer Maggie Crawford,
and the class is taught by experienced volunteer
teacher Laura Bechdel. Please help us spread the word
to employers in the area, and thank our volunteers.
Ongoing
Consolidated Department Report
November 3, 2016
Page 10 of 30
Department Project Comments Status
Library Makerspace Hands-on, informal creative commons includes things
like basic sewing, bead crafts, destruction activities,
and 3D printing. Last Friday of each month.
Ongoing
Library Grants for
digitizing local
history records
Scanning continues slowly with volunteers. We are
applying for an Idaho Heritage Trust grant to leverage
the 50% matching already granted by the LOT
commission to temporarily hire someone to complete
the first scanning stage of this large project.
Ongoing
Police Personnel The McCall Police Department welcomed Nathan
Kimmel as a Patrol Officer on October 31, 2016.
Officer Kimmel is a sworn peace officer and will have
a modified Field Training period before beginning a
routine patrol schedule.
Complete
Police Personnel Officer Butler is attending the Idaho POST Academy.
He is scheduled to graduate November 18, 2016.
Ongoing
Police Training No training was scheduled in October 2016.
Complete
Police Training Sandy Ryska is scheduled to attend UCR/NIBRS
(Uniform Crime Reporting/National Incident Based
Reporting System) Training in Meridian, Idaho
November 8, 2016.
Chief Justin Williams, Corporal Seth Arrasmith, and
Officer Adam Benjamin are scheduled to attend Patrol
Rifle Instructor Training November 13-18, 2016 in
Boise, Idaho.
Ongoing
Police Community
Service
The McCall Police Department participated in the
DEA annual Drug Takeback event on October 22,
2016. For those individuals who are unable to attend
the Drug Takeback event, the McCall Police
Department will continue to accept expired, unwanted,
or unused over the counter and prescription
medication during normal business hours, Monday -
Friday 8:00am – 5:00pm.
Ongoing
Consolidated Department Report
November 3, 2016
Page 11 of 30
Department Project Comments Status
Police Grant Money
Opportunity
McCall Officers are continuing to work with the
National Highway Safety Board, Idaho Transportation
Department, and Idaho State Police on emphasis
patrols for Seat Belt Usage, Aggressive Driving, and
DUI awareness. In return McCall Police Department
receives Grant Money for needed equipment. The
police department is using the money to upgrade video
and radar systems in the patrol cars.
Recreation Partnerships Summer partnerships in Progress.
In Progress
Recreation City Website Updating City Website to flow better with online
registration page/content.
Ongoing
Recreation Online
Registration
Working with current provider to update all upcoming
program offerings and learning new additional
features to the site. Also working with City
Communications manager on enabling more
marketing/linking capabilities with TeamSideline.
Ongoing
Parks &
Recreation
Environmental
Advisory
Committee
Working on Green initiative, air quality, Payette Lake
water quality, and noxious weeds projects. Proposals
going forward to Council for Air Quality regulations
and Green Business practices to be endorsed by the
City of McCall. Open seat for high school
representative.
In Progress
Parks &
Recreation
Parks &
Recreation
Advisory
Committee
Presented Annual Report to Council 10/20. In Progress
Parks &
Recreation
Environmental
Advisory
Committee
Working on suggesting updates for City Noxious
Weed Policy; closing in on Green Business Brochure-
need $64 to produce stickers
In Progress
Recreation Recreation
Social Media
/Communicatio
ns
Working with communications manager to streamline
Recreation related correspondence to interested user
groups.
In Progress
Recreation Alternative
partners
/programming
Ongoing efforts to work with local private
organizations to develop opportunities for additional
programming.
Ongoing
Consolidated Department Report
November 3, 2016
Page 12 of 30
Department Project Comments Status
Recreation Equipment
Purchases
Inventory existing gear, identified auction items, and
ordering projected items needed.
In Progress
Recreation Fall/Winter
Activity Guide
Live online; printed versions will be available and
distributed by 10/28
Complete
Recreation Fall Programs Youth Programs going on now: Wrestling, Volleyball
Skills Camp
Programs Starting Soon: youth basketball, adult open
gym volleyball, indoor soccer, tots in training
In Progress
Parks &
Recreation
Employees/
Volunteers
Administrative Assistant is being advertised
Parks Supervisor position is being updated and will be
advertised in Nov.
In Progress
Recreation Budget Create budget spreadsheet to keep track of monies
spent to compare with financial dept.
In Progress
Parks Riverfront Park Engineering drawings for road, parking, and storm
water conveyance, are complete – Work is scheduled
for late fall and spring.
In Progress
Parks Summer/Fall
transition
Working on Fall projects – Irrigation blowouts
complete – will winterize and close restrooms in mid-
November. (Skate Park, Brown Park, Boat Trailer
Parking, Gold Glove Park)
In Progress
Parks Downtown
Sidewalk Brick
Repairs
Will continue as time permits In Progress
Parks &
Recreation
Parks Shop and
Office Planning
Identifying needs and finalizing location. In Progress
Parks Rotary Park
Construction
Re-assessing parks CIP priorities and re-aligning
funds to complete Rotary Park Construction and
landscaping while contractor is mobilized and Parks
staff has time.
In Progress
Parks Rotary Parking
Lot Design
Began engineering the re-paving/re-placement of the
Rotary Park Parking Lot. (CIP funding for FY17)
In Progress
Consolidated Department Report
November 3, 2016
Page 13 of 30
Department Project Comments Status
Parks &
Recreation
Brown Park
Playground and
Site
Improvements
Began researching play structures and installation
costs. Gathering quotes for pathway repairs and
additional site improvements. (CIP funding for FY17)
In Progress
Parks Way-finding
signage
Began installing poles and will complete installation
during the first two weeks of November.
In Progress
PW Admin/
Engineering
DEQ Water
Master Plan
Water model calibration ongoing. Ongoing
PW Admin/
Engineering
DEQ
Wastewater
Planning Grant
Winter Storage
Pond
Groundwater
Study
Haz-tech Drilling, Inc. completed well drilling on
10/23. Well pumps will be installed by SPF and
groundwater sampling will begin by the end of
October, 2016
Ongoing/
Updated
PW Admin/
Engineering
Utility Rate
Study
Staff working with PLRWSD to tour WWTF and
finalize treatment CIP schedule of costs. Will be
provided to FCS group by mid-November. City
Manager routinely updating City Council
Ongoing/
Updated
PW Admin/
Engineering
Asset
Management
Software
Training began with department heads in the
water/wastewater departments, and at that time it was
felt that additional data needed to be available for field
work. Currently working with Elements on those
additional system enhancements prior deploying to
field staff
Ongoing/
Updated
PW Admin/
Engineering
Land Use
Application
Development
Reviews
City Engineer working with Community Development
of application review (engineering and PW
review/approval) for 2 ROS, 1 DR, 1 SUB, and 1 SH
projects. Multiple pre-application meetings with
developers and city staff.
Ongoing/
Updated
PW Admin/
Engineering
Public Works
Fees
Staff is currently reviewing proposed fee increases to
properly recover costs related to sewer disposal and
ROW utility permitting.
Ongoing
PW Admin/
Engineering
Emergency
Outfall
Discharge Pipe
Hess Construction and Reserve on Payette have
agreed to complete the repair work and cost share the
expense. Work to start 11/1.
Ongoing/
Updated
Consolidated Department Report
November 3, 2016
Page 14 of 30
Department Project Comments Status
PW Admin/
Engineering
Community
Choices 2016
Streetscape
Improvements
Ongoing punch list items still being completed.
Change orders 2-5 received final approval by City and
ITD. Final completion anticipated by the end of
October.
Ongoing/
Updated
PW Admin/
Engineering
Transportation
Master Plan
Streets staff has compiled overall winter and summer
costs for 2015 and 2016. Horrocks preparing draft
asset cost model and resulting 20 year CIP for staff
review.
Ongoing/
Updated
PW Admin/
Engineering
Edgewater
Circle Water
Main
Construction began on 10/13 and is anticipated to be
completed by early November.
New/
Ongoing
PW Admin/
Engineering
Drainage
Management
Guidelines –
treatment storm
update
Will present resolution for County approval during
November/December to allow modifications to apply
to Impact Area.
Ongoing/
Updated
PW Admin/
Engineering
Commerce
Street
Reconstruction
Horrocks met with property owners to discuss access
restrictions. Project team will present next to City
Council on 11/3.
Ongoing/
Updated
PW Admin/
Engineering
Downtown
Core
Construction
Feasibility
Horrocks has been preparing revised cost estimates for
various street segments, evaluating construction
sequencing options, and utility improvement concept
plans. Preparation for first presentation to City
Council to be scheduled for 11/18.
New/
Ongoing
PW Admin/
Engineering
Sewer Reuse
Permit
Financing
Staff/JWAG reviewing and revising Annexation
Agreement.
New/
Ongoing
PW Admin/
Engineering
Deinhard
Bridge –
Expansion
Joints
CPC Construction completed all work during October.
Staff has inspected and approved all work.
New/
Ongoing
PW Admin/
Engineering
PW Roof
Repair
Roman Roofing, Inc. has completed the majority of
roofing work including 2 of 3 layer system. Final top
coat painting and coping cap touch up painting will be
completed in Spring 2017 when temperatures are more
favorable.
New/
Ongoing
PW
Streets
Right-of-Way
Maintenance
Crews continue working on storm drain issues around
town as time allows. Have also begun cleaning catch
basins and water drains.
Ongoing/
Updated
Consolidated Department Report
November 3, 2016
Page 15 of 30
Department Project Comments Status
PW
Streets
Dust abatement Additional dust abatement materials just received, so
additional abatement will be done on as needed bases.
Completed
PW
Streets
Street Sweeping Street sweeping continues as needed. Ongoing
PW
Streets
Customer
Complaints
Customer complaints are being addressed in a timely
manner with the city manager assistance when
necessary.
Ongoing/
Updated
PW
Streets
Street
Maintenance
Crews continue to repair pot holes. Ongoing
PW
Streets
Emergency
Call-Ins
1 emergency call out this month. Updated
PW
Streets
Storm Water
Ditch
Maintenance
Crews have cleaned out ditches on Woodlands Drive
and Hemlock Street
New/
Completed
PW
Streets
Winter Snow
Removal Sign
Project
Crews began installing receivers, posts, and signs
throughout the whole city.
New/
Ongoing
PW
Streets
Snow
Maintenance
Crews will be marking snow routes with snow poles New/
Ongoing
PW
Sewer
Collection
Manhole
Inspection
There were no manhole repairs this month. Will
continue to make repairs as weather allows
Ongoing
PW
Sewer
Collection
Emergency
Call-Outs
Duty phone employee’s responded to 5 emergency
call outs for the month (all 5 were lift station alarms).
Ongoing/
Updated
PW
Sewer
Collection
Sewer Main
Flushing
Continue to flush slow-moving sewer mains. Ongoing/
Updated
PW
Sewer
Collection
Private Line
Connection
Inspections
Camera of sewer lagoons to inspect intake main. Ongoing
PW
Sewer
Collection
Routine Lift
Station
Maintenance
Crews perform routine system checks at every lift
station twice a week.
Ongoing
PW
Sewer
Collection
New Sewer
Connections
1 new sewer connection inspection for the month. Ongoing
Consolidated Department Report
November 3, 2016
Page 16 of 30
Department Project Comments Status
PW
Sewer
Treatment
Routine
Maintenance
Performing typical maintenance duties and water
testing.
Ongoing/
Updated
PW
Sewer
Treatment
J-Ditch/Winter
Storage Pond
Inspection of liner completed and repairs were made.
The inspection brought to our attention that the liner
seams are starting to breakdown, which is pushing the
time table up for having to replace it. Additional
conversations will be had with the city manager and
new public works director to establish a plan going
forward.
Ongoing/
Updated
PW
Sewer
Treatment
Pond #1 Grit
Removal
Hydro cleaned the influent line. New/
Completed
PW
Sewer
Treatment
Septic
Receiving
Basked
Trying to filter more solids out of substations. Testing
is ongoing.
New/
Ongoing
PW
Water
Distribution
Main Service
Line Repairs &
Boil Notices
One main line repair on Edgewater, which required 2
boiling notices.
Updated
PW
Water
Distribution
Dig Line
Requests
Responded to 50 dig line requests to mark both water
& sewer infrastructure.
Updated
PW
Water
Distribution
Emergency
Call-Ins
3 emergency call ins for water issues. Ongoing/
Updated
PW
Water
Distribution
New Water
Services
Had 4 new water meter connections for the month. Ongoing/
Updated
PW
Water
Distribution
Work Orders The crew responded to 3 work orders from customers
and 19 from Utility Billing.
Ongoing/
Updated
PW
Water
Distribution
Fire Hydrant
Repairs
Repairs made to 1 fire hydrant for the month. Ongoing
PW
Water
Distribution
Pre Turn-off
Door Hangers
Crew hung 24 door hangers for Utility Billing. Updated
PW
Water
Distribution
MXUs 5 MXU’s were replaced this month. Updated
Consolidated Department Report
November 3, 2016
Page 17 of 30
Department Project Comments Status
PW
Water
Distribution
ECRs 1 ECR was replaced this month. Updated
PW
Water
Distribution
PRV Repairs Repairs made to 2 different PRV’s. Additional repair
materials have been ordered and will continue work
on additional valves as time and weather allows.
Ongoing/
Updated
PW
Water
Treatment
Routine
Maintenance
Facility components are routinely inspected and
repairs are made as needed.
Ongoing
PW
Water
Treatment
Legacy Raw
Water Station
Pump pull is complete and a substantial flow increase. Completed
PW
Water
Treatment
Test Pilot Filter This activity has been placed on hold for the time
being. We have made some internal dosing changes,
now that the demand is down, and will monitor the
test findings for the next few months.
Updated
PW
Water
Treatment
Effluent Flows Flows have slowed down substantially. Completed
PW
Water
Treatment
Back Wash
Activities
Back wash activities are currently running 90 hrs. per
filter.
Completed
PW
Water
Treatment
Raw Water
Chlorine
Assessment
Work continues by SPF on options. Updated
Consolidated Department Report
November 3, 2016
Page 18 of 30
GRANT STATUS REPORT‐ November 3, 2016 Department Project Name Project Manager Purpose Funder Amount Status Streets Department Mission St. Reconstruction TBD Reconstruct Mission St. from Deinhard to S. City Limits FHWA through LHTAC $2.19 millionNo change. Parks Riverfront Park Access Improvements Kurt Wolf Improve road surface, parking, and stormwater management at Riverfront IDPR $17,866 No change Public Works/Water Water Master Plan update Nate Coyle Update master Plan Dept. of Environmental Quality $87,500 Revised amount: $89,998 No Change: Project is underway. Public Works/Sewer Groundwater Study Nate Coyle Study leakage at wastewater pond Dept. of Environmental Quality $77,000 No Change: Project is underway. Streets Department Commerce Street Reconstruction Nathan Stewart Reconstruction of Commerce; stormwater and sidewalks Local Highway Technical Assistance Council $100,000 No change. Project to occur in 2017 Library Digital History Intern Meg Lojek/ Casey Bruck Hire a temporary assistant for historic records scanning Idaho Heritage Trust $1500 Will be notified by December. Library Books for Babies Meg Lojek/ Melody DodgePurchase books and bags for families of newborns St. Luke’s McCall Auxiliary $725 Will be notified by December. Community Development Bridging the Source: the Arts and Payette Lake Delta James Public art installation on Lardo Bridge; partnership with MAHC programming National Endowment for the Arts $25,000 Will be notified in December. Consolidated Department Report
November 3, 2016
Page 19 of 30
$15,403$6,874$1,332$39$3,963$15,906$22,726$30,202$40,421$34,419$10,523$32,419$14,734$1,352$3,668$5,729$10,532$12,071$50,469$27,461$40,560$35,463$23,316$51,797$13,953$2,623$3,553$1,469$15,317$35,705$38,367$66,275$52,029$23,553$34,042$28,993$5,205$10,882$1,476$22,638$23,008$39,518$48,668$50,606$62,108$38,661$58,537$104,529$23,975$0$0$0$0$0$0$0$0$0$0$0$0$20,000$40,000$60,000$80,000$100,000$120,000123456789101112BLDG PERMIT FEE + APPLICATION/PLANS CHECK FEE = TOTAL PERMIT FEESTOTAL BLDG PERMIT FEES ‐PER MONTH ‐FISCAL YEAR20132014201520162017OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP
Consolidated Department Report
November 3, 2016
Page 20 of 30
1234567891011122013$15,403 $22,277 $23,610 $23,649 $27,611 $43,517 $66,244 $96,446 $136,867 $171,286 $181,809 $214,2282014$14,734 $16,086 $19,754 $25,482 $36,014 $48,085 $98,554 $126,015 $166,575 $202,038 $225,354 $277,1502015$13,953 $16,575 $20,129 $21,598 $36,915 $72,620 $110,987 $177,263 $229,291 $252,844 $286,885 $315,8792016$5,205 $16,087 $17,563 $40,201 $63,209 $102,727 $151,395 $202,001 $264,109 $302,770 $361,307 $465,8362017$23,975 $23,975 $23,975 $23,975 $23,975 $23,975 $23,975 $23,975 $23,975 $23,975 $23,975 $23,975$0$50,000$100,000$150,000$200,000$250,000$300,000$350,000$400,000$450,000$500,000BLDG PERMIT FEE + APPLICATION/PLANS CHECK FEE = TOTAL PERMIT FEESBLDG PERMIT FEES ‐RUNNING TOTAL ‐FISCAL YEAROCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPFY 2017 BUDGET $305,250 FY 2016 BUDGET $264,000 Consolidated Department Report
November 3, 2016
Page 21 of 30
2010 2011 2012 2013 2014 2015 2016 YTD
DR 32 29 30 20 29 26 28
DR-signs 16 16 14 15 17 13 19
SR 18 14 7 10 12 9 17
ROS 13 10 10 21 15 27 20
CUP 5 1 4 3 5 4 6
SUB 1 2 1 1 2 1 6
PUD 0 0 1 0 2 2 3
VAC 0 0 0 0 1 1 2
VAR 2 1 1 0 0 0 0
ZON 0 3 2 0 4 2 2
TOTAL 87 76 70 70 87 85 103
Note: The totals above do not include Administrative Approval, Development Agreement, Shoreline, or Code
Amendment applications.
0
5
10
15
20
25
30
35
2010 2011 2012 2013 2014 2015 2016 YTD
McCall City/Impact Area Land Use Applications 2010-2016
DR DR-signs SR ROS CUP SUB PUD ZON
Consolidated Department Report
November 3, 2016
Page 22 of 30
Library Statistics ‐‐ FY2016
Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16 May‐16 Jun‐16 Jul‐16 Aug‐16 Sep‐16 Totals
2 ‐ 000‐099 8 5 16 17 13 10 10 3 56812
3 ‐ 100‐199 14 71510241715 3 2 7 12 13
4 ‐ 200‐299 7 5 21 16 19 12 8 19 14 13 26 9
5 ‐ 300‐399 39 46 46 43 30 38 58 60 46 58 57 39
6 ‐ 400‐499 4241230712 10528
7 ‐ 500‐599 22 18 24 42 38 37 37 36 48 49 48 43
8 ‐ 600‐699 83 81 87 88 117 86 60 68 105 84 87 80
9 ‐ 700‐799 64 96 46 81 53 81 59 42 63 51 66 56
10 ‐ 800‐899 34 36 48 27 28 21 28 25 34 42 42 18
11 ‐ 900‐919.9 32 34 35 48 40 63 27 41 30 18 37 25
12 ‐ 929‐999 65 54 37 44 63 48 36 37 40 46 41 46
13 ‐ Adult Fiction 699 682 692 760 665 809 671 666 764 866 940 687
14 ‐ Audio Books Circ Set 0283245246921 17 26 28 6 1
16 ‐ Biography 28 15 18 16 27 32 32 11 18 21 23 18
17 ‐ Board Books 103 93 81 111 148 134 116 142 127 78 105 107
18 ‐ CD Fiction Books 222 217 203 196 229 223 241 163 157 178 259 168
19 ‐ CD Junior Books 70 39 33 41 51 105 54 23 63 63 71 74
20 ‐ CD Music 10 000000 0 0000
21 ‐ CD Non‐Fiction Books 41 38 18 15 19 42 27 28 25 28 49 39
22 ‐ CD YA Books 44406175 1 9 6 10 4
23 ‐ Chapter books 138 109 99 126 159 169 139 134 309 278 190 133
24 ‐ Classic Movies 5 7 7 18 15 15 9 11 15 24 17 13
27 ‐ Dawn Moudy Collection 694459613 13636
28 ‐ DVD 14 13779483 0 0000
29 ‐ DVD Blu‐Ray 16 10 29 13 8 12 6 19 12847
30 ‐ DVD Circ Set 67 104 47 16 11 29 41 19 51 52 5 31
31 ‐ DVD Fiction 266 325 387 307 319 388 203 145 204 231 252 165
32‐ DVD Kids 10 13 20 15 26 25 89 166 165 183 175 112
33 ‐ DVD Non‐Fiction 52 35 53 28 36 51 17 48 23 21 39 25
34 ‐ DVD TV Series 10 7 8 11 20 23 10 14 21 11 16 9
35 ‐ E Non‐Fiction 38 46 28 40 64 66 68 92 51 73 54 101
36 ‐ Eames Collection 6651182 3 0301
37 ‐ Early Readers 153 112 151 143 164 128 112 110 235 191 122 119
38 ‐ Idaho Archives 1022000 0 0210
39 ‐ Idaho Room 36 26 25 48 60 99 44 65 57 70 81 69
40 ‐ Independent Films 5 5 19 10 19 19 9 1 6101812
41 ‐ Junior Biography 21 37 23 28 19 29 16 16 12 10 22 15
42 ‐ Junior Non‐Fiction 356 337 300 273 412 463 328 238 306 353 416 403
43 ‐ Junior Readers 263 285 235 189 237 263 295 288 494 498 447 270
44 ‐ Junior Spanish 26 29 49 21 36 37 52 15 14 13 27 33
45 ‐ Kit 12661271 5 3 9 17 7
46 ‐ Language learning 2002200 0 0320
47 ‐ Large Print 104 67 116 133 100 128 129 168 172 157 148 117
48 ‐ LP Circ Set 171801000 0 2500
49 ‐ Magazine 45 28 28 54 33 42 50 51 69 60 68 78
50 ‐ Map 0100001 0 0040
51 ‐ Oversized 1440174 5 4430
52 ‐ Parenting 2003103 0 2212
53 ‐ Professional 6020001 3 0000
54 ‐ Reference 2411122 1 1131
55 ‐ Spanish 10 10 17 11 13 14 5 1 4230
56 ‐ Story Books 751 624 699 595 821 875 708 620 774 740 762 745
57 ‐ Story Collection 24 20 21 9 22 11 12 22 26 29 28 22
58 ‐ Y A Non‐Fiction 33 12 28 15 26 26 15 6 12 17 26 20
59 ‐ YA Biography 0000000 0 0000
60 ‐ Young Adult Fiction 84 78 89 91 61 70 75 72 145 207 192 63
Consolidated Department Report
November 3, 2016
Page 23 of 30
61 ‐ Yount Adult Story Collection 0000000 0 0000
Adult Circulation 2068 2057 2124 2141 2063 2453 1894 1821 2069 2201 2399 1820
Young Adult Circulation 121 94 121 106 93 113 95 79 166 230 228 87
Children's Circulation 1930 1726 1724 1583 2149 2301 1978 1849 2553 2489 2408 2119
Circulation Totals 4142 3914 3992 3859 4334 4892 4002 3776 4816 4956 5065 4064
Attendance 2351 2132 2032 2126 2286 2445 2194 2418 2695 3578 2990 2276
Computer Usage 630 510 459 495 320 546 502 533 624 908 961 662
ILL's Received 23 37 23 25 28 25 35 27 28 36 30 38
Reference Requests 509 439 398 412 395 452 373 411 478 612 516 323
Food for Fines 33 11 28 20 130 84 31 22 79 22 10 12
Volunteers/hrs 9/15 5/8 6/27 2/7 3/5 17/44 6/12 14/25 14/34 20/45 26/52 29/45
Adult Program Attendence 138 174 77 180 92 60 54 84 40 28 9 23
Young Adult Program Attendence 9 6 23 6 2 914 8 9627264
Children's Program Attendence 670 483 551 587 477 740 546 578 507 466 353 392
Consolidated Department Report
November 3, 2016
Page 24 of 30
McCall Public Library 208-634-5522 www.mccall.lili.org
Hours: Monday -Friday 10 -6pm; Saturday 10 -2pm; Sunday closed
Library will be Closed on November 11th, 24th, and 25th
Sun Mon Tue Wed Thu Fri Sat
30 31
1
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
2
10:30-11:00 StoryStop
4:00—5:30 Clase de
Ingles
7:00-9:00 Author Visit
3
10:30-11:30 Story Time
4
5
5:00-7:00 Capitol
Christmas Tree
Celebration
6 7
8
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
9
10:30-11:00 StoryStop
4:00—5:30 Clase de
Ingles
10
10:30-11:30 Story Time
7:00-9:00 Travelogue
11
LIBRARY CLOSED
12
13 14
15
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
16
10:30-11:00 StoryStop
4:00—5:30 Clase de Ingles
7:00 Alpine Playhouse Film
17
10:30-11:30 Story Time
IDAHO FAMILY READ-
ING WEEK
18
3:30-5:30 Mak-
erspace
19
.IGD
20 21
22
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
23
10:30-11:00 StoryStop
4:00—5:30 Clase de
Ingles
24
LIBRARY CLOSED
25
LIBRARY CLOSED
26
27 28
29
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
30
10:30-11:00 StoryStop
4:00-5:30 Clase de Ingles
6:30—8:30 Adult Board
Gaming
1
10:30-11:30 Story Time
2
3
30 31 1 2 3 4 5
Primary Business Address
Your Address Line 2
Your Address Line 3
Your Address Line 4
Your business tag line here.
Phone: 555-555-5555
Fax: 555-555-5555
E-mail: someone@example.com
November 2016 Programs
SPECIAL EVENTS:
Award winning Idaho author Gail Chumbley
Wednesday, November 2nd 7:00-9:00pm
River of January is a two-part memoir about the au-
thor’s in-laws: Montgomery "Chum" Chumbley, a
Virginian farm boy who became a famous pilot in
WWII; and how he met his wife Helen Thompson, a
successful dancer, Hollywood actress, and singer.
November 5th 5:00-7:00pm
Capitol Christmas Tree Celebration
Join us for some live music by Play Date
inside the library! Head in after the pa-
rade for a special acoustic set and
warm up with some hot cider.
Thursday, November 10th
7:00-9:00pm
Sacred Journey a Travelogue on
Delhi and Rishikesh, India Presented
by Renée Silvus
Join us for an entertaining evening with a slideshow
of Renée's spring trip to India. She documented ex-
periences and novel sights with the travelogue in
mind.
November 14-18,
Idaho Family Reading Week
INTERNATIONAL GAMES DAY?
Friday, November 18th 3:30-5:30
Makerspace
This month we will be designing our own mini wind
turbines! Designer of the turbine that generates the
most electricity will win a prize.
ONGOING PROGRAMS:
Board Gaming ~ Tuesdays 3:30 -5:30pm—Play Munchkin, Forbidden
Island, Monopoly and more!
all ages.
Tech Tuesdays ~ Tuesdays— 4:00pm-5:30pm –Dedicated time for 3D printing,
help with e-books, and
overdrive.
Story Stop ~ Wednesdays 10:30 – 11:00 am A streamlined library story time with rhymes & games for
children ages 0-3 (with adult). Consolidated Department Report November 3, 2016Page 25 of 30
STREETS LOT BUDGETED, ACTUAL, AND FORECASTED DOLLARSMonthTourism LOT Five year average percentageFY16 Budget dollarsFY16 actual and forecast based on trendPercentage +/‐ based on budgetActual total Budget total total +/‐ YTDOctober4.51%November2.51%December5.83%1591st Quarter Total159January6.91%55,313 99,990 80.77% 100,149 55,313 81.06%February7.44%59,481 100,891 69.62% 201,040 114,793 75.13%March5.77%46,135 85,243 84.77% 286,283 160,928 77.89%2nd Quarter Total 160,928 286,124 77.80%April2.56%20,494 70,264 242.86% 356,547 181,422 96.53%May4.02%32,169 97,418 202.83% 453,965 213,591 112.54%June10.30%82,423 168,504 104.44% 622,469 296,014 110.28%3rd Quarter Total 135,086 336,186 148.87%July20.00%160,017 235,029 46.88% 857,498 456,031 88.04%August18.42%147,396 207,968 41.09% 1,065,466 603,427 76.57%September11.72%93,759 165,959 77.01% 1,231,425 697,186 76.63%4th Quarter Total 401,172 608,956 51.79%Total100.00%697,186 1,231,425 209.47%697,186 1,460,395 26-Oct-16Consolidated Department Report
November 3, 2016
Page 26 of 30
TOURISM LOT ACTUAL PERCENTAGES AND FORECASTED DOLLARSMonth FY11 FY12 FY13 FY14 FY15Five year averageFY16 Budget dollarsFY16 Budget + Contingent dollarsFY16 actual and forecast based on trendPercentage +/‐ based on budgetActual total Budget total total +/‐ YTDOctober 4.85% 4.70% 3.96% 4.02% 5.03%4.51%15,773 19,270 22,085 40.02% 22,085 15,773 40.02%November 2.33% 2.32% 2.38% 2.47% 3.06%2.51%8,774 10,720 12,986 48.00% 35,071 24,547 42.87%December 6.51% 5.29% 6.23% 5.44% 5.68%5.83%20,372 24,889 31,168 52.99% 66,239 44,919 47.46%1st Quarter Total 44,919 54,880 66,239 47.46%January 7.37% 6.48% 6.30% 7.44% 6.98%6.91%24,166 29,524 31,157 28.93% 97,396 69,086 40.98%February 8.38% 7.48% 7.28% 6.60% 7.43%7.44%25,987 31,749 32,613 25.50% 130,009 95,073 36.75%March5.03% 6.59% 6.60% 5.81% 4.80%5.77%20,156 24,626 23,712 17.64% 153,721 115,229 33.40%2nd Quarter Total 70,310 85,900 87,482 24.42%April2.61% 2.54% 2.01% 2.61% 3.03%2.56%8,954 10,939 15,255 70.38% 168,976 124,183 36.07%May3.40% 3.59% 3.62% 4.62% 4.88%4.02%14,055 17,171 22,047 56.87% 191,023 138,237 38.18%June8.72% 9.62% 10.98% 11.10% 11.09%10.30%36,011 43,995 50,323 39.74% 241,346 174,248 38.51%3rd Quarter Total 59,019 72,105 87,625 48.47%July20.98% 20.57% 20.27% 19.60% 18.58%20.00%69,911 85,413 82,520 18.04% 323,866 244,159 32.65%August 18.73% 18.56% 18.76% 19.49% 16.58%18.42%64,397 78,676 71,300 10.72% 395,166 308,557 28.07%September 11.09% 12.26% 11.61% 10.79% 12.86%11.72%40,963 50,046 53,538 30.70% 448,704 349,520 28.38%4th Quarter Total 175,272 214,136 207,358 18.31%Total 100.00% 100.00% 100.00% 100.00% 100.00%100.00%349,520 427,020 448,704 349,520 427,020 483,841 430,134 18,570 Year to date the actual revenues received for FY16 are 16.59% OVER the year to date revenues for FY15 and 46.54% over the 5 year average year to date.26-Oct-16Consolidated Department Report
November 3, 2016
Page 27 of 30
80,000 90,000 Five Year Actuals Comparison to Average70,000 50,000 60,000 40,000 20,000 30,000 10,000 ,‐October November December January February March April May June July August SeptemberAveragesFY11FY12FY13FY14FY15FY 16ForecastConsolidated Department Report
November 3, 2016
Page 28 of 30
30 00040,000 50,000 60,000 70,000 80,000 90,000 LOT FiveYear Average Compared to FY16 Actual October November December January February March April May June July August SeptemberAverage13,753 7,780 17,685 21,098 22,493 17,472 7,882 12,550 31,860 60,575 55,946 36,163 Budget15,773 8,774 20,372 24,166 25,987 20,156 8,954 14,055 36,011 69,911 64,397 40,963FY15 Actual22,085 12,986 31,168 31,157 32,613 23,712 15,255 22,047 50,323 82,520 71,300 52,152 Forecast‐10,000 20,000 30,000 AverageBudgetFY15 ActualForecastConsolidated Department Report
November 3, 2016
Page 29 of 30
MonthFY06Tourism LOT Actual Dollars Earned per Month FY07 FY08 FY09FY10 FY11 FY12 FY13 FY14 FY15 FY16 TotalsOctober14,274 16,938 14,412 11,306 10,483 11,520 12,392 12,163 13,390 19,298 22,085 136,176November11,272 9,748 7,978 7,147 5,850 5,535 6,103 7,298 8,233 11,738 12,986 80,902December18,547 21,746 22,261 16,224 14,294 15,459 13,939 19,101 18,122 21,802 31,168 181,495January17,232 18,707 20,163 17,932 17,007 17,510 17,065 19,334 24,733 26,778 31,157 196,461February20,446 22,943 27,324 24,826 18,873 19,921 19,716 22,331 22,013 28,487 32,613 226,880March15,110 13,668 21,527 15,969 8,925 11,941 17,344 20,251 19,365 18,422 23,712 162,523April7,294 8,049 6,425 5,954 6,183 6,210 6,696 6,165 8,719 11,641 15,255 73,336May11,994 11,230 9,368 8,595 7,335 8,074 9,461 11,113 15,390 18,711 22,047 111,271June23,442 24,611 25,426 22,248 21,491 20,728 25,352 33,681 37,000 42,541 50,323 276,520July47,654 54,276 47,052 42,408 48,747 49,843 54,214 62,187 65,335 71,296 82,520 543,012August44,024 52,948 41,089 32,480 39,398 44,505 48,919 57,546 64,959 63,598 71,300 489,466September26,973 26,073 23,600 25,826 20,258 27,603 33,029 35,605 35,959 49,346 52,152 304,272Total Dollars Received258,263 280,937 266,627 230,991 218,844 238,849 260,743 306,775 333,218 383,658 447,318 2,778,904
Consolidated Department Report
November 3, 2016
Page 30 of 30