A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TEMPLE CITY APPROVING A LIST OF PROJECTS FOR FISCAL YEAR
2020-21 TO BE FUNDED BY THE ROAD REPAIR AND ACCOUNTABILITY
ACT OF 2017 (SB 1)
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5,
Statutes of 2017) was passed by the Legislature and signed into law by the Governor in April 2017 to
address the significant multi -modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the
residents of Temple City are aware of the projects proposed for funding and which projects have been
completed each fiscal year; and
WHEREAS, Temple City must adopt by City Council resolution a list of all projects proposed to
receive funding from the Road Maintenance and Rehabilitation Account (RMRA) created by SB 1, which
must include a description and the location of each proposed project, a proposed schedule for the
projects' completion, and the estimated useful life of each improvement; and
WHEREAS, Temple City will receive an estimated $ 608,000 in RMRA funding in Fiscal Year
2019-20 from SB 1: and
WHEREAS, this is the third year in which Temple City is receiving SB 1 funding and will enable
the City to continue essential road maintenance and rehabilitation projects, safety improvements,
repairing and replacing aging bridges, and increasing access and mobility options for the traveling public
that would not have otherwise been possible without SB 1; and
WHEREAS, Temple City has undergone a public process to ensure public input into the
community's transportation priorities; and
WHEREAS, Temple City used a Pavement Management System to develop the SB 1 project list
to ensure funds are being used on the most high- priority and cost-effective projects that also meet the
community's priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help Temple City maintain and rehabilitate multiple streets
throughout the city this year and many similar projects into the future; and
WHEREAS, the 2016 California Statewide Local Streets and Roads Needs Assessment found
that Temple City's streets and roads are in an " at -risk" condition and this funding will help increase the
overall quality of the City's street system and over the next decade will improve the condition of the
streets; and
WHEREAS, the SB 1 project list and overall investment in local streets and roads infrastructure
with a focus on basic maintenance and safety; investing in complete streets infrastructure; and using
cutting- edge technology, materials, and practices will have significant positive co -benefits statewide.
NOW, THEREFORE, the City Council of the City of Temple City does hereby resolve, find,
determine, and order as follows:
SECTION 1. The foregoing recitals are true and correct.
SECTION A. The following projects are planned to be funded with RMRA funds for Fiscal Year 2020-21
Resolution N0, 20-5472
Page 2 of 3
Title:
Las Tunas Drive Resurfacing
Description:
carried over from FY 2019-20
Description:
Grind and overla resurfacin of about 2 miles of ma'or
arterial street
From
Las Tunas Drive from wester City boundary at Muscatel Avenue to
Location:
eastern City boundary east of Rowland Avenue
Estimated Useful Life:
Minimum 10 years, maximum 20 years
Anticipated Completion
Pre -construction 06/2020; construction 10/2020
Dates:
Kauffman Ave
Garibaldi Ave
$2,000,000
Estimated Cost:
Longden Ave
Title:
Street Resurfacing Phase 5A
carried over from FY 2018-19 and 2019-20
Description:
Resurfacing of about 3 miles of collector and local streets with slurry
seal or asphalt overlay as appropriate for pavement management
condition
Location:
Various Residential Streets throughout the City
Street
From
To
Alessandro Ave
Las Tunas Dr
Garibaldi Ave
Golden West Ave
Las Tunas Dr
Longden Ave
Kauffman Ave
Garibaldi Ave
Longden Ave
Lemon Ave (N/S)
Longden Ave
Northern City Limit
Lemon Ave (E/W)
Temple City Blvd
Eastern City Limit
Livia Ave
Longden Ave
Woolle St
Longden Ave
Oak Ave
Eastern City Limit
Noel Dr
Broadway
North End
Primrose Ave
Garibaldi Ave
Flaherty St
Rowland Ave
Flaherty St
Wendon Ave
Trelawny Ave
South End
Lemon Ave
Workman Ave
Alley E/O TC Blvd
Camellia Ave
Workman Ave
Oak Ave
Cloverly Ave
Estimated Useful Life:
Slurry seal: minimum 5 years, maximum 7 years
Overlay: minimum 10 years, maximum 20 years
Anticipated Completion
Dates:
Pre -construction 06/2020; construction 10/2020
Estimated Cost:
$7102000
Title:
Street Resurfacing Phase 6A
Description:
Resurfacing various residential streets according to 2020 updated
Pavement Management Plan
Location:
Various Residential Streets throughout the City
Estimated Useful Life:
Slurry seal: minimum 5 years, maximum 7 years
Overlay: minimum 10 years, maximum 20 years
Resolution N0, 20-5472
Page 3 of 3
Anticipated Completion
Dates:
Pre -construction 06/2020; construction 10/2020
Estimated Cost:
$750,000
SECTION
3. The City Clerk
shall certify
to the passage and adoption of this Resolution and it shall
thereupon
take effect.
PASSED, APPROVED AND ADOPTED on this 5 h day of May, 2020.
ATTEST:
N
Peggy Kuo, City Clerk
I hereby certify that the foregoing resolution, Resolution No. 20-5472, was duly passed, approved
and adopted by the City Council of the City of Temple City at a regular meeting held on the 5'^ day of
May, 2020 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
Councilmember- Man, Stern quist, Yu, Chavez
Councilmember- None
Councilmember- None
Councilmember- None
Peggy Kuo, City Clerk