MEMORANDUM
Please find my highlights from the month of July below:
1. Streets LOT
Nathan Stewart is conducting individual meetings with property owners along Commerce Street
through the month of August. Once the individual meetings are concluded, an update to the
Council will be provided regarding the outcome of these meetings.
I previously mentioned that a handful of property owners within the Jasper Subdivision may be
interested in formation of an LID to pave roads within their neighborhood. I have also been
approached by property owners on Conifer Lane and Flynn Lane with the same interest. Staff is
providing assistance to these property owners to help outline the process for pursuit of an LID.
2. Public Works Director Recruitment
The advertisement for this recruitment has closed, and staff is reviewing applications in
preparation for interviews. The first round of interviews will be conducted during the week of 15
August. An update will be provided to the Council as more information is available.
3. Parks and Recreation Director Recruitment
As previously announced, Dennis Coyle will enter retirement on 1 September of this year. A
recruitment for this position has been released with a closing date of 22 August. Following
closure of the advertisement, a review of applications and interviews will be conducted. I will
keep the Council informed as we move along in this process.
4. Sewer Rate Study
City staff has answered all follow-up questions for review by FCS. We are now simply awaiting
a request for a meeting to review and interpret data from FCS. At this time, we will be able to
engage the Council in a discussion regarding rate impact as related to proposed sewer
improvements.
TO: City Council
FROM: Nate Coyle
DATE: 8/11/2016
RE: CITY MANAGER DEPARTMENT REPORT— JULY
____________________________________________________________________________________
Consolidated Department Report
August 11, 2016
1 of 29
5. Sewer Planning Discussions
I believe we are ready to begin presenting components of an option for consolidation to the
Council. I have prepared a brief outline with a timeline for these discussions and will review this
with the Council during our upcoming meetings portion of the Council meeting.
City and PLRWSD staff conducted a focus group with volunteers on 1 August to discussion the
reuse process and also introduce our consolidation discussions. We received great feedback and
questions for each component of discussion. I will review the comments and feedback we
received during my review of this report with the Council.
6. Samson Trail Discussions
As mentioned in my recent email to the Council, Cris Malvich and I are continuing to work with
IDL to develop a permanent signage plan for the Samson Trail pathway. To date, IDL has stated
that it would be agreeable to placing signs at the entrance of the pathway to identify ownership
and contact information for the property. We proposed placing ecology blocks at the northern
entrance to the pathway, on city property, which would mitigate vehicle through-traffic on the
pathway and this is tentatively acceptable to IDL. IDL is in the process of marking property
boundaries and coordinating for development of signs. Once the property boundary markings are
complete, we will provide a proposal to IDL for city signage and proposed placement of blocks. I
will present this proposal to the Council prior to submitting to IDL for consideration.
7. July 4th Follow-up
July 4th has come and gone. Staff is now working to develop survey material to engage local
businesses and the general public for feedback on the event, and to seek ideas for enhancing the
event in future years. Two separate surveys will be developed; one survey will target businesses
and the other will look for input from the general public. Staff will provide a draft copy of the
business survey to the Chamber for review prior to release, and will also ask the Chamber for
assistance with circulating the business survey. I expect that we will present the draft surveys to
City Council for review and feedback during the 11 August Council Meeting. We plan to release
the surveys the following week for a two-week period.
8. Health Care Premium Quotes
Traci and I met with the broker and received initial quote information from other competitive
health care providers, which include Pacific Source and Select Health. We were not yet satisfied
with the options that were presented within the quotes from these providers and have asked the
broker to engage in conversations to seek additional options for consideration. Once we receive
this follow-up information from the broker, Traci and I will present options to the City Council
for selection (tentatively scheduled for the 25 August Council Meeting).
Consolidated Department Report
August 11, 2016
2 of 29
Department Project Comments Status
Airport AIP-21 – Land
Acquisition
Eminent Domain Complaint filed with 4th
District Court.
Ongoing
Airport Minimum Standards
and Rules/Regulations
Review
City Council provided recommended changes to
the Minimum Standards and Rules and
Regulations. Changes will be incorporated and
documents will be submitted for Council’s
approval.
Ongoing
Airport Hangar Lease Rate
Analysis
Airport Advisory Committee has completed
review of Lease Rates. Airport is preparing
package for Council’s consideration.
Ongoing
Airport AIP-22 – Snow
Removal Equipment
Bid protest received from Legacy Equipment.
Council will hear complaint July 14th.
Ongoing
Airport Airport Open House Airport Staff assisted Idaho Aviation
Association with planning and preparations for
an Airport Open House. Open House is
scheduled for July 16, 2016 from 9am – 2pm.
New
Community
Development
Building See attached chart for building permit status and
comparison to previous years.
Updated
Community
Development
Building Library Expansion Committee continues to meet
and move the design process forward.
Updated
Community
Development
Geographic
Information Systems
(GIS)
Staff have been working with U of I student to
create interpretive signs for Wildhorse Park.
Completed work with Communications Staff on
the Parking kiosk for the Mill Street lot. Created
custom application for parking study counts to
take place at the end of July. Working with
consultants on updated maps for the Comp Plan
update. Continuing to assist Water and Sewer
Dept on mapping of new and existing
infrastructure.
Updated
Community
Development
Grants See attached Grant Status Report for updates.
The Mission Street Reconstruction Project is
included in ITD’s 5 year funding plan and the
projected award to the City is $2.195 million.
Boo-ya!
Updated
Consolidated Department Report
August 11, 2016
3 of 29
Community
Development
McCall In Motion Recent public outreach events Community
Resource Fair (June 11), Payette Forest
Coalition presentation (June 15), and the July 4
Chalk It Up McCall. The next event is the
Rosebery Music Festival. Preparing for parking
study counts (July 20-23). Also planning for
workshops in September. Save the date for a
McCall In Motion boat cruise on September 12
3-6pm.
Updated
Community
Development
Building, Planning and
Zoning
Staff has archived project files and is updating
the secondary archive database.
Updated
Community
Development
Planning & Zoning
Commission
The August 2 meeting agenda includes 1 zoning
amendment, 1 subdivision plat amendment, 1
Conditional Use Permit, 1 Record of Survey, 3
Design Review, 1 Scenic Route, and 2 Shoreline
applications. The agenda also includes a pre-
application presentation for a zoning ordinance
amendment to redefine “formula, restaurant” to
apply to businesses that have 5 or more
businesses in common at other locations.
Updated
Community
Development
Public Art The “goats” and public art plaza next to the
Alpine Playhouse was completed just before the
July 4 holiday. The Rotary Parks railings project
is underway. The additional murals on the
Railroad Ave. retaining wall will be installed
when Parks crew time allows.
Updated
Community
Development
Payette River Scenic
Byway (PRSB)
The Byway Committee will have a joint meeting
with the Payette River Water Trails committee in
late July to discuss consolidation of efforts.
Updated
Community
Development
McCall Improvement
Committee
The McCall Improvement Committee met June
9. McCall in Bloom is well underway. Planning
for first annual Garden Tour is underway.
Updated
Community
Development
McCall Redevelopment
Agency (MRA)
MRA/Community Choices with new sidewalk,
paved boat parking, and storm water
improvements are complete.
Updated
Community
Development
Centennial Committee The Centennial Committee is working on final
tasks for Plaza completion.
Updated.
Community Historic Preservation The HPC will meet July 25. They are continuing
to work on the McCall History DVD. Work on
Updated
Consolidated Department Report
August 11, 2016
4 of 29
Development Commission Rotary Park interpretive signs begins in July.
Community
Development
Outreach/Regional
Collaboration
CD Director has agreed to work with U of I
extension on the ASAP Sector Analysis for the
region.
Updated
Golf Staffing At the end of the month of June there were three
full time and 15 seasonal employees. Two of the
seasonals are working part time. The staff this
year is working out great. One high school
student and two college students were hired at
the end of the month.
Update
Golf Greens The greens were vertical cut and top dressed at
the end of the month. Mowing daily with
triplexes on all greens. Extra work is still being
done on the new Aspen 1 green. There was a
fertilizer oops on a spot in the green.
Replacement will start soon by The Amateur.
We have also been either Hydrojecting it or
Needle tining it once a week to help it out.
Update
Golf Equipment The equipment is running nicely with the
exception of the fairway mowers that hopefully
will limp by until replaced.
Update
Golf Vole Damage Most of the seed that was planted has come up
and is starting to fill in the bad areas left by the
voles. A lot of time was spent using sand and
seed to help fill in some of the holes that were
left.
Update
Golf Revenue Revenue has been running ahead of last year and
it has been busy. Most of the increases are in
daily greens fees.
New
Golf Club House The windows and doors finally arrived and the
crew got started the last week of the month
changing them out. Hopefully to have it finished
the week after the 4th.
Update
Golf Cart Paths Crack Seal The Cedar cart paths were crack sealed. Work
will continue on Aspen and Birch as time allows.
Update
Golf Irrigation The system has been running pretty smoothly
although well water ran short during the last hot
Update
Consolidated Department Report
August 11, 2016
5 of 29
spell.
Golf Aspen 5 – Bathroom The lift pump for the golf course bathrooms
failed in the middle of the month. A portable
toilet was brought in while it was worked on.
The failed pump was finally extracted. There
were also golf balls in the check valve which
could have been the culprit as well as the pump
has not been replaced in at least the 10 years. A
new pump has been ordered and working on
putting in a bigger culvert around it so the foot
valve can be serviced without having to dig up
the whole thing.
New
Information
Systems
Work Focus and
Projects
Datacenter expansion for FY16 is complete, to
accommodate projected growth in Police video
retention. Vendor engineering was onsite with us
the week of June 27.
Virtual desktop infrastructure (VDI) pilot project
for the Public Library is underway. Objectives
are cost savings in desktop hardware and less
labor intensive management of public access
computing.
Second round purchasing of replacement staff
computers and network equipment has begun.
Additional field-oriented tablets for Public
Works asset management were configured and
deployed to the department on June 15.
Updated
Information
Systems
Management Capital project submission and review, and
annual operating budget development are
underway. Chris Curtin is participating in the
capital project process and review team.
InfoSys is participating in comprehensive plan
update processes, particularly in the area of city-
wide infrastructure. We did not receive a
technical assistance award under the EPA “Cool
and Connected” rural broadband program, but
our efforts to help provide infrastructure for
efficient City operations and progressive
economic development will continue.
Updated
Consolidated Department Report
August 11, 2016
6 of 29
Information
Systems
Facilities Planned and opportunistic projects to modernize
data infrastructure in City facilities will continue
whenever possible. Some facility networks have
been operating over cabling that is nearly 20
years old and in poor condition. Tie-in to
facilities planning and rehabilitation.
Updated
Parks &
Recreation
Partnerships Summer partnerships in Progress. In Progress
Parks &
Recreation
City Website Updating City Website to flow better with online
registration page and content.
Ongoing
Parks &
Recreation
Online Registration Working with current provider to update all
upcoming program offerings and learning new
additional features to the site. Also working with
City Communications manager on enabling
more marketing and linking capabilities with
TeamSideline.
Ongoing
Parks &
Recreation
Environmental Action
Committee
Working on Green initiative, air quality, Payette
Lake water quality, and noxious weeds projects.
Proposals going forward to Council for Air
Quality regulations and Green Business practices
to be endorsed by the City of McCall. Open seat
for high school representative.
In Progress
Parks &
Recreation
Gold Glove Park ADA walkway and additional bathroom hand
dryers upcoming. Summer landscaping with city
and donated funds to take place this Summer.
In Progress
Parks &
Recreation
Rec Social
Media/Communication
s
Working with communications manager to
streamline Rec related correspondence to
interested user groups.
In Progress
Parks &
Recreation
Alternative
Partners/Programming
Ongoing efforts to work with local private
organizations to develop opportunities for
additional programming.
Ongoing
Parks &
Recreation
Summer Programs Programs:
Boys Baseball – Complete
Girls Softball – Complete
Traveling ASA – Complete
Yth Spring Soccer – Complete
Soccer Camp – In Progress
Tennis – In Progress
In Progress
Consolidated Department Report
August 11, 2016
7 of 29
Adult Softball – Upcoming
Football Camp – Upcoming
Swimming Lessons – Upcoming
Snorkel – Upcoming
Mtn. Bike – Upcoming
Wee- Soccer – Upcoming
Tee-ball – Upcoming
Summer Programs – All marketing,
coordination, and updating website-complete
4th of July Celebration was a huge success!
Parks &
Recreation
Helmet Loaner
Program/Scholarship
$600 used for helmet purchases and $400 to be
used for students. Working with the school to
identify 10-15 scholarships based on need and
whole student concept. Re-visit in Fall 2016.
In Progress
Parks &
Recreation
Summer Equipment
Purchases
Inventory existing gear and ordering projected
items needed.
In Progress
Parks &
Recreation
Summer
Employees/Volunteers
Contacting instructors, coaches and umpires
from last summer about current openings.
Seasonal employees hired and training is
ongoing.
In Progress
Parks &
Recreation
Recreation Supervisor
Position
Two in-house employees applied for the
position; decision to be made by 06/29. Tara
Woods hired.
Complete
Parks &
Recreation
Administrative
Assistant
Parks seasonal employee Tyler Padgett was
asked to split work day between Gold Glove
(Parks), Adult Softball League (Recreation) and
Admin. Assistant (PAR)
In Progress
Parks &
Recreation
Mountain Bike Skills
Park
Grant accepted, with due completion date of
May 2017. Contractor and designer will work
with PAR to ensure completion date.
In Progress
Parks &
Recreation
Riverfront Park Adjustments to construction drawings underway.
Coordinating with Streets Dept. on schedule.
In Progress
Parks &
Recreation
Wild Horse Property –
Thompson Street
Working with a University of Idaho graduate
student on the design of interpretive panels and
pathway.
In Progress
Parks & Grant Applications Road and Bridge Grant – Riverfront; Mtn. Bike AWARDED
Consolidated Department Report
August 11, 2016
8 of 29
Recreation Skills Park Grant
Parks &
Recreation
Downtown Sidewalk
Brick Repairs
Will continue as time permits. In Progress
Parks &
Recreation
Parks Shop and Office
Planning
Identifying needs and finalizing location. In Progress
Parks &
Recreation
Rotary Park
Construction
Documents and Bid
Package
Bid awarded, finalizing schedule. In Progress
Parks &
Recreation
Way-Finding Signage Working with Community Director on the
design and implementation of Way Finding
signs.
In Progress
Parks &
Recreation
Fourth of July Cleanup considerably less. Very successful.
Staff assisted with events.
Complete
Parks &
Recreation
Employee P&R Director has announced retirement
effective 9/1
Not Yet
Complete
Police Personnel The McCall Police Department has completed
the recruitment for new officers. Two positions
have been filled. The new Officers are scheduled
to report on July 11, 2016.
Ongoing
Police Personnel Sergeant Larry Stokes retired from the McCall
Police Department on June 30, 2016 after
working 11 years for The City of McCall.
Officers Brian Gestrin and Seth Arrasmith were
promoted to Patrol Corporals.
Code Enforcement Officer Stephanie Brandt has
completed the McCall Police Department’s Code
Enforcement FTO program. Stephanie is now
working a regular shift rotation.
Complete
Police Training Pete Rittenger attended Verbal Excellence
Training June 12, 2016 in Boise, Idaho.
Det. Brian Koch and Sandy Ryska attended
Investigating Sex Crimes, June 12-13, 2016, in
Las Vegas, NV.
Corporal Seth Arrasmith attended Ground
Complete
Consolidated Department Report
August 11, 2016
9 of 29
Control Instructor training in Coeur D’Alene,
Idaho, June 19-23, 2016.
Police Training Officer Adam Benjamin is scheduled to attend
Instructor Development Training July 11-15,
2016, in Meridian, Idaho.
Sandy Ryska is scheduled to attend NIBRs and
Missing Persons Training July 19-20, 2016 in
Moscow, Idaho.
Dallas Palmer and Christian Wann are scheduled
to attend Advanced Search and Seizure Training
in Kimberly, Idaho, July 21-22, 2016.
Justin Williams, Seth Arrasmith, Adam
Benjamin are scheduled to attend Glock Armorer
Training July 27-28, 2016 in Meridian, Idaho.
Ongoing
Police Community Service The McCall Police Department continues to
accept expired, unwanted or unused over the
counter and prescription medication during
normal business hours, Monday - Friday 8:00am
– 5:00pm.
McCall Officers are continuing to work with the
National Highway Safety Board, Idaho
Transportation Department and Idaho State
Police on emphasis patrols for Seat Belt Usage,
Aggressive Driving, and DUI awareness. In
return, McCall Police Department receives Grant
Money for needed equipment. The police
department is using the money to upgrade video
and radar systems in the patrol cars.
Ongoing
PW Admin/
Engineering
DEQ Water Planning
Grant
Fire flow testing for water model calibration
scheduled completed June 22/23. Water model
calibration ongoing.
Ongoing
PW Admin/
Engineering
DEQ Wastewater
Planning Grant
Winter Storage Pond
Groundwater Study
The revised Quality Assurance Project Plan and
Groundwater Monitoring Plan have been
approved by IDEQ. It is expected that new
monitoring wells will be installed in July and
August
Ongoing/
Updated
Consolidated Department Report
August 11, 2016
10 of 29
PW Admin/
Engineering
Utility Rate Study PW and SPF completed draft CIP submittals to
FCS. FCS provided updated rate study
calculators. Staff and SPF are further evaluating
CIP timeline to identify infrastructure critical for
new reuse permitting and potential FY17
bonding be completed during mid-June.
Ongoing/
Updated
PW Admin/
Engineering
Asset Management
Software
Tablets for the water/wastewater crew members
have been programmed by IS, and training
should begin later this month or first of August.
Ongoing/
Updated
PW Admin/
Engineering
Land Use Application
Development Reviews
City Engineer working with Community
Development of application review (engineering
and PW review/approval) for 2 ROS, 7 DR and 1
CUP projects. Multiple pre-application meetings
with developers and city staff.
Ongoing/
Updated
PW Admin/
Engineering
Public Works Fees Staff is currently reviewing proposed fee
increases to properly recover costs related to
sewer disposal and ROW utility permitting.
Ongoing
PW Admin/
Engineering
Emergency Outfall
Discharge Pipe
PW is compiling an engineer’s estimate for
relocation to compare against the cost of
repairing the damage pipe in place. Analysis to
be completed in July.
Ongoing/
Updated
PW Admin/
Engineering
Community Choices
2016 Streetscape
Improvements
Substantial completion inspection completed on
6/30/16. Outstanding items (lights, electrical)
will be completed in July.
Ongoing/
Updated
PW Admin/
Engineering
Mill Street Parking Lot
Paving – Summer 2016
MRA funded paving project was bid and
awarded to Granite Excavation in May.
Construction timing was coordinated with the
Community Choices Project.
New/Comple
ted
PW Admin/
Engineering
Transportation Master
Plan
Traffic count analysis is ongoing. Parking
capacity study will commence in July using CD
and PW staff. Public outreach development for
transportation plan will commence in July.
Ongoing/
Updated
PW Admin/
Engineering
Edgewater Circle
Water Main
Horrocks and staff conducted final site meeting
to confirm final design criteria and existing
sewer utility locations. Final design and bid
documents to be completed in July. Bid award
and construction scheduled for
August/September.
New/Ongoin
g
Consolidated Department Report
August 11, 2016
11 of 29
PW Admin/
Engineering
Drainage Management
Guidelines – Treatment
Storm Update
Will present resolution for County approval
during June or July to allow modifications to
apply to Impact Area.
Ongoing/
Updated
PW Admin/
Engineering
Commerce Street
Reconstruction
City staff and select Council Members met with
property owners twice during June. Work
session with City Council scheduled for July 15
New/Ongoin
g
PW Admin/
Engineering
Downtown Core
Construction
Feasibility
Initial construction estimates being developed
and coordination with Franchise utilities is
ongoing
New/Ongoin
g
PW
Streets
Street Striping Bids Contract awarded to Curtis Clean Sweep.
Painting will begin later this month.
New/Comple
ted
PW
Streets
Right-of-Way
Maintenance
Crews continue working on storm drain issues
around town as time allows.
Ongoing/
Updated
PW
Streets
Seal Coating Crew prepped city owned parking lots for seal
coating by sub-contractor.
New/Comple
ted
PW
Streets
Dust abatement Dust abatement continues. New/Ongoin
g
PW
Streets
Street Sweeping Street sweeping continues as needed. New/
Ongoing
PW
Streets
Customer Complaints Customer complaints are being addressed in a
timely manner with the City Manager assistance
when necessary.
Ongoing/
Updated
PW
Streets
Rotary Park Assisted the Park Department with paving at
Rotary Park
New/Comple
ted
PW
Streets
Street Maintenance Crews continue to repair pot holes in the down
town core.
Ongoing
PW
Streets
Mill Street Storm
Water Upgrade
Construction of new catch basin completed, as
well as paving around the lip.
Completed
PW
Streets
Emergency
Call-Ins
No emergency call outs this month. Updated
PW
Streets
Street Striping/City Crews have been stripping crossbars, and
crossing marks. This will continue into July due
to poor weather the first of the month.
Updated
Consolidated Department Report
August 11, 2016
12 of 29
PW
Sewer
Collection
Manhole Inspection Inspections are going well. Lines are showing
much less clear water in lines. This would
correlate directly with homeowners in lower
areas not needing to use sump pumps.
New/
Ongoing
PW
Sewer
Collection
Emergency
Call-Outs
Duty phone employees responded to three
emergency call outs for the month (lift station
alarms).
Ongoing/
Updated
PW
Sewer
Collection
Sewer Main Flushing Continue to flush slow-moving sewer mains. Ongoing/
Updated
PW
Sewer
Collection
Private Line
Connection Inspections
Cleaned and camera sewer line for possible
sewer tap for lot at corner of Hemlock & Louisa.
With building picking up, more requests like this
have been coming in.
New
PW
Sewer
Collection
Routine Lift Station
Maintenance
Crews perform routine system checks at every
lift station twice a week.
Ongoing
PW
Sewer
Collection
New Sewer
Connections
Two new sewer connections for the month. New/
Ongoing
PW
Sewer
Treatment
PLWSD-J-Ditch The district replaced the PLC card for the 60
horse pump at the winter storage pond, thinking
it was for the additional pumping into the J-
Ditch line. This pump is plumbed for sending
effluent back into treatment pond #3, for
additional treatment should any issue arise as to
the conditions in the winter storage pond.
New/
Completed
PW
Sewer
Treatment
Routine Maintenance Performing typical maintenance duties and water
testing.
Ongoing/
Updated
PW
Sewer
Treatment
J-Ditch/Winter Storage
Pond
The last week of June PLWSD began releasing
effluent into the J-Ditch line using pump #2.
Ongoing/
Updated
PW
Sewer
Treatment
Ground Maintenance Grounds maintenance completed. Completed
Consolidated Department Report
August 11, 2016
13 of 29
PW
Sewer
Treatment
450 Pump at Winter
Storage Pond
PLWSD has pump #1 under repair for replacing
water solenoid.
New
Completed
PW
Water
Distribution
Edgewater Circle Met with City Engineer and Horrock’s to go
over new line design.
New/ongoing
PW
Water
Distribution
Main Service Line
Repairs
Additional repairs required to the line on Broken
Rein as well as the line on Timm St.
Updated
PW
Water
Distribution
Dig Line Requests Responded to 66 dig line requests to mark both
water & sewer infrastructure.
New/Ongoin
g
PW
Water
Distribution
Boil Notices Two lines (3rd Street & Broken Rein) where the
water was turned off for repairs caused the water
pressure to drop below 20 PSI’s. Per DEQ when
this occurs, the city must advise all property
owners to boil their drinking water until water
samples can be analyzed. Notices were hung on
all door knobs prior to the main being shut
down, and once the work was complete, the line
was pressured up, water samples were taken and
sent to Analytical Lab for testing. The water
tests for both lines came back showing no
contaminations, and the notices were lifted.
New
PW
Water
Distribution
Emergency
Call-Ins
No emergency call in for water issues. Ongoing/
Updated
PW
Water
Distribution
New Water Services Three new water services for the month. Ongoing/
Updated
PW
Water
Distribution
Work Orders The crew responded to 25 work orders from
customers and two from Utility Billing.
Ongoing/
Updated
PW
Water
Distribution
Fire Hydrant Repairs Repaired two fire hydrants. New
PW
Water
Distribution
Pre Turn-off
Door Hangers
Crew hung 36 door hangers for Utility Billing. Updated
Consolidated Department Report
August 11, 2016
14 of 29
PW
Water
Distribution
MXUs 3 MXUs were replaced this month. Updated
PW
Water
Distribution
ECRs 0 ECRs were replaced this month. Updated
PW
Water
Treatment
Eastside Water Tank In the past, the water treatment plant would draw
down the level in the eastside tank by only one
foot and pulled the additional needed water from
the wet well during the backwash process. When
SPF reviewed the system earlier in the month, a
recommendation was made that PW should be
pulling all the water off the tank and nothing
from the wet well. The new process has been
utilized with major benefits.
New/Comple
ted
PW
Water
Treatment
Davis Beach Intake
Pumps
Have begun pulling the raw water from the
Davis Beach facility, with Legacy set as the
secondary source. This will continue until the
demand for irrigation water and summer home
usages concludes for the summer.
New/Ongoin
g
PW
Water
Treatment
Test Pilot Filter No work has been completed yet, as Eric from
SPF is waiting for the approved Task Order.
Hopefully this will get back on track in July.
Updated
PW
Water
Treatment
Effluent Flows Summer flows have begun and are now up from
running 1.5 million gallons per day to a
consistent out flow of over 2 million gallons per
day.
New/Ongoin
g
PW
Water
Treatment
Back Wash Activities Double backwash activities continue, with an
employee coming in at 5:00 am each day.
Updated
Library Upcoming Programs Please see the calendar for the Library’s
upcoming July programs included with this
report.
Ongoing
Library Statistics June statistics included in this report. Ongoing
Library Story Stop Every Wednesday, children ages 0-3, a crowded
but fun atmosphere for families.
Ongoing
Library Story Time Every Thursday 10:30-11:30 a.m. is reading and
art activities to aid childhood development. Ages
Ongoing
Consolidated Department Report
August 11, 2016
15 of 29
3-5 with an adult.
Library Building Expansion Committee members and Board members and the
Library Director are hard at work in anticipation
of the first visit with Library design professionals,
July 12-15. Work session with Council 30
minutes on July 14th.
(See attached postcard/flyer below)
Ongoing
Library Council Invited Council members are also invited to take part in
the public process and meet with the consultants:
• 5:00 pm July 13, BBQ at Lola Elliot’s
house
• 7:00 pm July 13, Community meeting at
library
• 9:00 am July 14, Focus Group at library
Soon
Library BRMES School Visit Meg, Casey and the school librarian Yvonne
Loper presented a skit and information to inspire
elementary aged children to sign up and pledge to
read all summer long. A smashing success.
Complete
Library Summer Reading
Programs
Independent readers started already; active
programs start next week under the theme
“Ready, Set, Read!” There will be 3 sessions
weekly, and all registration is full.
Ongoing
Library Noxious Weed
Presentation
Valley County gave an informative talk to show
different types of local noxious weeds and what
can be done about it. This inspired at least one
HOA to organize a work day in June in their
neighborhood to help eradicate knapweed.
Complete
Library ESL classes Free ESL classes Mondays for community
members to practice and learn more English.
Great class, taught by a volunteer.
Ongoing
Library Community Resource
Fair
Librarians attended to spread information about
library resources.
Complete
Library 3D printing June 17 Casey held another demo day for the 3D
printer, with outstanding attendance and some
very, very excited patrons who keep coming back
for more.
Ongoing
Consolidated Department Report
August 11, 2016
16 of 29
Library Kaleidoscope Programming librarians hosted a booth at
McCall’s annual arts festival for kids, decorating
“Zentangle” rocks in a peaceful, creative activity
that parents enjoyed too!
Complete
Library Tech Tuesdays Staff are available to help the public with their e-
readers any day, but Tech Tuesdays have been
designated as a special time for folks to bring in
their devices to assist them log into OverDrive,
the e-book application, or to print 3D items.
Tuesdays, 4-6 PM.
Ongoing
Library Chess Club & Board
Gamers
An all-ages Chess Club has expanded to include
other board games. Attendance low lately.
Ongoing
Library Grants for Digitizing
Local History Records
Scanning continues with volunteers through 1/6
of the subject files.
Ongoing
Library Summer Hire Sarah Wright, high school student, hired again as
the temporary Library Page to help with the
summer crunch.
Complete
Consolidated Department Report
August 11, 2016
17 of 29
$20,281$6,024$16,429$1,903$1,062$0$34,870$29,713$18,526$21,884$26,242$13,147$22,387$7,241$4,840$1,638$1,925$8,025$27,946$29,861$34,038$11,627$35,111$12,689$15,403$6,874$1,332$39$3,963$15,906$22,726$30,202$40,421$34,419$10,523$32,419$14,734$1,352$3,668$5,729$10,532$12,071$50,469$27,461$40,560$35,463$23,316$51,797$13,953$2,623$3,553$1,469$15,317$35,705$38,367$66,275$52,029$23,553$34,042$28,993$5,205$10,882$1,476$22,638$23,008$39,518$48,668$50,606$62,108$38,661$0$0$0$10,000$20,000$30,000$40,000$50,000$60,000$70,000123456789101112BLDG PERMIT FEE + APPLICATION/PLANS CHECK FEE = TOTAL PERMIT FEESTOTAL BLDG PERMIT FEES ‐PER MONTH ‐FISCAL YEAR201120122013201420152016OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP
Consolidated Department Report
August 11, 2016
18 of 29
1234567891011122011$20,281 $26,305 $42,734 $44,637 $45,699 $45,699 $80,569 $110,282 $128,807 $150,691 $176,933 $190,0802012$22,387 $29,628 $34,468 $36,107 $38,032 $46,057 $74,004 $103,865 $137,903 $149,529 $184,640 $197,3292013$15,403 $22,277 $23,610 $23,649 $27,611 $43,517 $66,244 $96,446 $136,867 $171,286 $181,809 $214,2282014$14,734 $16,086 $19,754 $25,482 $36,014 $48,085 $98,554 $126,015 $166,575 $202,038 $225,354 $277,1502015$13,953 $16,575 $20,129 $21,598 $36,915 $72,620 $110,987 $177,263 $229,291 $252,844 $286,885 $315,8792016$5,205 $16,087 $17,563 $40,201 $63,209 $102,727 $151,395 $202,001 $264,109 $302,770 $302,770 $302,770$0$50,000$100,000$150,000$200,000$250,000$300,000$350,000BLDG PERMIT FEE + APPLICATION/PLANS CHECK FEE = TOTAL PERMIT FEESBLDG PERMIT FEES ‐RUNNING TOTAL ‐FISCAL YEAROCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPFY 2016 BUDGET $264,000 Consolidated Department Report
August 11, 2016
19 of 29
Streets LOT Actual Dollars Earned per Month
Month FY06 Totals
October ‐
November ‐
December ‐
January 99,990$
February 100,890$
March 85,253$
April 70,337$
May 97,416$
June 166,185$
July
August
September
Total Dollars Received $620,071
Difference compared to prior year
Budgeted Dollars $700,000
Contingent Budgeted dollars
2nd Contingent Budgeted Dollars
Total Budgeted
Consolidated Department Report
August 11, 2016
20 of 29
STREETS LOT BUDGETED, ACTUAL, AND FORECASTED DOLLARSMonthTourism LOT Five year average percentageFY16 Budget dollarsFY16 actual and forecast based on trendPercentage +/‐ based on budgetActual total Budget total total +/‐ YTDOctober4.51%November2.51%December5.83%1st Quarter TotalJanuary6.91%55,313 99,990 80.77% 99,990 55,313 80.77%February7.44%59,481 100,890 69.62% 200,880 114,793 74.99%March5.77%46,135 85,253 84.79% 286,133 160,928 77.80%2nd Quarter Total 160,928 286,133 77.80%April2.56%20,494 70,337 243.21% 356,470 181,422 96.49%May4.02%32,169 97,416 202.82% 453,886 213,591 112.50%June10.30%82,423 166,185 101.62% 620,071 296,014 109.47%3rd Quarter Total 135,086 333,938 147.20%July20.00%160,017 264,526 65.31%884,597 456,031 93.98%August18.42%147,396 243,662 65.31%1,128,259 603,427 86.98%September11.72%93,759 154,995 65.31%1,283,254 697,186 84.06%4th Quarter Total 401,172 663,183 65.31%Total100.00%697,186 1,283,254 209.47%697,186 1,460,395 5-Aug-16Consolidated Department Report
August 11, 2016
21 of 29
30,000 40,000 50,000 60,000 70,000 80,000 LOT FiveYear Average Compared to FY16 Actual October November December January February March April May June July August SeptemberAverage13,753 7,780 17,685 21,098 22,493 17,472 7,882 12,550 31,860 60,575 55,946 36,163 Budget15,773 8,774 20,372 24,166 25,987 20,156 8,954 14,055 36,011 69,911 64,397 40,963FY15 Actual22,085 12,986 31,168 31,157 32,613 23,699 15,255 22,047 50,183 ‐ ‐ ‐Forecast75,000 75,000 56,603‐10,000 20,000 AverageBudgetFY15 ActualForecastConsolidated Department Report
August 11, 2016
22 of 29
70,00080,000 Five Year Actuals Comparison to Average60,000 70,000 50,000 30 00040,000 20,000 30,000 10,000 ‐October November December January February March April May June July August SeptemberAveragesFY11FY12FY13FY14FY15FY 16ForecastConsolidated Department Report
August 11, 2016
23 of 29
MonthFY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 TotalsOctober14,274 16,938 14,412 11,306 10,483 11,520 12,392 12,163 13,390 19,298 22,085 136,176November11,272 9,748 7,978 7,147 5,850 5,535 6,103 7,298 8,233 11,738 12,986 80,902December18,547 21,746 22,261 16,224 14,294 15,459 13,939 19,101 18,122 21,802 31,168 181,495January17,232 18,707 20,163 17,932 17,007 17,510 17,065 19,334 24,733 26,778 31,157 196,461February20,446 22,943 27,324 24,826 18,873 19,921 19,716 22,331 22,013 28,487 32,613 226,880March15,110 13,668 21,527 15,969 8,925 11,941 17,344 20,251 19,365 18,422 23,699 162,523April7,294 8,049 6,425 5,954 6,183 6,210 6,696 6,165 8,719 11,641 15,255 73,336May11,994 11,230 9,368 8,595 7,335 8,074 9,461 11,113 15,390 18,711 22,047 111,271June23,442 24,611 25,426 22,248 21,491 20,728 25,352 33,681 37,000 42,541 50,183 276,520July47,654 54,276 47,052 42,408 48,747 49,843 54,214 62,187 65,335 71,296543,012August44,024 52,948 41,089 32,480 39,398 44,505 48,919 57,546 64,959 63,598489,466September26,973 26,073 23,600 25,826 20,258 27,603 33,029 35,605 35,959 49,346304,272Total Dollars Received258,263 280,937 266,627 230,991 218,844 238,849 260,743 306,775 333,218 383,658 241,193 2,778,904LOT Actual Dollars Earned per MonthConsolidated Department Report
August 11, 2016
24 of 29
TOURISM LOT ACTUAL PERCENTAGES AND FORECASTED DOLLARSMonth FY11 FY12 FY13 FY14 FY15Five year averageFY16 Budget dollarsFY16 Budget + Contingent dollarsFY16 actual and forecast based on trendPercentage +/‐ based on budgetActual total Budget total total +/‐ YTDOctober 4.85% 4.70% 3.96% 4.02% 5.03%4.51%15,773 19,270 22,085 40.02% 22,085 15,773 40.02%November 2.33% 2.32% 2.38% 2.47% 3.06%2.51%8,774 10,720 12,986 48.00% 35,071 24,547 42.87%December 6.51% 5.29% 6.23% 5.44% 5.68%5.83%20,372 24,889 31,168 52.99% 66,239 44,919 47.46%1st Quarter Total 44,919 54,880 66,239 47.46%January 7.37% 6.48% 6.30% 7.44% 6.98%6.91%24,166 29,524 31,157 28.93% 97,396 69,086 40.98%February 8.38% 7.48% 7.28% 6.60% 7.43%7.44%25,987 31,749 32,613 25.50% 130,009 95,073 36.75%March5.03% 6.59% 6.60% 5.81% 4.80%5.77%20,156 24,626 23,712 17.64% 153,721 115,229 33.40%2nd Quarter Total 70,310 85,900 87,482 24.42%April2.61% 2.54% 2.01% 2.61% 3.03%2.56%8,954 10,939 15,255 70.38% 168,976 124,183 36.07%May3.40% 3.59% 3.62% 4.62% 4.88%4.02%14,055 17,171 22,047 56.87% 191,023 138,237 38.18%June8.72% 9.62% 10.98% 11.10% 11.09%10.30%36,011 43,995 50,183 39.36% 241,206 174,248 38.43%3rd Quarter Total 59,019 72,105 87,485 48.23%July20.98% 20.57% 20.27% 19.60% 18.58%20.00%69,911 85,413 75,000 7.28%316,206 244,159 29.51%August 18.73% 18.56% 18.76% 19.49% 16.58%18.42%64,397 78,676 75,000 16.46%391,206 308,557 26.79%September 11.09% 12.26% 11.61% 10.79% 12.86%11.72%40,963 50,046 56,603 38.18%447,809 349,520 28.12%4th Quarter Total 175,272 214,136 206,603 17.88%Total 100.00% 100.00% 100.00% 100.00% 100.00%100.00%349,520 427,020 447,809 138.43%349,520 427,020 483,841 Year to date the actual revenues received for FY16 are 20.92% OVER the year to date revenues for FY15 and 58.05% over the 5 year average year to date.5-Aug-16Consolidated Department Report
August 11, 2016
25 of 29
GRANT STATUS REPORT- July 14, 2016
Department Project Name Project
Manager
Purpose Funder Amount Status
Streets
Department
Mission St.
Reconstruction
TBD Reconstruct Mission St. from
Deinhard to S. City Limits
FHWA
through
LHTAC
$1.525 million Updated: public
comment period
has closed.
Streets
Department
TIGER 8 Nathan Stewart
Cris Malvich
Reconstruct downtown core;
streets, water, sewer, and
sidewalks
US DOT $5,843,239 No Change:
announcement to be
made in fall, 2016
Parks Mountain Bike
Skills Park
Kurt Wolf Design and construct skills
park on MDSD property
IDPR $11,994 Update: project
underway
Parks Riverfront Park
Access
Improvements
Kurt Wolf Improve road surface, parking,
and stormwater management
at Riverfront
IDPR $17,866 Update: project to
be completed in
August/September
Community
Development
Alpine
Playhouse Public
Art
Delta James Install public artwork near
Alpine Playhouse
Idaho
Commission
on the Arts
$10,000 Updated: project is
complete
Streets MRA sidewalks Nathan Stewart Sidewalks in MRA district Federal
Highways/ITD
$198,000 Project is complete.
Community
Development
Public Art
Project
Delta James Install public art in Rotary
Park
Idaho
Commission
on the Arts
$10,000 Updated: project is
underway and will
be completed this
year
Public
Works/Water
Water Master
Plan update
Peter Borner Update master Plan Dept. of
Environmental
Quality
$87,500
Revised amt:
$89,998
No Change: project
is underway.
Public
Works/Sewer
Groundwater
Study
Peter Borner Study leakage at wastewater
pond
Dept. of
Environmental
Quality
$77,000 No Change: project
is underway.
Streets
Department
Commerce Street
Reconstruction
Peter Borner Reconstruction of Commerce;
stormwater and sidewalks
Local Highway
Technical
Assistance
Council
$100,000 Project to occur in
2017
Consolidated Department Report August 11, 201626 of 29
McCall Public Library 208-634-5522 www.mccall.lili.org
Hours: Monday -Friday 10 -6pm; Saturday 10 -2pm; Sunday closed
Sun Mon Tue Wed Thu Fri Sat
31 1 2:00-3:30 Harry
Potter Release Party
4:30—6:00pm Clase
de Ingles
2
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
10:00—2:00 Summer
Reading Program
3
10:30-11:00 StoryStop
1:00-3:00 Summer Reading
Tweens
4
10:30-11:30 Story Time
5
6
7 8
4:30—6:00pm Clase
de Ingles
9
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
10:00—2:00 Summer
Reading Program
10
10:30-11:00 StoryStop
1:00-3:00 Summer Reading
Tweens
11
10:30-11:30 Story Time
12
13
14 15
4:30—6:00pm Clase
de Ingles
16
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
17
10:30-11:00 StoryStop
18
10:30-11:30 Story Time
19
20
.
21 22
4:30—6:00pm Clase
de Ingles
23
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
24
10:30-11:00 StoryStop
25
10:30-11:30 Story Time
26
3:30-5:30 Mak-
erspace
27
28 29
4:30—6:00pm Clase
de Ingles
30
4:00– 6:00 Board Games
4:00-5:30 Tech Tuesday
31
10:30-11:00 StoryStop
1
10:30-11:30 Story Time
2 3
1
Primary Business Address
Your Address Line 2
Your Address Line 3
Your Address Line 4
Your business tag line here.
Phone: 555-555-5555
Fax: 555-555-5555
E-mail: someone@example.com
August 2016 Programs
SPECIAL EVENTS:
Harry Potter Release Party
Monday, August 1 from 2:00-3:00pm
Come down and celebrate the release of the latest
addition to the Harry Potter saga by JK Rowling!
We will be celebrating with snacks, prizes, givea-
ways, and a giant game of Harry Potter trivia!
Clases de Inglés
Mondays 4:30-6:00pm
Free conversational English classes are available
every Monday August 1st - August 29th
McCall Library Summer Reading Program
Ready, Set, READ!
Summer Reading Programs start
July 12th—August 9th.
Morning session: 11:00-12:00
Afternoon session: 1:00-2:00
Registration is required
McCall Library Summer Reading Program
Tween Program
Thursday, June 9th
Summer Reading Programs start
July 13th—August 10th.
1:00-3:00pm
Registration is required
Makerspace
Friday, August 26th 3:30-5:30pm
3D printing, coding robots and so much more!
ONGOING PROGRAMS:
Chess Club ~ Tuesdays 4:00 pm – all ages, all levels.
Board Gaming ~ First Tuesdays 3:30 -5:30pm—Play Munchkin, Forbidden Island, Monopoly and more! all ages.
Story Stop ~ Wednesdays 10:30 – 11:00 am A streamlined library story time with rhymes & games for children
ages 0-3 (with adult).
Tech Tuesdays ~ Tuesdays— 4:00pm-5:30pm –Dedicated time for 3D printing, help with e-books, and overdrive.
Children’s Story Time ~ Thursdays 10:30 - 11:30 am Ages 3-5 (with adult). Preschool stories, art, and social
time. Consolidated Department Report August 11, 201627 of 29
Library Statistics -- FY2016
Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Totals
2 - 000-099 8 5 16 17 13 10 10 3 5 6
3 - 100-199 14 7 15 10 24 17 15 3 2 7
4 - 200-299 7 5 21 16 19 12 8 19 14 13
5 - 300-399 39 46 46 43 30 38 58 60 46 58
6 - 400-499 4 2 4 12 3 0 7 12 10 5
7 - 500-599 22 18 24 42 38 37 37 36 48 49
8 - 600-699 83 81 87 88 117 86 60 68 105 84
9 - 700-799 64 96 46 81 53 81 59 42 63 51
10 - 800-899 34 36 48 27 28 21 28 25 34 42
11 - 900-919.9 32 34 35 48 40 63 27 41 30 18
12 - 929-999 65 54 37 44 63 48 36 37 40 46
13 - Adult Fiction 699 682 692 760 665 809 671 666 764 866
14 - Audio Books Circ Set 0 28 32 45 24 69 21 17 26 28
16 - Biography 28 15 18 16 27 32 32 11 18 21
17 - Board Books 103 93 81 111 148 134 116 142 127 78
18 - CD Fiction Books 222 217 203 196 229 223 241 163 157 178
19 - CD Junior Books 70 39 33 41 51 105 54 23 63 63
20 - CD Music 10 0 0 0 0 0 0 0 0 0
21 - CD Non-Fiction Books 41 38 18 15 19 42 27 28 25 28
22 - CD YA Books 4 4 4 0 6 17 5 1 9 6
23 - Chapter books 138 109 99 126 159 169 139 134 309 278
24 - Classic Movies 5 7 7 18 15 15 9 11 15 24
27 - Dawn Moudy Collection 6 9 4 4 5 9 6 13 13 6
28 - DVD 14 13 7 7 9 4 8 3 0 0 0
29 - DVD Blu-Ray 16 10 29 13 8 12 6 19 12 8
30 - DVD Circ Set 67 104 47 16 11 29 41 19 51 52
31 - DVD Fiction 266 325 387 307 319 388 203 145 204 231
32- DVD Kids 10 13 20 15 26 25 89 166 165 183
33 - DVD Non-Fiction 52 35 53 28 36 51 17 48 23 21
34 - DVD TV Series 10 7 8 11 20 23 10 14 21 11
35 - E Non-Fiction 38 46 28 40 64 66 68 92 51 73
36 - Eames Collection 6 6 5 1 1 8 2 3 0 3
37 - Early Readers 153 112 151 143 164 128 112 110 235 191
38 - Idaho Archives 1 0 2 2 0 0 0 0 0 2
39 - Idaho Room 36 26 25 48 60 99 44 65 57 70
40 - Independent Films 5 5 19 10 19 19 9 1 6 10
41 - Junior Biography 21 37 23 28 19 29 16 16 12 10
42 - Junior Non-Fiction 356 337 300 273 412 463 328 238 306 353
43 - Junior Readers 263 285 235 189 237 263 295 288 494 498
44 - Junior Spanish 26 29 49 21 36 37 52 15 14 13
45 - Kit 1 2 6 6 12 7 1 5 3 9
46 - Language learning 2 0 0 2 2 0 0 0 0 3
47 - Large Print 104 67 116 133 100 128 129 168 172 157
48 - LP Circ Set 17 18 0 1 0 0 0 0 2 5
49 - Magazine 45 28 28 54 33 42 50 51 69 60
50 - Map 0 1 0 0 0 0 1 0 0 0
51 - Oversized 1 4 4 0 1 7 4 5 4 4
52 - Parenting 2 0 0 3 1 0 3 0 2 2
53 - Professional 6 0 2 0 0 0 1 3 0 0
54 - Reference 2 4 1 1 1 2 2 1 1 1
55 - Spanish 10 10 17 11 13 14 5 1 4 2
56 - Story Books 751 624 699 595 821 875 708 620 774 740
57 - Story Collection 24 20 21 9 22 11 12 22 26 29
58 - Y A Non-Fiction 33 12 28 15 26 26 15 6 12 17
59 - YA Biography 0 0 0 0 0 0 0 0 0 0
Consolidated Department Report
August 11, 2016
28 of 29
60 - Young Adult Fiction 84 78 89 91 61 70 75 72 145 207
61 - Yount Adult Story Collection 0 0 0 0 0 0 0 0 0 0
Adult Circulation 2068 2057 2124 2141 2063 2453 1894 1821 2069 2201
Young Adult Circulation 121 94 121 106 93 113 95 79 166 230
Children's Circulation 1930 1726 1724 1583 2149 2301 1978 1849 2553 2489
Circulation Totals 4142 3914 3992 3859 4334 4892 4002 3776 4816 4956
Attendance 2351 2132 2032 2126 2286 2445 2194 2418 2695 3578
Computer Usage 630 510 459 495 320 546 502 533 624 908
ILL's Received 23 37 23 25 28 25 35 27 28 36
Reference Requests 509 439 398 412 395 452 373 411 478 612
Food for Fines 33 11 28 20 130 84 31 22 79 22
Volunteers/hrs 9/15 5/8 6/27 2/7 3/5 17/44 6/12 14/25 14/34 20/45
Adult Program Attendence 138 174 77 180 92 60 54 84 40 28
Young Adult Program Attendence 9 6 23 6 2 9 14 8 5 62
Children's Program Attendence 670 483 551 587 477 740 546 578 507 466
Consolidated Department Report
August 11, 2016
29 of 29