Loading...
HomeMy Public PortalAbout07) 7F- Staff Report_LAS TUNAS REHAB PHASE 2 SULTANA TO BALDWIN 7-21-2020AGENDA ITEM 7.F. COMMUNITY DEVELOPMENT DEPARTMENT MEMORANDUM DATE: July 21, 2020 TO: The Honorable City Council FROM: Bryan Cook, City Manager By: Ali Cayir, PE, City Engineer Okan Demirci, Project Manager SUBJECT: APPROVAL OF PLANS AND AUTHORIZATION TO INVITE BIDS FOR THE LAS TUNAS DRIVE PAVEMENT REHABILITATION PHASE 2 FROM SULTANA AVENUE TO EAST CITY LIMIT (WEST OF BALDWIN AVENUE), CIP NO. P20-07 RECOMMENDATION: The City Council is requested to approve plans (Attachment “A”) for the Las Tunas Drive Pavement Rehabilitation Phase 2 from Sultana Avenue to Baldwin Avenue, and authorize staff to advertise the project for bids. BACKGROUND: 1. On April 2, 2019, City Council approved the City’s updated Pavement Management Program (PMP). Las Tunas Drive from west city limit to from Sultana Avenue to east city limit (west of Baldwin Avenue) is identified for pavement rehabilitation in City’s updated PMP. 2. In May, 2020, Las Tunas Avenue rehabilitation Phase 1 from west city limit to Sultana Avenue was completed. ANALYSIS: The rehabilitation work in Phase 2 will involve cold-milling of existing asphalt up to 3”, and installing a new asphalt base course up to 1” and asphalt wearing course up to 2” with localized dig-out at areas as necessary per field conditions. This rehabilitation method is developed based on field reviews and engineering evaluations as the structurally and economically optimum approach to improve the pavement conditions. The estimated budget for the project is in the range of $2.3 million, which includes hard construction costs and budget allocation for localized area reconstruction based on field City Council July 21, 2020 Page 2 of 2 conditions, industry standard 10% for construction contingency allowance, and 20% for soft costs budget allowance (Attachment “B”). The work will be performed at night-time to minimize impacts to adjacent businesses and traffic flow along Las Tunas Drive. The estimated duration of night work is approximately 5 weeks. With the approval of the bid package and Notice Inviting Bid (NIB) distribution, staff will advertise the project for bids. It is anticipated the bid advertisement will be approximately 1 month. After the bids are opened, staff will conduct a bid analysis, and recommend to City Council award of the contract to the lowest responsible bidder. The proposed project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA) pursuant to 14 California Code of Regulations § 15301 as a Class 1 categorical exemption (Existing Facilities). CITY STRATEGIC GOALS: Approval of the bid package and NIB distribution will further City Strategic Goals of Public Health and Safety, Quality of Life, and Sustainable Infrastructure. FISCAL IMPACT: Engineer’s project cost estimate for Phase 2 of the Las Tunas Dr Pavement Rehabilitation is approximately $2.3 million. Project funding is included in the approved FY 2020-2021 Capital Improvement Program, which appropriated a total of $4.6 million for the project. At the bid award, staff will be seeking Council authorization for any allocation of funds. ATTACHMENTS: A.Project Plan B.Project Cost Estimate Document Control: D:\Dropbox (Transtech Engineers)\JOBRECRD\2018\18328 TC ROSEMEAD BL RESURFACING\WIP\3 BID PACKAGE\0 FRONT SPECS, TC, ROSEMEAD BLVD RESURFACING.docx CITY OF TEMPLE CITY, CALIFORNIA BIDDING AND CONTRACT DOCUMENTS, PLANS AND SPECIFICATIONS for LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-07 Date Issued: July xx, 2020 Bid Due Date: August xx, 2020, 2:00 PM Submit bids to: Office of the City Clerk City of TEMPLE CITY 9701 Las Tunas Drive, TEMPLE CITY, CA 91780 CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 1 of 63 ATTACHMENT A TABLE OF CONTENTS DESCRIPTION SECTION NOTICE INVITING SEALED BIDS A INSTRUCTIONS TO BIDDERS B BIDDER’S PROPOSAL (Entire section C shall be submitted with the bid) C GENERAL PROVISIONS D SPECIAL PROVISIONS E BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” APPENDICES: APPENDIX A - SAMPLE CONTRACT TO BE EXECUTED APPENDIX B - PROJECT PLANS CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 2 of 63 Page: A.1 A.NOTICE INVITING FORMAL SEALED BIDS LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-07 City of Temple City PUBLIC NOTICE IS HEREBY GIVEN that the City of Temple City invites sealed bids for the above stated project and will receive such bids in the office of the City Clerk, City of Temple City, 9701 Las Tunas Drive, Temple City, CA 91780, up to the hour of 2:00 PM on August xx, 2020. The bids received will be publicly opened approximately 15 minutes after the bid submittal deadline in the City Hall. This Notice Inviting Formal Sealed Bids will be advertised in a newspaper of general circulation, printed and published in the jurisdiction of the City of Temple City at least fourteen (14) calendar days before the bid opening date. Pre-Bid Meeting: There is no pre-bid meeting for this project. Bidding and Contract Documents, Plans and Specifications Available: Copies of the Bidding and Contract Documents, Plans and Specifications can be obtained as follows: 1.Please e-mail your request with your contact information to: okan.demirci@transtech.org. Upon receipt of your e-mail, you will be registered as a plan holder, and a pdf file of the Bidding and Contract Documents, Plans and Specifications will be e-mailed to you at no cost. 2.Hard copy of the Bidding and Contract Documents, Plans and Specifications can be picked up at a non-refundable cost of $100 from City of Temple City, 9701 Las Tunas Drive, Temple City, CA 91780. Please first e-mail to okan.demirci@transtech.org and request a hard copy 2 days in advance. Make check payable to “City of TEMPLE CITY”. Place a note on the check as follows: Cost for Plan Set for CITY PROJECT ID: P20- xx. 3.Hard copies will not be mailed. Pre-Bid Inquiries: All questions regarding this bid shall be directed via email, no later than 7 calendar days prior to the Bid due date and time, to Okan Demirci, PE, Project Manager at okan.demirci@transtech.org. Any questions received after this deadline will not be answered. It is the responsibility of the bidder to confirm transmission of correspondence. Scope of Work: The work consists of furnishing all materials, equipment, tools, labor, and incidentals as described in detail in the Bidding and Contract Documents, Plans and Specifications to construct the project. Major work components include coldmill and overlay of LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2, FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) and other improvements as shown in BIDDING AND CONTRACT DOCUMENTS, PLANS AND SPECIFICATIONS. Location of Work: Locations of work is shown on Appendix B-Project Plan. Estimated Cost of Work: Estimated cost is $1.800,000. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 3 of 63 Page: A.2 Retention: The City will deduct a State-mandated 5 percent retention from all progress payments. Project Completion: The project shall be completed per the schedule specified in Section “B. INSTRUCTIONS TO BIDDERS”, Subsection “CONSTRUCTION SCHEDULE, PROGRESS OF WORK, LIQUIDATED DAMAGES”. Bid Bond: Bids must be accompanied by a bid bond, made payable to the City of TEMPLE CITY for an amount no less than ten percent (10%) of the bid amount. Required License Classification: Required License Classification is State of California, A-General Engineering Contractor. No bid will be accepted from a Contractor who has not been licensed in accordance with the provisions of the Business and Professions Code. SB 854 Requirements This project is subject to the requirements of SB 854. No prime contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. No prime contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. The bid proposal must include a print out from the DIR registration website showing that the prime contractor and each subcontractor is currently registered. No bid proposals will be accepted nor any contract entered into with a prime contractor without proof of registration as required above. [Unless within the limited exceptions from this requirement for bid proposals only under Labor Code Section 1771.1(a)]. The prime contractor will be required to post job site notices regarding Labor Code compliance as described in 8 California Code of Regulation section 16451(d). Prevailing Wages Required: Prevailing wages shall be paid to all workers in accordance with California Labor Code 1771. A copy of the prevailing wages schedule is on file with the City. Federal Funds: There are no Federal Funds utilized for this project. DBE: There is no mandatory DBE Participation requirement. All bidders are required to comply with all applicable competitive bidding and labor compliance laws including, but not limited to, active solicitation of subcontract bids from minority-owned businesses, women-owned businesses, and businesses owned by disabled veterans. The City hereby notifies all qualified bidders that it will affirmatively insure that qualified minority business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the basis of race, color, national origin, ancestry, sex, religion, or handicap in consideration for an award. Attention is directed to the provisions of Section 1777.5 (Chapter 1411, Statutes of 1968) and 1777.5 of the Labor CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 4 of 63 Page: A.3 Code concerning the employment of apprentices by the Contractor’s or any such subcontractors under hire. The bidders and the selected Contractor shall not allow discrimination in employment practices on the basis of race, color, national origin, ancestry, sex, religion, or handicap. Bonds Required: A labor and materials payment bond is required in accordance with California Civil Code 9550 in a form approved by the City. Also a performance bonds and public improvement warranty are required. See Sample Contract for the required bond forms. Substitution of Securities for Retention: The contractor may deposit securities in lieu of the 5% progress payment retentions in accordance with California Public Contracts Code 22300. Excavation Safety: If the work involves an excavation or trench five feet or deeper, the bid must contain a separate bid item for adequate sheeting, shoring, bracing and safety measures approved by the City. City Business License: The successful Contractor and his subcontractors will be required to possess business licenses from the City. In entering into a public works contract, or a subcontract, to supply goods, services, or materials pursuant to a public works contract, the Contractor, or subcontractors, offers and agrees to assign to the awarding body all rights, title and interest in, and to, all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Section 15) or under the Cartwright Act (Chapter 2 [commencing with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public work’s contract or subcontract. This assignment shall be made and become effective at the time the awarding body tenders final payment to the Contractor, without further acknowledgment by the parties. Bids must be prepared on the approved Proposal forms in conformance with the Instructions to Bidders and submitted in a sealed envelope plainly marked on the outside. Bids must be accompanied by a bid bond, made payable to the City of Temple City for an amount no less than 10 percent of the amount of bid. The City reserves the right to reject any or all bids, to waive any irregularity, and to take all bids under advisement for a period of 60 calendar days. Any contract entered into pursuant to this notice shall become effective or enforceable against the City of TEMPLE CITY only when the formal written contract has been duly executed by the appropriate officers of the City. Submittal of your bid assumes that you have made a thorough and complete investigation of the project site and that you have discovered no apparent discrepancies between the scope of work set forth in the plans and specifications and the actual field conditions. If there are any questions regarding this project, please contact in writing via e-mail: Okan Demirci, PE CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 5 of 63 Page: A.4 okan.demirci@transtech.org All inquiries must be submitted in writing. BY ORDER of the City of Temple City, California. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 6 of 63 Page: B.1 B.INSTRUCTIONS TO BIDDERS LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-07 City of Temple City LOCATION OF WORK The exact location of the project is outlined in the drawings, specifications and other Contract Documents on file at the office of the City Clerk of the City of Temple City. See Appendix B for Project Plan. PROPOSAL FORMS Bids shall be submitted in writing on the Proposal forms provided by the City. All information requested therein must be clearly and legibly set forth in the manner and form indicated. The City will not consider any proposal not meeting these requirements. PROPOSAL GUARANTEE Proposals must be accompanied by a proposal guarantee consisting of a bid bond payable to the City of Temple City in the amount not less than 10 percent of the total amount of bid. Any proposal not accompanied by such a guarantee will not be considered. If a bidder to whom a contract is awarded fails or refuses to execute the contract documents or furnish the required insurance policies and bonds as set forth in those documents, the proposal guarantee shall be forfeited to the City. The proposal guarantees of all bidders will be held until the successful bidder has properly executed all contract documents. DELIVERY OF PROPOSAL Proposals shall be enclosed in a sealed envelope plainly marked on the outside: LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P20-XX City of Temple City DO NOT OPEN WITH REGULAR MAIL Proposals may be mailed or delivered by messenger. However, it is the bidder’s responsibility alone to ensure delivery of the proposal to the hands of the City’s designated official prior to the bid opening hour stipulated in the Notice Inviting Bids. Late proposals will not be considered. CONSTRUCTION SCHEDULE, PROGRESS OF WORK, LIQUIDATED DAMAGES In accordance with the Standard Specifications, and/or as may be provided for within the herein Special Provisions, after notification of award and prior to start of any work, the Contractor shall submit to the Engineer for approval its proposed Construction Schedule. At a scheduled date prior to commencement of work, the Contractor and all subcontractors shall attend a pre-construction conference at the City Hall. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 7 of 63 Page: B.2 The project shall be completed per the following schedule: Task No Description Date Step 1.City Task Contract award by the City Council. Date 1 (= September xx, 2020) Step 2.City Task City will send out Contract to Contractor for signatures. Date 2 = Date 1 + 2 working days (= September xx, 2020) Step 3.Contractor Task Contractor shall return signed Contract with required bonds and insurances to City. Date 3 = Date 2 + 5 working days (= September xx, 2020) Step 4. City Task City will counter sign the Contract and provide a fully executed Contract to Contractor. Date 4 = Date 3 + 2 working days (= September xx, 2020) Step 5. Joint Task A Pre-construction meeting will be held. Contractor shall submit its project schedule to the City at the Pre-construction meeting, with project start date established based on Date 6 shown in Task 6. Date 5 = Date 4 + 1 working day (= September xx, 2020) Step 6. City Task City will issue to the Contractor NTP (Notice to Proceed) to commence with the project construction. Date 6 = Effective Date of for the start of construction (= September xx, 2020) Step 7. Contractor Task Contractor shall complete field construction within 30 working days (which includes 10 working night time-counted as work days- for coldmill and overlay; and 2 working night time-counted as work days- for striping cat-tracking and 3 working night time-counted as work days- for final striping. Date 7A = Date 6 + specified duration. Note: If and Contactor tasks and the work described in this schedule are not completed by the contractor within the required durations, City will assess $1,000 per calendar day as liquidated damages. All durations above related to Contractor tasks shall remain the same regardless of City’s completion of City tasks. The Contractor agrees that failure to complete work within the time allowed will result in damages being sustained by the City. Contractor and City agree that failure to complete the project will result in inconvenience to the citizens of the City. The parties also agree that failure to complete the project on time will prevent the City from having the use of the affected facilities. Therefore, the parties agree such damages among others are, and will continue to be, impracticable and extremely difficult to determine, but that One Thousand Dollars ($1,000) a calendar day is the minimum value of such costs to the City and is a reasonable amount that the Contractor agrees to reimburse the City for each calendar day of delay in finishing the work in excess of the time specified for completion, plus any authorized time extensions. Execution of the contract under these specifications shall constitute agreement by the Contractor and the City that the above indicated liquidated damage amount per calendar day is the minimum value of the costs and actual damage caused by failure of the Contractor to complete the work within the allotted time, that such sum is liquidated damages and shall not be construed as a penalty, and that such sum may be deducted from payments due the Contractor if such delay occurs. Said amount may be reduced by the City if work is sufficiently completed within the/an allotted time so that the damages are minimized. All construction graffiti shall be removed prior to the release of retention payment. WITHDRAWAL OF PROPOSALS A proposal may be withdrawn by a written request signed by the bidder. Such requests must be delivered to the City’s designated official prior to the bid opening hour stipulated in the Notice Inviting Bids. Proposals CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 8 of 63 Page: B.3 may not be withdrawn after the bid opening hour stipulated in the Notice Inviting Bids without forfeiture of the proposal guarantee. The withdrawal of a proposal will not prejudice the right of the bidder to submit a new proposal, providing there is time to do so. IRREGULAR PROPOSALS Unauthorized conditions, limitations, or provisions attached to a proposal will render it irregular and may cause its rejection. The completed proposal forms shall be without interlineations, alterations, or erasures. Alternative proposals will not be considered unless specifically requested. No oral, telegraphic, or telephonic proposal, modification, or withdrawal will be considered. TAXES No mention shall be made in the proposal of Sales Tax, Use Tax, or any other tax, as all amounts bid will be deemed and held to include any such taxes which may be applicable. DISQUALIFICATION OF BIDDERS In the event that any bidder acting as a prime contractor has an interest in more than one proposal, all such proposals will be rejected, and the bidder will be disqualified. This restriction does not apply to subcontractors or suppliers who may submit quotations to more than one bidder, and while doing so, may also submit a formal proposal as a prime contractor. No proposal will be accepted from a bidder who has not been licensed in accordance with the provisions of the State Business and Professions Code. DISCREPANCIES AND MISUNDERSTANDINGS Before submitting a Proposal, Bidders must satisfy themselves by personal examination of the work site, Plans, Specifications, and other contract documents, and by any other means as they may believe necessary, as to the actual physical conditions, requirements and difficulties under which the work must be performed, and shall include in the Proposal, the cost of all items necessary in the construction of the project. The Bidder shall not be allowed any extra compensation by reason of any matter or thing, concerning that which such the Bidder might have fully informed himself prior to the bidding. No bidder shall at any time after submission of a proposal make any claim or assertion that there was any misunderstanding or lack of information regarding the nature or amount of work necessary for the satisfactory completion of the job. Any errors, omissions, or discrepancies found in the Plans, Specifications, or other contract documents shall be called to the attention of the City. Should a Bidder find any ambiguity, inconsistency or error in the plans and project manual, or be in doubt as to their meaning, the Bidder shall notify the City, in writing via e-mail as specified in the Notice of Inviting Bids Section. Issues requiring clarification will be addressed in a written addendum response, sent by facsimile to each Bidder, person or firm recorded by the City as having received plans. Any addenda issued by the City during the time of bidding are to be included in the proposal from the Bidder, and shall become a part of the Bid documents. The Bidder shall acknowledge receipt of addenda on the proposal form in the space provided. By submitting a bid, the Bidder shall be held to have personally examined the site and the drawings, to have carefully read the specifications, and to have satisfied itself as to its ability to meet all the difficulties attending the execution of the proposed contract before the delivery of this proposal, and agrees that if CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 9 of 63 Page: B.4 awarded the contract, will make no claim against the City based on ignorance or misunderstanding of the plans, specifications, site conditions and/or contract provisions. PERMITS AND LICENSES The Contractor shall procure all permits and licenses, pay all charges and fees, and give all notices necessary and incidental to the due and lawful prosecution of the work. No fee is charged for the Permit issued by the City for a public works project. The Contractor shall pay for and obtain a City Business License. CONTRACTORS LICENSE LAW The successful Bidder shall comply with and require all subcontractors to comply with all Federal, State and City Contractor License Laws and be dully registered and licensed thereunder as required. The successful Bidder is required to provide and pay for a performance and a payment bond. These bonds shall cover the faithful performance (100%) of the Contract for Construction and the payment of all obligations (100%) arising thereunder, in such form as the City may prescribe and with such sureties as they may approve. The successful Bidder shall require the attorney in fact who executes the required bonds on behalf of the surety to affix thereto a certified and current copy of his Power of Attorney indicating the monetary limit of such power. The City reserves the right to reject any proposed bonding company without stating cause. In this event the successful Bidder shall provide an alternate bonding company selection acceptable to the City. Bonds shall conform to state statutes regarding performance bond and labor and material payment bond with amount shown on each part equal to 100% of the total amount payable by terms of the Contract for Construction. The surety company shall be licensed to do business in state in which construction project is located and shall be acceptable to the City. Bond amount shall be increased to include any Change Order(s) added to the contract to 100% total value amount of each Change Order. Bonds will be recorded along with a copy of the construction contract in the County Recorder Records by the General Contractor with written proof submitted to the City. LIABILITY INSURANCE The liability insurance coverage values shall be: 1.Public Liability and Property Damage Insurance in an amount of not less than ONE MILLION DOLLARS ($1,000,000); 2.Products/Completed Operations Hazard Insurance in an amount of no less than ONE MILLION DOLLARS ($1,000,000); 3.Comprehensive Automobile Liability Insurance in an amount not less than ONE MILLION DOLLARS ($1,000,000); 4.Contractual General Liability Insurance in an amount not less than ONE MILLION DOLLARS ($1,000,000); 5.or GENERAL AGGREGATE LIABILITY in an amount of not less than TWO MILLION DOLLARS ($2,000,000). *Automobile and lease vehicle insurance; owned, not owned and hired. Insurance to include bodily CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 10 of 63 Page: B.5 injury, sickness and death of any person and property damage owned and un-owned per occurrence. SOCIAL SECURITY ACT The successful Bidder agrees to comply with and to require all of his subcontractors to comply with all the provisions of the Act of Congress approved August 14, 1935, known and cited as the Social Security Act and also the provisions of the act of the State Legislature Approved, and known as the State Unemployment Compensation Law and all other laws and regulations pertaining to labor and workmen and all amendments to such data, and the contractor further agrees to indemnify and hold harmless the City of Temple City of and from any and all claims and demands made against it by virtue of the failure of the contractor or any subcontractors to comply with the provisions of any or all of said acts and amendments. SALES AND USE TAX The successful Bidder agrees to comply with and to require all of his subcontractors to comply with all the provisions of applicable state sales excise tax law and compensation use tax law and all amendments to same. The successful Bidder further agrees to indemnify and hold harmless the City of Temple City of and from any and all claims and demands made against virtue of the failure of the Contractor or any Subcontractors to comply with the provisions of any or all said laws and amendments. WAIVER OF LIENS The successful Bidder (General Contractor) is responsible for the payment of all bills for labor and materials furnished by the subcontractors, the suppliers, and the General Contractor on this project. The General Contractor shall deliver to the City, unconditional Lien Waivers and/or Releases from himself and from each of his subcontractors and suppliers, and at such time he shall certify that he is submitting such lien waivers for all subcontractors and suppliers involved. If any liens are filed against the City property, the City may, at its option, demand General Contractor immediately provide a bond in accordance with state statutes. LEGAL RESPONSIBILITIES All proposals must be submitted, filed and executed in accordance with State and Federal laws relating to bids for contracts of this nature whether the same or expressly referred to herein or not. Any bidder submitting a proposal shall by such action thereby agree to each and all of the terms, conditions, provisions, and requirements set forth, contemplated, and referred to in the Plans, Specifications, and other contract documents, and to full compliance therewith. AWARD OF CONTRACT The award of contract, if made, will be to the lowest responsible bidder as determined solely by the City. The City of Temple City reserves the right to reject any or all proposals, to waive any irregularity, and to take the bids under advisement for a period of sixty (60) calendar days, as may be required to provide for the best interests of the City. In no event will an award be made until all necessary investigations are made as to the responsibility and qualifications of the bidder to whom the award is contemplated. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 11 of 63 Page: B.6 The Contractor shall submit a signed contract, bonds, insurance and all necessary documents to the City, within the required schedule. EMPLOYMENT OF APPRENTICES Attention is directed to the provisions in Section 1777.5 of the California Labor Code concerning employment of apprentices by the contractor or any subcontractor under him. The contractor and any subcontractor under him shall comply with the requirements of said section in the employment of apprentices; however, the contractor shall have full responsibility for compliance with said Labor Code section for all apprenticable occupations, regardless of any other contractual or employment relationships alleged to exist. CONFLICT OF INTEREST In the procurement of supplies, equipment, construction, and services by sub-recipients, the conflict of interest provisions in (State LCA-24 CFR 85.36 and Non-Profit Organizations – 24 CFR 84.4), OMB Circular A-110, and 24 CFR 570.611, respectively, shall apply. No employee, officer or agent of the sub-recipient shall participate in selection, or in the award or administration of a contract supported by Federal funds if a conflict of interest, real or apparent, would be involved. SUBCONTRACTS Subcontracts shall comply with SECTION 2-SCOPE AND CONTROL OF THE WORK, of the Greenbook (Standard Specifications for Public Works Construction, latest edition). The Contractor is required to perform, with its own organization, contract work amounting to at least 51 percent of the Contract Price. Failure to meet these requirements will result in disqualifying of the bid or termination of the contract. This provision supersedes any other provisions which specified a different subcontract requirement Proposed subcontractor names, a general description of the work to be performed by each subcontractor and the dollar amount for each subcontractor shall be submitted with the bid. PROJECT CLOSE OUT DOCUMENTS Within 10 calendar days of completion of the project, the Contractor shall submit project close out documents, including: Drawings showing as built conditions with red pencil; All warranties and guarantees; All paperwork required for labor compliance; All final lien releases; All other project related documents requested by the City. PROPOSAL REQUIREMENTS AND CONDITIONS The bidder’s attention is directed to the applicable provisions in the Standard Specifications for Public Works Construction requirements and conditions which must be observed in the preparation of the proposal form and the submission of the bid. 1.Examination of Site, and Specifications: Bidders shall examine the site of the work and acquaint themselves with all conditions affecting the work. By submitting a bid, the Bidder shall be held to have personally examined the site, to have carefully read the specifications, and to have satisfied itself as to its ability to meet all the difficulties attending the execution of the proposed contract before the CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 12 of 63 Page: B.7 delivery of this proposal, and agrees that if awarded the contract, will make no claim against the City based on ignorance or misunderstanding of the specifications, site conditions and/or contract provisions. 2.The Contractor shall have included in the contract price a sufficient sum to cover all items, including labor, materials, tools, equipment and incidentals, that are implied or required for the complete improvements as contemplated by the contract documents. OTHER CONTRACT PROVISIONS The bidder’s attention is directed to other contract provisions, as listed below, which must be observed in the preparation of the proposal form and the submission of the bid: •Federal Labor Standards Provisions •Current Federal DOL Wage Decision •Federal EEO and Affirmative Action Requirements •Contracting with Small & Minority Firms, Women’s Business Enterprise •Compliance with Clean Air and Water Acts If there are any questions regarding this project, please contact via e-mail: Okan Demirci, PE, Project Manager okan.demirci@transtech.org All inquiries must be submitted in writing. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 13 of 63 Page: C.1 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” C.BIDDER’S PROPOSAL LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-05 City of Temple City Bidder’s Name: In accordance with the City of Temple City’s Notice Inviting Sealed Bids, the undersigned BIDDER, hereby proposes to furnish all materials, equipment, tools, labor, and incidentals required for the above stated project as set forth in the Plans, Specifications, and contract documents therefore, and to perform all work in the manner and time prescribed therein. BIDDER declares that this proposal is based upon careful examination of the work site, Plans, Specifications, Instructions to Bidders, and all other contract documents. If this proposal is accepted for award, BIDDER understands that failure to enter into a contract in the manner and time prescribed will result in forfeiture to the City of Temple City of the guarantee accompanying this proposal. BIDDER understands that a bid is required for the entire work. The contract will be awarded on the prices shown on the bid schedule. It is agreed that the unit and/or lump sum prices bid include all appurtenant expenses, taxes, royalties and fees. In the case of discrepancies in the amounts of bid, unit prices shall govern over extended amount, and words shall govern over figures. If awarded the Contract, the undersigned further agrees that in the event of the BIDDER’S default in executing the required contract and filing the necessary bonds and insurance certificates within ten working days after the date of the City of Temple City’s notice of award of contract to the BIDDER, the proceeds of the security accompanying this bid shall become the property of the City of Temple City and this bid and the acceptance hereof may, at the City of Temple City’s option, be considered null and void. BID SCHEDULE To the Temple City’s City Council, herein called the “Council”. Pursuant to and in compliance with your Notice Inviting Bids and the other documents relating thereto, the undersigned bidder, having familiarized himself with the work as per the paragraph, Discrepancies and Misunderstandings, contained in the INSTRUCTIONS TO BIDDERS section, and with the terms of the contract, the local conditions affecting the performance of the contract, and the cost of the work at the place where the work is done, and with the drawings and specifications and other contract documents, hereby proposes and agrees to perform, within the time stipulated, the contract, including all of its component parts, and everything required to be performed, and to provide and furnish any and all of the labor, materials, tools, expendable equipment, and all applicable taxes, utility and transportation services necessary to perform the contract and complete in a workmanlike manner, all in strict conformity with the Contract Documents on file at the office of the City Clerk of said City, per the following bid schedule: (Bidder shall provide a bid amount for each bid item listed below. Failure to provide a bid for each bid item shall render the bid non-responsive). CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 14 of 63 Page: C.2 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” BID SCHEDULE LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-07 City of Temple City ITEM NO. DESCRIPTION OF ITEM QUANTITY UNIT PRICE TOTAL PRICE NO. UNITS UNIT MEAS. 1 3" COLD MILL ASPHALT PAVEMENT 400,000 SF $__________ $_______________ 2 CONSTRUCT ASPHALT RUBBER HOT MIX-GAP GRADE (ARHM-GG-C) 5,500 TONS $__________ $_______________ 3 CONSTRUCT ASPHALT CONCRETE TYPE B-PG 64-10 2,750 TONS $__________ $_______________ 4 SAWCUT AND REMOVE 10" THICK AC/BASE PAVEMENT SECTION AND RECONSTRUCT 10" AC PAVEMENT SECTION CONSISTING OF 2" AHRM ON 2" AC (TYPE B-PG 64-10) ON 6" CAB (AREA TO BE DETERMINED BY THE ENGINEER DURING CONSTRUCTION) 10,000 SF $__________ $_______________ 5 REMOVE EXISTING MARKINGS AND STRIPING IN EXISTING PCC CONCRETE SURFACES ON LAS TUNAS (WEST ND EAST OF TEMPLE CITY), AND REINSTALL NEW STRIPING MARKINGS. (ALL STRIPING SHALL COMPLY WITH CURRENT STANDARDS, AND SHALL HAVE RAISED MARKERS AS SHOWN ON GOOGLE AERIALS.) 1 LS $__________ $_______________ 6 RESTORE ALL MARKINGS AND STRIPING (ALL STRIPING SHALL COMPLY WITH CURRENT STANDARDS, AND SHALL HAVE RAISED MARKERS AS SHOWN ON GOOGLE AERIALS.) 1 LS $__________ $_______________ 7 REMOVE AND RESTORE TRAFFIC LOOP DETECTOR (WITH VARYING, SHAPE & SIZES) 85 EA $__________ $_______________ 8 ADJUST STORM DRAIN/SEWER MANHOLE FRAME AND COVER TO GRADE 16 EA $__________ $_______________ 9 ADJUST VALVE COVER TO GRADE . THIS ITEM WILL ONLY PAY IF THE WORK IS PERFORMED BY THE CONTRACTOR. IF THE WORK IS PERFORMED BY THE OWNER OF A VALVE (UTILITY OWNER) NO PAYMENT WILL MADE TO THE CONTRACTOR. 70 EA $__________ $_______________ 10 TRAFFIC CONTROL 1 LS $__________ $_______________ 11 THIS IS A CITY ESTABLISHED ALLOWANCE FOR MISC. PCC SIDEWALK REPAIRS IF SUCH WORK IS APPROVED BY THE CITY. THIS AMOUNT MAY ONLY BE USED AT CITY'S DISCRETION. 1 LS $__________ $_______________ TOTAL BID AMOUNT (Total of all Bid Items above) $_______________ In the case of discrepancies, total bid will be based on calculated amounts based on quantities and Unit Bid Amounts. The bid prices shall include any and all costs, including labor, materials, appurtenant expenses, taxes, royalties and any and all other incidental costs to complete the project, in compliance with the Bid and Contract Documents and all applicable codes and standards. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 15 of 63 Page: C.3 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” All other work items not specifically listed in the bid schedule, but necessary to complete the work per bid and contract documents and all applicable codes and standards are assumed to be included in various bid items and costs as applicable and as necessary. Note: Mobilization and demobilization is assumed to be part of various bid items. The City reserves the right to add, delete, increase or decrease the amount of any quantity shown and to delete any item from the contract and pay the contractor at the bid unit prices so long as the total amount of change does not exceed 25% (plus or minus) of the total bid amount for the entire project. If the change exceeds 25%, a change order may be negotiated to adjust unit bid prices. A bid is required for the entire work, that the quantities set forth in the Bid Schedule are to calculate total bid amount, and that final compensation under the contract will be based upon the actual quantities of work satisfactorily completed. Bidder shall provide a bid amount for each bid item listed below. Failure to provide a bid for each bid item shall render the bid no responsive CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 16 of 63 Page: C.4 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” DESIGNATION OF SUBCONTRACTORS BIDDER proposes to subcontract certain portions of the work which are in excess of one-half of one percent of the bid and to procure materials and equipment from suppliers and vendors as follows: Name, address, and phone number pf subcontractors, suppliers, and vendors Work to be Performed Contractor’s License # DIR # Dollar Amount $_____________ $_____________ $_____________ $_____________ $_____________ $_____________ $_____________ $_____________ $_____________ Total Subcontract Amount (shall not exceed 49% of Total Bid Amount) $___________ CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 17 of 63 Page: C.5 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” REFERENCES The City of Temple City is interested in obtaining bids from the most qualified and capable contractors with a proven track record able to perform work desired by the Public Works Department. Any and all references required to be provided by the bid specifications must be for projects constructed by the bidding company; references for other projects performed by principals or other individuals of the bidding company may not be included. The following are the names, addresses, and telephone numbers for three public agencies for which BIDDER has performed similar work within the past three years. Reference Contact Information Reference Project Name Contract Value Date Completed Agency Name: $_________ Contact Name and Title: Contact Tel No: Agency Name: $_________ Contact Name and Title: Contact Tel No: Agency Name: $_________ Contact Name and Title: Contact Tel No: BONDS The following are the names, addresses, and telephone numbers for all brokers and sureties from whom Bidder intends to procure insurance bonds: ______________________________________________________________________________ SITE INSPECTION The Bidder declares that he/she has carefully read and examined the plans, specifications, bid documents, and he/she has made a personal examination of the site (indicate name of the person, representing the bidder, who inspected the site and date below) and that he/she understands the exact scope of the Project WITHOUT QUESTION. Name of Person who inspected the site: _____________________ Date of Inspection: _____________________ CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 18 of 63 Page: C.6 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” ADDENDA ACKNOWLEDGMENT The Bidder acknowledges receipt of the following Addenda and has included their provisions in this Proposal: Addendum No.___________________ Dated________________ Addendum No.___________________ Dated________________ Addendum No.___________________ Dated________________ Addendum No.___________________ Dated________________ EQUAL EMPLOYMENT OPPORTUNITY COMPLIANCE BIDDER certifies that all previous contracts or subcontracts, all reports which may have been due under the requirements of any Agency, Site, or Federal equal employment opportunity orders have been satisfactorily filed, and that no such reports are currently outstanding. AFFIRMATIVE ACTION CERTIFICATION BIDDER certifies that affirmative action has been taken to seek out and consider minority business enterprises for those portions of work to be subcontracted, and that such affirmative actions have been fully documented, that said documentation is open to inspection, and that said affirmative action will remain in effect for the life of any contract awarded hereunder. Furthermore, BIDDER certifies that affirmative action will be taken to meet all equal employment opportunity requirements of the contract documents. NONCOLLUSION AFFIDAVIT BIDDER declares that the only persons or parties interested in this proposal as principals are those named herein: that no officer, agent, or employee of the City of Temple City is personally interested, directly or indirectly, in this proposal; that this proposal is made without connection to any other individual, firm, or corporation making a bid for the same work and that this proposal is in all respects fair and without collusion or fraud. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 19 of 63 Page: C.7 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” BIDDER INFORMATION Bidder’s Name: Address: Form of Legal Entity (i.e., individual, partnership, corporation, etc.) If a Corporation, State of Incorporation (i.e., Calif.) State Contractor’s License No. and Class DIR Registration No.: (Also provide DIR No’s for subcontractors as separate attachment) Contact Person Information: Name Title E-mail Tel The following are the names, titles, addresses, and phone numbers of all individuals, firm members, partners, joint venturers, and/or corporate officers having a principal interest in this proposal: _______________________________________________________________________________ ____________________________________________________________________________ ____________________________________________________________________________ The date(s) of any voluntary or involuntary bankruptcy judgements against any principal having an interest in this proposal are as follows: __________________________________________________________________________ _________________________________________________________________________ All current and prior DBA’S, alias, and/or fictitious business names for any principal having an interest in this proposal are as follows: __________________________________________________________________________ Previous contract performance history: 1.Was any contract terminated previously:_______ If the answer to the above is “yes”, provide the following information: Contract/project name and number:___________________________________________ Date of termination:________________________________________________________ Reason for termination:_____________________________________________________ Owner’s name:___________________________________________________________ Owner contact person and tel. no.: _________________________________________ 2.In the past ten years have you filed a claim for money against any public entity? If the answer to the above is “yes”, provide the following information: CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 20 of 63 Page: C.8 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” Contract/project name and number:___________________________________________ Date of filing claim:________________________________________________________ Reason for filing claim:_____________________________________________________ Owner’s name:___________________________________________________________ Owner contact person and tel. no.: _________________________________________ 3.In the past ten years have you been a party to legal action by or against a public entity arising out of the performance of a public works contract? If the answer to the above is “yes”, provide the following information: Contract/project name and number:___________________________________________ Date of commencement of litigation:______________________________________________ Reason for litigation:_____________________________________________________ Owner’s name:___________________________________________________________ Owner contact person and tel. no.: _________________________________________ IN WITNESS WHEREOF, BIDDER executes and submits this proposal with the names, titles, hands, and seals of all aforementioned principals this ____ day of ___________, 201_. BIDDER ______________________________________________________________ ______________________________________________________________ ______________________________________________________________ ______________________________________________________________ Subscribed and sworn to this _____ day of _______________, 201_. NOTARY PUBLIC _______________________________________________________________ CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 21 of 63 Page: C.9 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” Department of Industrial Relations (DIR) Contractor Registration Number Beginning July 1, 2014, contractors must register with the Department of Industrial Relations (DIR) before bidding on public works contracts in California. For more information, please refer to this section of the Department of Industrial Relations Website: http://www.dir.ca.gov/Public-Works/PublicWorks.html. Per this requirement, provide the following information: ______________________________________________________________________ Contractor Name Contractor Department of Industrial Relations Registration Number: ______________________________________________________________________ Expiration Date of Registration Number *(THIS FORM MUST BE SUBMITTED WITH THE SEALED BID)* CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 22 of 63 Page: C.10 BIDDER SHALL COMPLETE AND SUBMIT ALL DOCUMENTS AND PAGES IN SECTION “C. BIDDER’S PROPOSAL” PROPOSAL GUARANTEE/BID BOND LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-07 City of Temple City KNOW ALL MEN BY THESE PRESENTS that __________________________________________, as BIDDER, and ____________________________________________________, as SURETY, are held and firmly bound unto the City of Temple City, in the penal sum of ___________________dollars ($_____________), which is 10 percent of the total amount bid by BIDDER to the City of Temple City for the above stated project, for the payment of which sum, BIDDER and SURETY agree to be bound, jointly and severally, firm by these presents. THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, whereas BIDDER is about to submit a bid to the City of Temple City for the above stated project, if said bid is rejected, or if said bid is accepted and a contract is awarded and entered into by BIDDER in the manner and time specified, then this obligation shall be null and void, otherwise it shall remain in full force and effect in favor of the City of Temple City. IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seals this ____ day of _______________, 201_. BIDDER* _____________________________________________________________ _____________________________________________________________ SURETY* _____________________________________________________________ _____________________________________________________________ *Provide BIDDER/SURETY name, address and telephone number and the name, title, address and telephone number for authorized representative. Subscribed and sworn to this _____ day of _______________, 201_. NOTARY PUBLIC:______________________________________________________ CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 23 of 63 Page: D.1 D.GENERAL PROVISIONS LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-07 City of Temple City 1.GENERAL All work shall be performed in accordance with the "Standard Specifications for Public Works Construction" (SSPWC), Latest Edition, “California Manual on Uniform Traffic Control Devices” (CA MUTCD), “Caltrans Standard Specifications”, “Caltrans Standards”, “Standard Plans for Public Work Construction”, the General Provisions and these Special Provisions. In case of conflict the more stringent requirement shall apply, except when the City makes an exception. The City has the right to make such exception at its discretion, and the contractor shall provide reasonable cost discount if the City decides to implement the lesser stringent option. 2.CONTRACTORS DUTIES: Comply with codes, ordinances, rules, regulations, orders, and other legal requirements of public authorities which bear on performance of work. 3. CONTRACTS: Construct entire work under one contract with the City. 4.SPECIFICATIONS AND DRAWINGS COMPLEMENTARY: The Specifications and Drawings are complementary, and what is called for in one shall be binding as if called for in both. 5.ORDER OF PRECEDENCE OF CONTRACT DOCUMENTS: Subsection 2-5.2, "Precedence of Contract Documents", (SSPWC), revise the order of precedence and incorporate additional items as follows: a.Permits issued by jurisdictional regulatory agencies. b.Change Orders and/or Supplemental Agreements; whichever occurs last c. Contract/Agreement d. Addenda e.Bid/Proposal f.Special Provisions (Section E) g.Plans h.General Provisions (Section D) i.Standard Plans j.Standard Specifications k.Reference Specifications CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 24 of 63 Page: D.2 With reference to the Drawings the order of precedence is as follows: a.Figures govern over scaled dimensions b.Detail drawings govern over general drawings c.Addenda/Change Order drawings govern over Contract Documents d.Contract Documents govern over standard drawings e.Contract Drawings govern over shop drawings 6.DISCREPANCIES IN THE CONTRACT DOCUMENTS: Any discrepancies, conflicts, errors or omissions found in the Contract Document shall be promptly reported in writing to the Engineer, who will issue a correction in writing. The Contractor shall not take advantage of any such discrepancies, conflicts, errors or omissions, but shall comply with any corrective measures regarding the same prescribed by the Engineer, and no additional payment or time shall be allowed therefor, except as provided in the Standard Specifications. If discrepancies are discovered between the drawings and the specifications, and no specific interpretation is issued prior to the bidding, the decision regarding this interpretation shall rest with the Engineer. The Contractor shall be compelled to act on the Engineer’s decision as directed. In the event the installation is not in compliance with the direction of the Engineer, the installation shall be corrected by and at the expense of the Contractor at no additional cost to the City. In case of such discrepancies on the plan sheets, it is assumed that the bid included the cost for implementing/constructing the discrepancy that would have the highest dollar value. 7.ERRORS AND OMISSIONS: If the Contractor, in the course of the work, becomes aware of any claimed errors or omissions in the contract documents or in the City's field work, it shall immediately inform the Engineer. City Engineer shall promptly review the matter, and if he/she finds an error or omission has been made, he/she shall determine the corrective actions and advise the Contractor accordingly. If the corrective work associated with an error or omission increases or decreases the amount of work called for in the Contract, the City shall issue an appropriate Change Order. After discovery of an error or omission by the Contractor, any related work performed by the Contractor shall be done at its risk unless authorized by the Engineer. 8.CHANGED CONDITIONS: The plans for the work show conditions as they are believed by City Engineer to exist, but is not intended or to be inferred that the conditions as shown thereon constitute a representation by the City that such conditions are actually existent, nor shall the City be liable for any loss sustained by the Contractor as a result of any variance of the conditions as shown on the plans and the actual conditions revealed during the progress of the work or otherwise. The word "conditions" as used in this paragraph includes, but is not limited to, site conditions, both surface and subsurface. The Contractor shall examine the site, compare it with the drawings and specifications and shall satisfy itself as to the conditions under which the work is to be performed. The Contractor shall ascertain and check the location of all existing structures, utilities and equipment which may affect its work. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 25 of 63 Page: D.3 The Contractor shall be responsible to re-examine the site, as necessary, for performance of change orders or other proposed changes which may affect its work. No allowance shall subsequently be made on the Contractor's behalf for any extra expense or loss of time which incurred due to failure or negligence on its part to make such examination. 9.MARKUP: For extra work and change orders the following percentages shall apply: a.LABOR COSTS 1.Labor markup for employer taxes standard federal/state rates, approximately: 10% 2.Labor markup for fringe benefits (if fringe benefits are not included in the labor cost: 15% 3.Labor overhead markup: 10% 4.Profit markup: 10% b.MATERIAL, EQUIPMENT, SUBCONTRACTOR COSTS Only 5% markup by prime contractor will be allowed on materials, equipment and subcontractor costs. No other additional markups (overhead, profit, etc.) will be allowed. c.After the total amount is established by adding the above items, an additional 2% markup for INSURANCE AND BONDING COSTS will be allowed. The subcontractor costs shall be established using the same cost accounting principal above. The markups mentioned hereinafter shall include, but are not limited to, all costs for the services of superintendents, project managers, timekeepers and other personnel not working directly on the change order, and pickup or yard trucks used by the above personnel, and other vehicles and/or equipment present at the job site but not directly used in actual construction activities. Incidental movements of labor, materials, supplies or equipment shall not be considered as use in actual construction activities. These costs shall not be reported as labor or equipment elsewhere, except when actually performing work directly on the change order and then shall only be reported at the labor classification of the work performed. The City shall not pay for the cost of foremen or vehicles used by foremen unless authorized in advance by the Engineer. 10.SITE SECURITY AND SAFETY The Contractor shall secure the project as well as the adjoining properties during the duration of the project. 11.PAYMENTS TO CONTRACTOR AND CLAIMS a.Payment for Labor and Materials. The Contractor shall pay and cause the subcontractors to pay any and all accounts for labor, including Worker's Compensation premiums, State Unemployment and Federal Social Security payments and all other wage and salary deductions required by law. The Contractor also shall pay and cause the subcontractors to pay any and all accounts for services, equipment and materials used by it and the subcontractors during the performance of CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 26 of 63 Page: D.4 work under this contract. All such accounts shall be paid as they become due and payable. If requested by the Engineer, the Contractor shall immediately furnish the City with proof of payment of such accounts. b.Additional Work. Payment for additional work and all expenditures in excess of the bid amount must be authorized in writing by the City Engineer. Such authorization shall be obtained by the Contractor prior to engaging in additional work. It shall be the Contractor's sole responsibility to obtain written approval from City Engineer for any change(s) in material or in the work proposed by suppliers or subcontractors. No payment shall be made to the Contractor for additional work which has not been approved in writing, and the Contractor hereby agrees that it shall have no right to additional compensation for any work not so authorized. c.Claims. The Contractor shall not be entitled to the payment of any additional compensation for any cause, including any act, or failure to act, by the City, or the happening of any event, thing or occurrence, unless he shall have given the City due written notice of potential claim as hereinafter specifications. The written notice of potential claim shall set forth the reasons for which the Contractor believes additional compensation will or may be due, the nature of the costs involved, and, insofar as possible, the amount of the potential claim. Said notice shall be submitted on a form approved by the City at least forty-eight (48) hours (two working days) in advance of performing said work, unless the work is of an emergency nature, in which case the Contractor shall notify and obtain approval from the Inspector prior to commencing the work. The City Engineer. may require the Contractor to delay construction involving the claim, but no other work shall be delayed, and the Contractor shall not be allowed additional costs for any said delay but may be allowed on extension of time if the City Engineer. agrees that the work delayed is a controlling element of the Construction Schedule. The Contractor shall be required to submit any supporting data (or a detailed written explanation justifying further delay) within five (5) Work Days of a request from the City Engineer, and shall be responsible for any delays resulting from late and/or incomplete submittals. By submitting a Bid, the Contractor hereby agrees that this Section shall supersede Sections 6-6.3 and 6-6.4 of the Standard Specifications. The City shall be the sole authority to interpret all plans, specifications and contract documents, and no claim shall be accepted which is based on the Contractor's ignorance, misunderstanding or noncompliance with any provision or portion thereof. The above provisions shall supplement Section 3 of the Standard Specifications. The Contractor shall be responsible to provide all data and to obtain all approvals required by said Specifications, including submittal of Daily Extra Work Reports. No claims or extras shall be approved by the City unless all work was done under the direction of and subject to the approval of the Inspector. Disputed work claims shall comply with Section 3 of the Standard Specifications, as modified herein. It is the intention of this Subsection that differences between the parties arising under and by virtue of the Contract be brought to the attention of the Engineer at the earliest possible time in order that such matters may be settled, if possible, or other appropriate action promptly taken. The Contractor hereby agrees that it shall have no right to additional compensation for any claim that may be based on any such act, failure to act, event, thing or occurrence for which no written notice of potential claim as herein required was filed. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 27 of 63 Page: D.5 d.Noncompliance with Plans and Specifications. Failure of the Contractor to comply with any requirement of the Plans and Specifications, and/or to immediately remedy any such noncompliance upon notice from the Engineer, may result in suspension of Contract Progress Payments. Any Progress Payments so suspended shall remain in suspension until the Contractor's operations and/or submittals are brought into compliance to the satisfaction of the Engineer. No additional compensation shall be allowed as a result of suspension of Progress Payments due to noncompliance with the plans or specifications. The Contractor shall not be permitted to stop work due to said suspension of Progress Payments. e.Request for Payment. Contractor shall submit all requests for payment on the City provided form. The City shall provide the form for use after Contract is awarded. Prior to submittal of said form, all items for which payment is requested shall be checked and approved in writing by the City Engineer. No payments will be made unless all back-up data is submitted with the payment request and the Progress Payment Invoice is signed by both Contractor and City Engineer. There shall be no separate payment for any relocations, barriers or forms, grading or temporary construction required to construct the improvements herein. Payment for these items shall be absorbed in the Bid Prices for the applicable work to which they are appurtenant, and no extra costs shall be allowed. The payment of amounts due to the Contractor shall be contingent upon the Contractor and subcontractors furnishing the City with a release of all claims against the City arising by virtue of the Contract related to said amounts. 12.LEGAL ADDRESS OF CONTRACTOR The address given in the Bidder's Proposal is hereby designated as the place to which all notices, letters, and other communications to the Contractor will be mailed or delivered, except such notices and communications as shall be given by the City's Inspectors to the Contractor's designated Superintendent in the field. The mailing or delivering to said address of any notice, letter, or other communication, or the hand-delivery to said Superintendent, shall be deemed sufficient service thereof upon the Contractor. The date of such service shall be the date of such mailing or delivery. Said address may be changed at any time by a written notice signed by the Contractor and delivered to the Engineer. 13. NOTIFICATION The Contractor shall notify the City of Temple City and the owners of all utilities and substructures not less than 48 hours prior to starting construction. The following list of names and telephone numbers is intended for the convenience of the Contractor and is not guaranteed to be complete or correct: Agency Name and Title Tel City of Temple City Director of Community Development 626-285-2171 City of Temple City Ali Cayir, PE, City Engineer 714-883-8677 City of Temple City Bryan Ariizumi, Public Safety Officer 626-285-2171 City of Temple City, PD County Sheriff’s Station 626-285-7171 CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 28 of 63 Page: D.6 City of Temple City, Fire Fire Department 626-287-9521 Electric Southern California Edison 626-303-8473 Gas The Gas Company 310-687-2020 AT&T Business Customer Service 626-570-5314 SPRINT Customer Service 800-211-4727 MCI Customer Service 888-624-5622 Refuse Athens Disposal Company 626-336-3636 Cable Charter Communications 626-430-3570 Water California American Water Co. 626-614-2534 Water East Pasadena Water Co. 626-793-6189 Water Golden State Water Company 626-287-5238 Water San Gabriel County Water District 626-287-0341 Water So. California Water Co. 626-446-1372 Water Sunny Slope Water Co. 626-287-5238 Underground Service Alert 811 14.CITY HOLIDAYS City offices are closed on the following days: New Years Day; President’s Day; Memorial Day; Independence Day; Labor Day; Veteran’s Day; Thanksgiving (2 days) and Christmas Day. During these holidays, inspections will not be available. 15.EMERGENCY INFORMATION The names, addresses and telephone numbers of the Contractor and subcontractors, or their representatives, shall be filed with the Engineer and the City Police Department prior to beginning work. 16.FINAL ACCEPTANCE Final acceptance by CITY will be made when Contractor has provided 'as-built' drawings and satisfactorily completed all work and improvements as called for in the Contract Documents including reconciliation of materials. The CITY shall notify Contractor in writing of final acceptance of the work. Failure or neglect on the part of CITY to reject inferior work during the construction period shall not be construed to imply acceptance of such work nor to preclude its right to reject it. Contractor shall be required to correct all defects which become evident at any time prior to final acceptance of Contractor's work by CITY. The cost of all such repairs, material, labor, and overheads shall be borne by Contractor. Ownership, custody, and control of the work and facilities shall pass to CITY only upon Final Acceptance. 17. WARRANTY The Contractor expressly represents and warrants that all work performed and all materials used are free from defects of workmanship and conform to the Contractor's Contract obligations. This warranty shall commence upon Final Acceptance and end one year from that date. The Contractor shall pay the actual cost to CITY for any breach of this warranty corrected by CITY (including labor, material and overheads). If CITY is unable to collect for the work after 30 days from completion, the CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 29 of 63 Page: D.7 actual cost may be deducted from the Contractor's refundable monies on deposit with CITY. CITY may recover such cost by claim against the surety on the performance or maintenance bond furnished by the Contractor. 18. AS- BUILT DRAWINGS Provide and record a complete “As Built” records set of blue line prints showing changes from the original drawings and specifications and the exact “As Built” locations, sizes and types of equipment. Prints for this purpose may be obtained from the City. Keep this set of drawings on the site and use only as a record set. Use these drawings as work progress sheets. With red pencil, make neat and legible annotations thereon as the work proceeds, showing the work as actually completed. Keep these drawings available at all times for inspection. Before the date of the final inspection, provide the “As Built” prints to the City. Please note, that failure to submit an “As Built” set of drawings as noted above will result in the retention payment being delayed. 19.PAYMENT Payment will be made under applicable bid items in the bid schedule. If no specific bid item is provided for a work item, it is assumed all work is included in various bid items as necessary. The bid prices shall include any and all costs, including labor, materials, appurtenant expenses, taxes, royalties and any and all other incidental costs to complete the project, in compliance with the Bid and Contract Documents and all applicable codes and standards. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 30 of 63 Page: E.1 E. SPECIAL PROVISIONS LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-07 City of Temple City 1.SCOPE OF THE WORK COVERED BY CONTRACT DOCUMENTS The work consists of furnishing all materials, equipment, tools, labor, and incidentals as described in detail in the Bidding and Contract Documents, Plans and Specifications to construct the project. Major work components include coldmill and overlay of Las Tunas Boulevard from West City Limit at Muscatel Avenue to Sultana Avenue, Temple City High School Traffic Improvements and other improvements as shown in BIDDING AND CONTRACT DOCUMENTS, PLANS AND SPECIFICATIONS. 2.ALLOTTED WORKING SPACE The contractor shall be responsible for storing his materials and equipment and to use as work yard as necessary. The City will not allow keeping equipment, materials, vehicles, removed items, debris, etc. within this space with no liability to the City. It shall be the responsibility of the Contractor to provide adequate fencing, security of the yard and equipment to the Engineer’s satisfaction, and to restore the assigned area to its original, pre-use condition, or better, to the satisfaction of the City. 3.ACCEPTANCE OF SITE The Contractor shall accept the site and the character of the work as they exist on the first day of work under this contract. 4.MAINTENANCE OF EXISTING PLANTINGS, IMPROVEMENTS AND FACILITIES The Contractor shall protect and maintain all existing trees and shrubs (plantings) to remain from the first day of work under this contract to acceptance. In similar fashion, Contractor shall protect and maintain all improvements and facilities in place to remain from the first day of work under this contract to acceptance. Contractor shall notify City Engineer of any damage to any existing plantings, improvements or facilities as soon as possible. Contractor shall replant or repair any damage to the satisfaction of City Engineer at no cost or extra burden to the City. 5.PUBLIC CONVENIENCE AND SAFETY Add the following to Section 7-10. “Public Convenience and Safety” of the SSPWC: •At the end of the Work Day the job site shall be left in a neat and orderly manner. Roadway and parking shall be made available wherever possible to the satisfaction of the City Engineer. •During construction the Contractor shall provide adequate access to each residence or business affected by this project to the satisfaction of the Engineer. •Should any change in these requirements be necessitated by extraordinary occurrences or requirements during the execution of the work, the Contractor shall obtain prior written approval of the Engineer. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 31 of 63 Page: E.2 6.WORK SITE MAINTENANCE Add the following to Section 7-8, “Work Site Maintenance” of the SSPWC: •Sanitary Conditions. The Engineer may from time to time prescribe rules and regulations for maintaining sanitary conditions along the work and the Contractor shall enforce observance of the same by its employees and the employees of the subcontractor, and, if the Contractor fails to enforce these rules and regulations, the Engineer shall have the authority to enforce them. •Water Pollution Control. The Contractor shall adhere strictly to Subsection 7-8.6 of the Standard Specifications through the entire project and add the following: o The Contractor, without limitation, shall be responsible to provide and implement Best Management Practices to comply with National Pollution Discharge Elimination System (NPDES) standards and practices. The Contractor shall be responsible, to the fullest extent possible, not to permit any contaminants, including soil, to enter any drainage system. Contractor shall be responsible to be prepared to provide hay bales or similar devices to prevent erosion from being washed into the storm drain system. Contractor shall be responsible to maintain equipment so that oil, grease, gasoline, diesel fuel, et al., does not contaminate areas subject to run-off. The Contractor and its Surety shall fully indemnify the City for any pollution damage and/or cleaning costs. o All construction on off-site or on-site improvements shall adhere to NPDES (National Pollution Discharge Elimination System) Best Management Practices to prevent deleterious materials or pollutants from entering the City or County storm drain systems. The following are the areas to be addressed: Handle, store and dispose of materials properly. Avoiding excavation and grading activities during wet weather. Construct diversion dikes and drainage swales around working sites. Cover stockpiles and excavated soil with secured tarps or plastic sheeting. Develop and implement erosion control plans. Check and repair leaking equipment away from construction site. Designate a location away from storm drains for refueling. Cover and seal catch basins whenever working in their vicinity. Use vacuum with all concrete sawing operations. Never wash excess material from aggregate, concrete or equipment onto a street Catch drips from paver with drip pans or absorbent material. Clean up all spills using dry methods. Sweep all gutters at the end of each working day. Gutters shall be kept clean after leaving construction site. Call 911 in case of a hazardous spill. Keep a running log of all activities in connection with the Storm Water Pollution Prevention Plan (SWPPP) Name a person, on site, responsible for complying with S.W.P.P.P. CONTRACTOR TO COMPLY WITH THESE REQUIREMENTS AND CITY ENGINEER'S DIRECTIONS DURING THE COURSE OF CONSTRUCTION. 7.SOLID WASTE MANAGEMENT AND RECYCLING PLAN The contractor shall submit a Solid Waste Management and Recycling Plan to the City Manager’s CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 32 of 63 Page: E.3 Office for review and approval prior to issuance of a demolition permit and/or grading permit for the project. Said plan shall indicate that the permittee/contractor shall provide documentation such as receipts from landfills, salvage and recycling facilities upon completion of the demolition/construction. Said plan shall identify: •Types of materials for recycling, reuse or sorting •Estimated quantities •Separation requirements •On site storage •Transportation methods •Destinations •Plan manager (contractor’s representative) Prior to issuance of a demolition and/or grading permit, the permittee/contractor shall contact the California Integrated Waste Management Board (recycling hotline 800-553-2962) to obtain an approved recycler (processor and/or receiver) for demolition and construction waste. At the minimum the contractor shall recycle each of the following demolition and construction waste materials: •Asphalt paving: 75% •Concrete and concrete masonry units: 75% •Non-lead based painted wood wastes (dimensional lumber and broken crates and pallets): 50% •Metals: 60% •Toilets: 75% •Appliances: 75% •Copper cable/wire: 50% •Transformers and ballasts: 100% •Fluorescent lamps: 100% •Glass: 50% •Unpainted gypsum board: 50% A minimum of 50% of the total weight of the waste (demolition and construction wastes) shall be diverted from landfill. 8.REFUSE ROUTE SCHEDULE The Contractor shall accommodate and coordinate with the City’s refuse pick-up service in the project area. The Contractor shall accommodate and coordinate with the City’s street sweeping service in the project area. 9.SURVEY AND LAYOUT Contractor shall verify all dimensions on the drawings and shall report to the City Representative any discrepancies before proceeding with related work. Contractor shall perform all survey and precise layout work to the satisfaction of the City Engineer. Contractor shall establish final grades and extents for the improvements and preserve such work on as-built plans. 10.LIMITS OF WORK CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 33 of 63 Page: E.4 Limits of work shall be the legal property boundaries of the site unless modified by Contract limit lines indicated on the plans or as noted otherwise. 11.NOTICE TO PROCEED The Contractor shall not commence work until a Notice to Proceed has been issued by the City to the Contractor. Prior to the issuance of Notice to Proceed the Contractor shall provide the following: •The Contractor shall provide all required contract bonds and evidences of insurance to the City; •The Contractor shall submit a Construction Schedule to City Engineer; •The Contractor shall obtain a City of Temple City Business License; •Obtain a no-fee Construction Permit from the City Notwithstanding any other provisions of the Contract, the Contractor shall not be obligated to perform any work and the City shall not be obligated to accept or pay for any work performed by the Contractor prior to delivery of a Notice to Proceed. The City's knowledge of work being performed prior to delivery of the Notice to Proceed shall not obligate the City to accept or pay for such work. 12.PROJECT SCHEDULE The Contractor shall submit a Construction Schedule to the Engineer prior to Notice To Proceed is issued. No work may be started until the Schedule has been approved in writing. The work shall be scheduled to assure that construction will be completed within the specified time in Section “B. INSTRUCTIONS TO BIDDERS”, Subsection “CONSTRUCTION SCHEDULE, PROGRESS OF WORK, LIQUIDATED DAMAGES”. The Contractor shall be held responsible for coordination of all phases of the operation so that the time schedule can be met. If the Contractor desires to make a major change in its method or operations after commencing construction or if its Schedule fails to reflect the actual progress, the Contractor shall submit to the Engineer a revised Construction Schedule. Said Schedule shall be submitted in advance of the beginning of the revised operations or within two (2) working days after notification by the Engineer. The Engineer may suspend all progress payments if the Contractor fails to comply. 13.CONTRACT TIME The Contractor shall submit evidence to the City that all materials have been purchased by the date indicated in the construction schedule in INSTRUCTIONS TO BIDDERS SECTION of these specifications. The date construction shall begin will be specified in a Notice to Proceed, by the date indicated in the construction schedule in INSTRUCTIONS TO BIDDERS SECTION of these specifications. Except as otherwise specified, working hours in traffic lanes will be restricted to between the hours of 8:30 a.m. and 3:00 p.m., and, except as otherwise stated in the Special Provisions or approved by the City Engineer, working hours for areas not affecting traffic are between 7:00 a.m. and 4:00 p.m. Monday through Friday, excluding legal holidays and weekends. During periods when weather or other conditions are unfavorable for construction, the Contractor shall pursue only such portions of the work as shall not be damaged thereby. No portions of the work whose acceptable quality or efficiency will be affected by any unfavorable conditions shall be CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 34 of 63 Page: E.5 constructed while those conditions exist. It is expressly understood and agreed by and between the Contractor and the City that the Contract time for completion of the work described herein is a reasonable time taking into consideration the average climatic and economic conditions and other factors prevailing in the locality of the work. 14.DELAY IN OBTAINING MATERIALS No extension of time will be granted for a delay caused by the inability to obtain materials unless the Contractor either obtains advance written approval from City Engineer or obtains from the supplier and furnishes to the Engineer documentary proof that such materials could not be obtained due to war, government regulations, labor disputes, strikes, fires, floods, adverse weather conditions necessitating the cessation of work, or other similar action of the elements. The Contractor is required to order materials in a timely manner as specified in the "Instruction to Bidders". 15.RECORD DRAWINGS The Contractor shall maintain at the job site a copy of all required permits, one (1) set of plans, standard plans and specifications and contract documents. At the end of each working day, the Contractor shall submit to the Inspector an accurate "as-built" drawing of any changes that occurred from the approved plans and drawings, including Change Order work, changed conditions in the field, and/or claimed extra work. The Contractor shall be responsible to obtain the Inspector's written approval of the accuracy of said drawing. No invoice will be accepted for processing until all work included therein is accurately shown on the record drawings. 16. MATERIALS Material Specifications: Whenever any material is specified by name and number thereof, such specifications shall be deemed to be used for the purpose of facilitating a description of the materials and establishing the quality of the materials to be used. All materials shall be new and the best of their class and kind. No substitution will be permitted which has not been approved in writing by the Engineer. Material List: A complete material list shall be submitted prior to performing any work. Catalog data and full descriptive literature and manufacturer's specifications and installation instructions shall be submitted whenever the use of items different than those specified is requested. The material list shall be submitted using the following sample layout (double spaced between each item). Item No. Description Manufacturer Model Number 1.material ABC Corp. XXX Approval of Substitutes: Approval of any items, alternates or substitutes indicates only that the product(s) apparently meet the requirements of the drawings and specifications on the basis of the information and/or samples submitted. Contractor's Responsibility: Manufacturer's warranties shall not relieve the Contractor of liability under these Specifications. Such warranties only shall supplement the Contractor's responsibility. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 35 of 63 Page: E.6 17.INSPECTION AND TESTING All materials furnished and all work performed under the Contract shall be subject to review and inspection by the Engineer. Such review may include mill, plant, shop, nursery, or field inspection as required. City Engineer shall be permitted access to all parts of the work, including plants where materials are manufactured or fabricated, and shall be furnished with such materials, information and assistance by the Contractor and its subcontractors and suppliers as is required to make a complete and detailed inspection. The Contractor shall request inspection 24 hours in advance by calling the City Engineer or his designee. Submittal shall be provided by the Contractor per Subsection 2-5.3 Submittals of the Standard Specifications for Public Work Construction (SSPWC). The City will provide standard progress building and public works inspection at no cost to the Contractor. Contractor shall arrange and pay for all other inspections required by ordinance or governing authorities, including tests in connection therewith, as may be assigned to it in other sections of the specifications. It shall be the Contractor's responsibility to obtain Inspection in a timely manner prior to proceeding with any phase of construction. The Contractor shall neither allow nor cause any of its work to be covered or enclosed until it has been inspected, tested and approved by the Engineer. City Engineer will make, or have made, such inspections and tests as he deems necessary to see that the work is being accomplished in accordance with the requirements of the Contract. In the event such inspections or tests reveal non-compliance with the requirements of the Contract, the Contractor shall bear the cost of such corrective measures deemed necessary by the City Engineer, as well as the cost of the subsequent re-inspection and re-testing. It shall be understood and agreed that the inspection or making of tests shall not constitute an acceptance of any portion of the work nor relieve the Contractor from compliance with the terms of the Contract. Public works inspections shall be requested by the Contractor at least twenty-four (24) hours in advance of an anticipated inspection. Work done in the absence of prescribed inspection may be required to be removed and replaced under the proper inspection, and the entire cost of removal and replacement, including the cost of all materials which may be furnished by the City and used in the work thus removed, shall be borne by the Contractor, regardless of whether the work removed is found to be defective or not. Work covered without the authority of City Engineer shall, upon order of the City Engineer, be uncovered to the extent required, and the Contractor shall similarly bear the entire cost of performing all the work and furnishing all the materials necessary for the removal of the covering and its subsequent replacement. 18.CONSTRUCTION STAKING Locations of new sign posts, signage, pavement marking, lines and striping as shown on the plans are approximate and the exact locations shall be established by the Contractor with approval by Engineer CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 36 of 63 Page: E.7 in the field. The Contractor shall be responsible for construction staking. Unless otherwise provided in the special provision, lines and grades for the construction shall be the responsibility of the contractor, with the following provisions: Unless directed otherwise during construction by the City Engineer, all work under this contract shall be built in accordance with the existing street lines and grades. Field survey for establishing these, and for the control of construction, shall be the responsibility of the Contractor. All such survey work including construction staking shall be done on all items ordinarily requiring grade and alignment, at intervals normally accepted by the agencies and trade involved. All Survey Monuments such as centerline monuments and Bench Marks removed and/or altered during the construction shall be reset and certified "corner records" shall be submitted by the Land Surveyor, to the Engineer prior to the final acceptance of the construction. 19. UTILITIES The Contractor shall provide coordination with all the utility companies involved and shall provide protection from damage to their facilities. The Contractor shall be responsible for repair or replacement to said facilities made necessary by its failure to provide required protection. The Contractor is required to include utility requirements in the Construction Schedule. The Contractor shall notify all utility agencies and owners of all facilities within the area of construction a minimum of five (5) work days in advance of performing any work within said area. The Contractor shall protect all utilities and other improvements which may be impaired during construction operations. It shall be the Contractor's responsibility to ascertain the actual location of all existing utilities, including service laterals, and other improvements indicated on the drawings that will be encountered in its construction operations, and to see that such utilities or other improvements are adequately protected from damage due to such operations. The Contractor shall take all possible precautions for the protection of unforeseen utility lines to provide for uninterrupted service and to provide such special protection as may be directed by the Engineer. The Contractor shall be solely responsible to check all utility record maps, books, and/or other data in the possession of the City, other agencies, and/or all utility companies, and no allowance shall be made for any failure to have done so. It shall be the Contractor's responsibility to completely remove all "construction graffiti" (spray paint or other marking for utilities, survey points and construction limits) prior to acceptance of the work as completed. 48 hours prior to any excavation, the Contractor shall call "Underground Service Alert-Southern California" for utility locating in all public right-of-ways by calling 811. List of Utility Owners are listed in the Section D General Provisions of these contract documents and sheet 1 of the plans. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 37 of 63 Page: E.8 All utility structures, whether shown or not, within the street pavement rehabilitation shall be adjust to grade as follows: •Storm Drain and Sewer manhole frames and covers shall be adjusted to grade by the Contractor; •Water valves shall be adjusted to grade by the Contractor in coordination with the respective water company. The respective water company may provide new water valve covers otherwise the contractor will adjust the existing water cover; •SCE, Gas and Communication structures shall be adjusted by the respective purveyor. It shall be the Contractor responsibility to coordinate and notify the purveyors for the needs of their adjustment work. 20.TRAFFIC CONTROL REQUIREMENTS The Contractor shall provide a Traffic Control Plan prepared and signed by a licensed Engineer. The Contractor shall be responsible to furnish, install and maintain such devices which are necessary to provide safe and efficient passage for the traveling public through the work area, for the safety of personnel present in the work area, and to minimize inconvenience to adjacent properties. The Contractor shall be responsible to furnish, install and maintain such devices which are necessary to provide safe and efficient passage for the traveling public through the work area, for the safety of personnel present in the work area, and to minimize inconvenience to adjacent properties. All work and materials to implement construction staging and traffic control shall comply with the California Manual of Uniform Traffic Controls Device (CAMUTCD). Signs, markings, striping, barricades, delineators and all materials shall conform to applicable Caltrans standards and specifications. Arrow boards and other devises must comply with the City of Temple City requirements for nighttime noise standards at adjacent private property lines. The use of flagmen may be required if deemed so by the Engineer. Adequate flagmen, construction sign barricades, delineators, and arrow boards shall be used to the satisfaction of the Engineer. Adequate traffic control shall be maintained at all times through the construction zone, in compliance with the California Manual on Uniform Traffic Control Devices. It shall be the Contractor’s responsibility to notify affected businesses and residences within the project in writing within 10 days prior to the start of construction. Traffic control through the project area shall conform to the requirements of Section 7-10, “Public Convenience and Safety,” (SSPWC). Minimum Requirements for Maintaining Traffic Flow are: •The Contractor shall maintain one (1) minimum ten-foot-wide lanes in each direction at all times, and left turn pockets at all signalized intersections. •Driveways - The Contractor shall maintain access to each driveway at all times unless other arrangements have been made with each property owner, subject to approval by the Engineer. •The Contractor shall not allow traffic to travel on natural ground, subgrade, or aggregate base material. Traffic must only be allowed on a firm asphalt surface. A temporary ac pavement may be used for this reason to allow traffic. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 38 of 63 Page: E.9 •The Contractor shall not be allowed to leave vertical edge over 1.50” within the street pavement when the pavement is open to traffic except along the edge of gutter. Otherwise, the Contractor shall construct temporary AC transition at edges including around the edges of utility structures. •The transition at traverse edge to through traffic shall be 6:1 slope, at longitudinal edge shall be 4:1 slope and at driveways ramped at 6:1 slope. •The Contractor shall maintain a minimum of 5 feet clearance from the vertical edge of excavation. •All original traffic lanes shall be restored at the end of working hours each day. •If permanent pavement markings cannot be restored by the end of the work shift in which they were obliterated, temporary markings shall be provided by the Contractor prior to leaving the job site on all streets except any street closed to through traffic. These temporary markings shall be as follows: o Temporary lane lines and/or centerlines shall consist of day/night reflectorized raised pavement markers, approved by the City of Temple City, spaced approximately 24” apart. o Right edge lines shall not be simulated with dashes or pavement markers; however, portable delineators, guide markers, etc., may be used by the Contractor where it is considered desirable to enhance the edge of traveled way due to curvilinear alignment, narrowing pavement, etc., and shall be used when directed by the Engineer. The Contractor shall be responsible to periodically review the construction area at night to insure all lights are properly placed and operable. o Locations where no-passing zone centerline delineation has been obliterated shall be posted by the Contractor with a sign package consisting of a C18 (23) "ROAD CONSTRUCTION (WORK) AHEAD" and R63 "DO NOT PASS". o See other traffic requirements under other work sections. o Any deviation with these traffic requirements may be afforded only with the prior written approval of the Engineer. o See other traffic requirements under other work sections Holiday Period: No reduction in the number of lanes or in lane widths on any street shall be permitted during the holiday period which begins on the Monday prior to Thanksgiving and ends on the Friday following New Year's Day. Temporary No Parking Signs: The Contractor is responsible to post "Temporary No Parking" signs at least 5 working days in advance of the first date of enforcement. The City shall be informed before posting of signs. Parking will be restricted only for the minimum time necessary to complete on-going work. 21. CLEARING AND GRUBBING The following paragraphs shall be added to Subsection 300-1.3, Removal and Disposal of Materials of the SSPWC: •CONTRACTOR shall remove and transport debris and rubbish in a manner that will prevent spillage on streets or adjacent areas. Cleanup of spillage will be at CONTRACTOR’S expense. •Unless noted otherwise elsewhere on the contract documents, all materials indicated to be removed shall be recycled immediately at the CONTRACTOR’s expense at a site approved by the Engineer, per the requirements highlighted in Subsection E.7 above. No demolished materials shall be stored in the Work Area or Staging Area at any time, but instead shall be removed and recycled immediately. •Contractor shall not start any removal work unless it is prepared to perform reconstruction work CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 39 of 63 Page: E.10 immediately without interruption from the time removals begun, unless otherwise approved by the Engineer. •Prior to the removal of traffic loop, the Contractor shall contact the City Engineer to enable them to adjust the associated traffic signal timing. Subsection 300-1.3.2, “Bituminous Pavement”, (SSPWC), add the following •The existing AC pavement thicknesses are described in the Geotechnical/Pavement Engineering Report for TEMPLE CITY FY 19-20 PAVEMENT REHABILITATION prepared by Geo-Advantec, Inc dated November 1, 2019. In this report, it also indicates that there are reinforcing fabric interlayers along some segments of Las Tunas Dr. The fabric depths are approximately 2.0 to 3.5 inches below the pavement surface. •Miscellaneous Removals and Relocations. This item shall include all removals not specifically listed in the Bidder's Proposal or otherwise covered by these Specifications •such as all necessary relocations and restorations of water valves, manhole adjustment to grade and other items, whether shown on the Plans or not, and as necessary to complete the improvements. Contractor shall be responsible to review the project site prior to bidding and to include all such work, whether or not shown on the plan, in its bid prices for this item. •Limits. The Contractor shall meet with the Inspector prior to making removals to verify the limits of removals and the locations of joins, to establish smooth joins and to assure proper drainage. The Contractor may make minor changes in the location of joins and the limits of removals, provided a smooth join and proper drainage shall be achieved and it has obtained prior written approval from the City Engineer. 22. COLD MILLING AC PAVEMENT (3” DEEP) Cold mill shall conform to the provisions of Section 302.1 of the Standard Specifications. The Contractor shall cold mill existing AC pavement as specified on the plans. The Contractor shall take note of the existence of fabric in the AC pavement as indicated on the Geotechnical Report prepared by Geo-Advantec for Temple City Pavement Rehabilitation dated November 1, 2019. Cold milling shall remove 3” depth of AC to provide for placement of new AC paving overlay. The surface of pavement after cold milling shall be uniformly rough grooved or ridged as directed by the City Engineer. The grade shall not deviate from a suitable straight edge by more than 1/8” at any point. During the cold milling operation, the Contractor shall sweep the street with mechanical equipment and remove all loosened material from milled areas. The Contractor shall abate dust nuisance by cleaning, sweeping, and sprinkling with water (recycled water, if available) or other means as necessary. All Asphalt Concrete material covering existing concrete improvement shall be removed as directed by the City Engineer at no additional cost to the City. All materials to be removed as indicated on the plans shall be disposed of at a legal site as specified in subsection 300-1.3.1 of the Standard Specifications for Public Works Construction and Section E.7 of these Contract Documents. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 40 of 63 Page: E.11 After grinding and removing the specified thickness of the existing asphalt concrete layer and before adding the new asphalt concrete overlays, all damaged areas and cracks shall be repaired, sealed and patched properly. Cracks wider than ¼” should be sealed, loose pavement removed and patch, spalls repaired, and broken slabs or punch outs replaced. If any localized deep failure area is observed after grinding, the existing pavement section within such area should be completely removed and replaced with new asphalt concrete and base section. Payment for Cold Mill Existing AC Pavement (3” Deep) shall be made on a Square Foot (SF) Unit Price basis, and shall be considered full compensation for complying with the above requirements including the removal of reinforcement fabric embedded in the AC pavement, removal of all existing striping, legend, pavement marking, raised pavement markers, prepare area for asphalt application including chip seal application, crack sealing, remaining AC pavement section repair and solid waste management. 23.ASPHALT CONCRETE PAVEMENT All work shall conform to Section 302-5 and 400-4 of the “Standard Specifications for Public Works Construction” and these Special Provisions. Asphalt Concrete overlay along Las Tunas Dr. shall be 3” AC overlay consisting of 2” Asphalt Rubberized Hot Mix-Gap Graded wearing course on 1” thick leveling course, Type B-PG -10. A tack coat shall be applied to all surfaces when the wearing surface is not placed immediately following the leveling course and to all areas of joining existing pavement. Tack coat shall be Grade SS-1H, per Section 302-5.4 and shall be applied to the perimeter of all AC removal and replacement locations. (All tack coat overspray on gutter lip shall be removed.) Payment for AC Pavement overlay shall be per Ton (TON) Unit Price basis for AHRM and Asphalt Concrete as indicated in the Bid Schedule and shall be considered full compensation for complying with the above requirements. 24.ASPHALT CONCRETE PAVEMENT REMOVAL AND RECONSTRUCTION During construction at the direction of the Engineer, there will be some areas within the limit of the project that existing AC pavement section shall be removed and reconstructed. In general, the removal of AC pavement section shall be 10” deep consisting of the full depth of AC pavement portion of the pavement section plus varying depth of base. Per Geotech report, there are areas of the existing pavement section within the project limits that the AC pavement portion are more than 10” deep. In this case, remove full depth of the AC portion. Also, the Contractor shall take note that the existing AC pavement may have embedded fabric as reported in the Geotech report. The new AC pavement section shall consist of 2” ARHM wearing course on 2” AC leveling course, type B-PG 64-10 on 6” Crushed Aggregate Base. The thickness of the base may be increased due to the CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 41 of 63 Page: E.12 thickness of the existing Asphalt to be removed. Prior to placement of new pavement section, the exposed base shall be compacted to 90% relative compaction. The new aggregate base shall be compacted to 95% relative compaction prior to the placement of asphalt. Payment to remove and to reconstruct AC pavement section shall be paid per Square Feet of the area to be done and shall be considered full compensation for complying with the above requirements. 25.PAVEMENT STRIPING AND MARKERS All work shall conform to the latest edition of Caltrans Standard Plans, Standard Specifications, and California Manual on Uniform Traffic Control Devices (CAMUTCD). Traffic striping, raised pavement markers, reflective materials, the application of thermoplastic striping and pavement markings, and the installation of raised pavement markers shall conform to the provisions in the Caltrans Standard Specifications, Sections 84, “Traffic Stripes and Pavement Markings” and Section 85, “Pavement Markers”. Striping details, pavement legends and symbols shall conform to those in Caltrans Standard Plans. Pavement legends and symbols shall be white, unless noted otherwise. Lane line and/or centerline pavement delineation, where existing or called for on the Plans, shall be provided at all time for traveled ways open to public traffic. Whenever the Work causes obliteration of pavement delineation, temporary pavement delineation or permanent traffic stripes of the appropriate color and detail shall be in place. In the locations shown on the Plans, prior to opening the travelled way to public traffic. Striping shall be cat tracked and approved by the City Inspector prior to final installation. All conflicting existing striping, painted symbols and raised pavement markers shall be removed. The removal of painted markings and raised pavement markers shall conform to the provisions of the Caltrans Standard Specifications. Thermoplastic pavement marking materials and installation shall conform to Caltrans Standard Specifications Section 84-2. Materials shall consist of extruded Alkyd Binder Thermoplastic in conformance with State Specification 8010-19A. Application shall be by ribbon or extruded methods only (no spraying). All lane lines at intersection approaches and departures shall begin and end with 50-feet of 4-inch solid white line. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 42 of 63 Appendix A CITY STANDARD PUBLIC WORKS CONTRACT TO BE EXECUTED CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 43 of 63 1 CITY OF TEMPLE CITY PUBLIC WORKS CONTRACT PROJECT ____________________________________________________ THIS AGREEMENT (“Agreement”) is made and entered into this ____ day of _________________________, by and between the CITY OF TEMPLE CITY, a Municipal Corporation located in the County of Los Angeles, State of California (“CITY”), and ____________________________, [a corporation/partnership/limited liability company corporation, located at _____________________________ (“CONTRACTOR”), collectively referred to as the Parties. RECITALS A.CITY, by its Notice Inviting Bids, duly advertised for written bids to be submitted on or before ______________________________, for the following: __________________________________ __________________________________ in the City of Temple City, California (“Project”). B.At ________________ on said date, in the Temple City Council Chambers, the bids submitted for the Project were opened. C.At its regular meeting held on ________________________, the City Council of CITY accepted the bid of CONTRACTOR for the Project as being the lowest responsive bid received and directed that a written contract be entered into with CONTRACTOR. OPERATIVE PROVISIONS NOW, THEREFORE, in consideration of the promises and of the mutual covenants and agreements herein contained, the parties do hereby agree as follows: 1.CONTRACT DOCUMENTS. This Agreement consists of the following documents (“Contract Documents”), all of which are made a part of this Agreement: (a)Notice Inviting Bids (b)Instructions to Bidders (c)Bid Form (d)Bid Proposal and/or Contract Proposal, as accepted, including the Certificate of Bidders’ Experience and Qualifications and the List of Subcontractors CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 44 of 63 2 (e)Information Required by Bidder (f)Notice of Award (g)Notice to Proceed (h)This Agreement (i)Verification of California Contractor’s License (j)Contractor’s Certificate Regarding Workers’ Compensation (k)Security for payment (labor and materials) (l)Security for performance (m)Certificate(s) of Insurance (n)General Conditions/Specifications (o)Special Provisions (p)Plans and Standard Drawings (q)Prevailing Wage Scales (r)Standard Specifications for Public Works Construction, including subsequent addenda and supplements (s)Change orders issued by the City and signed by the Contractor pertaining to the Contract after the Contract is awarded to Contractor (t)All addenda issued by the City with respect to the foregoing prior to the opening of bids, including, Addenda Nos. _______. (u)Other documents (list here or delete) ________________________________________ ________________________________________ ________________________________________ In the event there is a conflict between the terms of the Contract Documents, the more specific or stringent provision shall govern. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 45 of 63 3 2.SCOPE OF WORK. CONTRACTOR agrees to perform all work required for the Project and to fulfill all other obligations as set forth in the Contract Documents (“Work”). Except as specifically provided in the Contract Documents, CONTRACTOR must furnish all of the labor, materials, tools, equipment, services and transportation necessary to perform all of the Work. CONTRACTOR must perform all of the Work in strict accordance with the Contract Documents. 3.COMPENSATION & PAYMENT. CONTRACTOR hereby agrees to receive and accept the total amount of ______________________ Dollars ($___________), based upon those certain unit prices set forth in CONTRACTOR’s Bid Schedule, a copy of which is attached hereto as Exhibit “A” and incorporated herein by this reference, as full compensation for the Work. Said compensation shall cover all expenses, losses, damages, and consequences arising out of the nature of the Work during its progress or prior to its acceptance, including those for well and faithfully completing the Work in the manner and time specified in the Contract Documents, and also including those arising form actions of the elements, unforeseen difficulties or obstructions encountered in the prosecution of the Work, suspension or discontinuance of the Work, and all other unknowns or risks of any description connected with the Work. CITY shall retain five percent (5%) of the compensation until the provisions of Section 14 herein have been met. CITY hereby agrees to pay CONTRACTOR at the time, in the manner, and upon the conditions set forth in the CONTRACT DOCUMENTS. 4.UNAUTHORIZED ALIENS. CONTRACTOR promises and agrees to comply with all of the provisions of State and Federal law with respect to the employment of unauthorized aliens, including without limitation the Federal Immigration and Nationality Act (8 USCA 1101, et seq.), as amended. Should CONTRACTOR employ one or more unauthorized aliens for the performance of the Work, and should the Federal Government impose sanctions against the CITY for such use of unauthorized aliens, CONTRACTOR hereby agrees to, and shall, reimburse CITY for the cost of all sanctions imposed, together with any and all costs, including attorney’s fees, incurred by the CITY in connection therewith. 5.REPRESENTATIONS AND WARRANTIES. CONTRACTOR hereby represents and warrants that: (a)It is not currently, and has not at any time within the past five (5) calendar years been, suspended, debarred, or excluded from participating in, bidding on, contracting for, or completing any project funded in whole or in part by program, grant or loan funded by the federal government or the State of California; and (b)CONTRACTOR currently has, and for the past five (5) calendar years has maintained in good standing, a valid California contractor’s license; and (c)CONTRACTOR is registered with the Department of Industrial Relations to perform services on public works projects as required by Labor Code section 1725.5. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 46 of 63 4 CONTRACTOR agrees to complete and execute any statement or certificate to this effect as may be required by the City or by any federal or State of California program, loan or grant utilized on this Project. 6.TIME TO PERFORM THE WORK. CONTRACTOR shall commence the Work on the date specified in the Notice to Proceed to be issued to CONTRACTOR by the Director of Public Works of CITY, and shall complete work on the Project within __________________ (___) days after commencement. 7.NONDISCRIMINATION. CONTRACTOR shall not discriminate in its recruiting, hiring, promotion, demotion or termination practices on the basis of race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, martial status, sex, age, or sexual orientation in the performance of this Agreement, and shall comply with the provisions of the California Fair Employment and Housing Act as set forth in Part 2.8 of Division 3, Title 2 of the California Government Code; the Federal Civil Rights Act of 1964, as set forth in Public Law 88-352, and all amendments thereto; Executive Order 11246; and all administrative rules and regulations issued pursuant to such acts and order. 8.LABOR CODE REQUIREMENTS. (a)CONTRACTOR is aware of and agrees to abide by the provisions of California Labor Code Sections 1720, et seq., as well as Sections 1771, 1773, 1773.1, 1773.6, 1773.7, 1774, 1775, 1776 and 1777, pertaining to the obligation to pay prevailing wages with respect to the performance of work (“Prevailing Wage Laws”). Copies of the prevailing rate of per diem wages and the general prevailing rate for holiday and overtime work for each craft are available upon request from the City. A copy of the prevailing rate of per diem wages shall be posted at the job site. If such posting is not possible, a copy shall be posted at the business of the CONTRACTOR. (b)CONTRACTOR acknowledges that under California Labor Code sections 1810 and following, eight hours of labor constitutes a legal day’s work. CONTRACTOR will forfeit as a penalty to City the sum of $25.00 for each worker employed in the execution of this Agreement by CONTRACTOR or any subcontractor for each calendar day during which such worker is required or permitted to work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of Labor Code section 1810. (Labor Code § 1813.) (c)CONTRACTOR must comply with Labor Code section 1771.1(a), which provides that CONTRACTOR is only eligible to perform the Work if CONTRACTOR is registered with the Department of Industrial Relations as required by Labor Code Section 1725.5, and that CONTRACTOR may award subcontracts for work that qualifies as a “public work” only to subcontractors which are at the time of award registered and qualified to perform public work pursuant to Labor Code Section 1725.5. CONTRACTOR must obtain proof of such registration from all such subcontractors. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 47 of 63 5 (d)CONTRACTOR, and any subcontractor engaged by CONTRACTOR, must pay not less than the specified prevailing rate of per diem wages to all workers employed in the execution of this Agreement. (Labor Code § 1774.) CONTRACTOR is responsible for compliance with Labor Code section 1776 relative to the retention and inspection of payroll records. (e)CONTRACTOR must comply with all provisions of Labor Code section 1775. Under Section 1775, Contractor may forfeit as a penalty to City up to $50.00 for each worker employed in the execution of the Agreement by CONTRACTOR or any subcontractor for each calendar day, or portion thereof, in which the worker is paid less than the prevailing rates. Contractor may also be liable to pay the difference between the prevailing wage rates and the amount paid to each worker for each calendar day, or portion thereof, for which each worker was paid less than the prevailing wage rate. (f)Nothing in this Agreement prevents CONTRACTOR or any subcontractor from employing properly registered apprentices in the execution of the Agreement. CONTRACTOR is responsible for compliance with Labor Code section 1777.5 for all apprenticeable occupations. This statute requires that contractors and subcontractors must submit contract award information to the applicable joint apprenticeship committee, must employ apprentices in apprenticeable occupations in a ratio of not less than one hour of apprentice’s work for every five hours of labor performed by a journeyman (unless an exception is granted under §1777.5), must contribute to the fund or funds in each craft or trade or a like amount to the California Apprenticeship Council, and that contractors and subcontractors must not discriminate among otherwise qualified employees as apprentices solely on the ground of sex, race, religion, creed, national origin, ancestry or color. Only apprentices defined in Labor Code section 3077, who are in training under apprenticeship standards and who have written apprentice contracts, may be employed on public works in apprenticeable occupations. (g)CONTRACTOR shall defend, indemnify and hold the CITY, its elected officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. 9.PROJECT SITE CONDITIONS. (a)CONTRACTOR shall, without disturbing the condition, notify CITY in writing as soon as CONTRACTOR, or any of CONTRACTOR’s subcontractors, agents or employees have knowledge and reporting is possible, of the discovery of any of the following conditions: (i)The presence of any material that the CONTRACTOR believes is hazardous waste, as defined in Section 25117 of the Health and Safety Code; (ii)Subsurface or latent physical conditions at the site differing from those indicated in the specifications; or, CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 48 of 63 6 (iii)Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of this character provided for in this Agreement. (b)Pending a determination by CITY of appropriate action to be taken, CONTRACTOR shall provide security measures (e.g., fences) adequate to prevent the hazardous waste or physical conditions from causing bodily injury to any person. (c)CITY shall promptly investigate the reported conditions. If CITY, through its Director of Public Works, or his or her designee, and in the exercise of its sole discretion, determines that the conditions do materially differ, or do involve hazardous waste, and will cause a decrease or increase in the CONTRACTOR’s cost of, or time required for, performance of any part of the Work, then CITY shall issue a change order. (d)In the event of a dispute between CITY and CONTRACTOR as to whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the CONTRACTOR’s cost of, or time required for, performance of any part of the Work, CONTRACTOR shall not be excused from any scheduled completion date, and shall proceed with all work to be performed under the Agreement. CONTRACTOR shall retain any and all rights which pertain to the resolution of disputes and protests between the parties. 10.INDEMNITY. CONTRACTOR shall assume the defense of and indemnify and hold harmless the CITY, its elective and appointive boards, officers, agents and employees, from all claims, loss, damage, injury and liability of every kind, nature and description, directly or indirectly arising form the performance of the Work, regardless of responsibility of negligence; and from any and all claims, loss, damage, injury and liability, resulting directly or indirectly from the nature of the Work covered by this Agreement, regardless of responsibility of negligence. (a)CITY does not, and shall not, waive any rights against CONTRACTOR which it may have because of the acceptance by CITY or the deposit with CITY by CONTRACTOR, of any of the insurance policies hereinafter described in this Agreement. (b)The indemnity provided by CONTRACTOR shall apply to all damages and claims for damages of every kind suffered, or alleged to have been suffered, by reason of any of the Work by CONTRACTOR, or any subcontractor, regardless of whether insurance policies are applicable to any of the damages or claims for damages. (c)The provisions of this section do not apply to claims occurring as a result of the City’s sole negligence or willful acts or omissions. (d)The provisions of this section will survive the expiration or earlier termination of this Agreement. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 49 of 63 7 11.BONDS. CONTRACTOR, before commencing the Work, shall furnish and file with CITY a bond, or bonds, in a form satisfactory to the CITY, in the sum of one hundred percent (100%) of the compensation amount stated in Section 3 of this Agreement conditioned upon the faithful performance of this Agreement and a bond, or bonds, in a form satisfactory to the CITY, in the sum of one hundred percent (100%) of the compensation amount stated in Section 3 of this Agreement conditioned upon the payment of all labor and materials furnished in connection with this Agreement. 12.INSURANCE. CONTRACTOR shall not commence the Work until CONTRACTOR has obtained all insurance required by the Contract Documents and such insurance has been approved by CITY as to form, amount and carrier. CONTRACTOR shall not allow any subcontractor to commence work on any subcontract until all similar insurance required of the subcontractor have been obtained and approved. (a)Workers’ Compensation. CONTRACTOR shall take out and maintain, during the life of this Agreement, Worker’s Compensation Insurance (Statutory Limits) with Employers Liability Insurance (with limits of at least $1,000,000) for all of CONTRACTOR’s employees employed at the Project site; and, if any work is sublet, CONTRACTOR shall require the subcontractor similarly to provide Worker’s Compensation Insurance for all of the latter’s employees, unless such employees are covered by the protection afforded by CONTRACTOR. If any class of employees engaged in Work under this Agreement at the Project site is not protected under any Workers’ Compensation law, CONTRACTOR shall provide and shall cause each subcontractor to provide adequate insurance for the protection of employees not otherwise protected. CONTRACTOR shall indemnify CITY for any damage resulting from failure of either CONTRACTOR or any subcontractor to take out or maintain such insurance. CONTRACTOR shall submit to Agency, along with the certificate of Insurance, a Waiver of Subrogation endorsement in favor of the Agency, its officers, agents, employees and volunteers. (b)Comprehensive General Liability, Products/Completed Operations Hazard, and Contractual General Liability Insurance. CONTRACTOR shall take out and maintain during the life of this Agreement such comprehensive general liability, products/completed operations hazard, comprehensive automobile liability and contractual general liability insurance as shall protect CITY, its elective and appointive boards, officers, agents and employees, CONTRACTOR, and any subcontractor performing work covered by this Agreement, from claims for damage for personal injury, including death, as well as from claims for property damage which may arise from CONTRACTOR’s or any subcontractor’s operations under this Agreement, whether such operations be by CONTRACTOR or by any subcontractor, or by anyone directly or indirectly employed by either CONTRACTOR or any subcontractor, and the amounts of such insurance shall be as follows: CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 50 of 63 8 (i)General Liability Insurance in an amount of not less than ONE MILLION DOLLARS ($1,000,000) per occurrence; (ii)Products/Completed Operations Hazard Insurance in an amount of not less than ONE MILLION DOLLARS ($1,000,000) per occurrence; and (iii)Contractual General Liability Insurance in an amount of not less than ONE MILLION DOLLARS ($1,000,000) per occurrence. General aggregate limits in an amount of not less than TWO MILLION DOLLARS ($2,000,000) shall be considered equivalent to the required minimum limits set forth hereinabove. (c)Comprehensive Automobile Liability. CONTRACTOR shall take out and maintain during the life of this Agreement, comprehensive automobile liability insurance as shall protect CITY, its elective and appointive boards, officers, agents and employees, CONTRACTOR, and any subcontractor performing work covered by this Agreement, from claims for damage for personal injury, including death, as well as from claims for property damage which may arise from CONTRACTOR’s or any subcontractor’s operations under this Agreement, whether such operations be by CONTRACTOR or by any subcontractor, or by anyone directly or indirectly employed by either CONTRACTOR or any subcontractor, and the amounts of such insurance shall be as follows: (i)Comprehensive Automobile Liability Insurance in an amount of not less than ONE MILLION DOLLARS ($1,000,000) combined single limit per accident. (d)Proof of Insurance. The insurance required by this Agreement shall be with insurers which are California Admitted and Best A rated or better. CITY shall be named as “additional insured” on the general liability and automobile liability required hereunder, and CONTRACTOR shall furnish CITY, concurrently with the execution hereof, with satisfactory proof of carriage of the insurance required, and adequate legal assurance that each carrier will give CITY at least thirty (30) days’ prior notice of the cancellation of any policy during the effective period of this Agreement. (e)Umbrella or excess liability insurance. [Optional depending on limits required]. Contractor shall obtain and maintain an umbrella or excess liability insurance policy with limits that will provide bodily injury, personal injury and property damage liability coverage at least as broad as the primary coverages set forth above, including commercial general liability and employer’s liability. Such policy or policies shall include the following terms and conditions: •A drop down feature requiring the policy to respond if any primary insurance that would otherwise have applied proves to be uncollectible in whole or in part for any reason; •Pay on behalf of wording as opposed to reimbursement; CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 51 of 63 9 •Concurrency of effective dates with primary policies; and •Policies shall “follow form” to the underlying primary policies. •Insureds under primary policies shall also be insureds under the umbrella or excess policies. (f)Requirements not limiting. Requirements of specific coverage features or limits contained in this Section are not intended as a limitation on coverage, limits or other requirements, or a waiver of any coverage normally provided by any insurance. Specific reference to a given coverage feature is for purposes of clarification only as it pertains to a given issue and is not intended by any party or insured to be all inclusive, or to the exclusion of other coverage, or a waiver of any type. If the CONTRACTOR maintains higher limits than the minimums shown above, the Agency requires and shall be entitled to coverage for the higher limits maintained by the CONTRACTOR. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the Agency. (g)Primary/contributing. Coverage provided by the CONTRACTOR shall be primary and any insurance or self-insurance or maintained by Agency shall not be required to contribute to it. The limits of insurance required herein may be satisfied by a combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and non-contributory basis for the benefit of Agency before the Agency’s own insurance or self-insurance shall be called upon to protect is as a named insured. (h)Notice to Proceed. The CITY will not issue any notice authorizing CONTRACTOR or any subcontractor to commence the Work under this Agreement until CONTRACTOR has provided to the CITY the proof of insurance as required by this Section 12. 13.LIQUIDATED DAMAGES. The parties agree that it would be impractical and extremely difficult to fix the actual damages to the CITY in the event the Project is not commenced and/or completed on or before the dates specified for commencement and completion of the Project in the Contract Documents. The parties have considered the facts of a breach of this Agreement and have agreed that the liquidated damages sum hereinafter set forth is reasonable as liquidated damages in the event of a breach, and that said sum shall be presumed to be the amount of the damages sustained by the CITY in the event such work is not begun and/or completed and accepted by the times so specified in the Contract Documents. The sum of ONE THOUSAND DOLLARS ($1,000.00) shall be presumed to be the amount of damages suffered by the CITY for each day’s delay in the starting and/or completion and acceptance of the Project after the dates specified in the Contract Documents for the start and/or completion thereof, and CONTRACTOR hereby agrees to pay said sum of ONE THOUSAND DOLLARS ($1,000.00) as liquidated damages for each day of delay in the starting and/or completing and acceptance of said Project beyond the dates specified in the CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 52 of 63 10 CONTRACT DOCUMENTS. Any and all such liquidated damages assessed shall be done in accordance with that certain edition of the Standard Specification for Public Works Construction currently in effect on the execution date of this Agreement. CONTRACTOR CITY OF TEMPLE CITY By ___________________________ By __________________________ Date: Date: 14.NOTICE OF COMPLETION. Upon completion of PROJECT and acceptance of same by the City Council of the CITY, the City Manager of the CITY shall cause to be recorded a Notice of Completion with the office of the Los Angeles County Recorder; and, after thirty-five (35) days from the date said Notice of Completion is recorded, the Director of Finance of CITY shall release the funds retained pursuant to Section 3 hereof; provided there have been no mechanics’ liens or stop notices filed against the Work which have not been paid, withdrawn or eliminated as liens against said work. 15.COMPLIANCE WITH LAWS. In performing the Work, CONTRACTOR must comply with all applicable statutes, laws and regulations, including, but not limited to, OSHA requirements and the Temple City Municipal Code. Contractor must, at Contractor’s sole expense, obtain all necessary permits and licenses required for the Work, and give all necessary notices and pay all fees and taxes required by law, including, without limitation, any business license tax imposed by City. 16.INDEPENDENT CONTRACTOR. CONTRACTOR is and will at all times remain as to CITY a wholly independent contractor. Neither the CITY nor any of its officers, employees, or agents will have control over the conduct of CONTRACTOR or any of CONTRACTOR’s officers, employees, agents or subcontractors, except as expressly set forth in the Contract Documents. CONTRACTOR may not at any time or in any manner represent that it or any of its officers, employees, agents, or subcontractors are in any manner officers, employees, agents or subcontractors of CITY. 17.GENERAL PROVISIONS. (a)Authority to Execute. Each Party represents and warrants that all necessary action has been taken by such Party to authorize the undersigned to execute this Agreement and to bind it to the performance of its obligations. (b)Assignment. CONTRACTOR may not assign this Agreement without the prior written consent of CITY, which consent may be withheld in the CITY’s sole discretion since the experience and qualifications of CONTRACTOR were material considerations for this Agreement. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 53 of 63 11 (c)Binding Effect. This Agreement is binding upon the heirs, executors, administrators, successors and permitted assigns of the Parties. (d) Integrated Agreement. This Agreement, including the Contract Documents, is the entire, complete, final and exclusive expression of the Parties with respect to the Work to be performed under this Agreement and supersedes all other agreements or understandings, whether oral or written, between CONTRACTOR and CITY prior to the execution of this Agreement. (e)Modification of Agreement. No amendment to or modification of this Agreement will be valid unless made in writing and approved by CONTRACTOR and by the City Council or City Manager of CITY, as applicable. The Parties agree that this requirement for written modifications cannot be waived and that any attempted waiver will be void. (f)Counterparts and Facsimile Signatures. This Agreement may be executed in several counterparts, each of which will be deemed an original, and all of which, when taken together, constitute one and the same instrument. Amendments to this Agreement will be considered executed when the signature of a party is delivered by facsimile transmission. Such facsimile signature will have the same effect as an original signature. (g)Waiver. Waiver by any Party of any term, condition, or covenant of this Agreement will not constitute a waiver of any other term, condition, or covenant. Waiver by any Party of any breach of the provisions of this Agreement will not constitute a waiver of any other provision, or a waiver of any subsequent breach or violation of any provision of this Agreement. Acceptance by City of any Work performed by CONTRACTOR will not constitute a waiver of any of the provisions of this Agreement. (h)Interpretation. This Agreement will be interpreted, construed and governed according to the laws of the State of California. Each party has had the opportunity to review this Agreement with legal counsel. The Agreement will be construed simply, as a whole, and in accordance with its fair meaning. It will not be interpreted strictly for or against either party. (i)Severability. If any term, condition or covenant of this Agreement is declared or determined by any court of competent jurisdiction to be invalid, void or unenforceable, the remaining provisions of this Agreement will not be affected and the Agreement will be read and construed without the invalid, void or unenforceable provision. (j)Attorneys’ Fees. The prevailing party in any action to resolve a dispute concerning this Agreement shall be entitled to have and recover from the losing party the reasonable attorneys’ fees and costs of such action. (k)Venue. In the event of litigation between the parties, venue in state trial courts will be in the County of Los Angeles. In the event of litigation in a U.S. District Court, venue will be in the Central District of California, in Los Angeles. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 54 of 63 12 (l)Notices. All written notices required or permitted to be given under this Agreement will be deemed made when received by the other Party at its respective address as follows: To CITY: City of Temple City 9701 Las Tunas Drive Temple City, California 91780 Attention: ____________ (Tel.) _______________ (Fax) _______________ To Contractor: ______________________ ______________________ ______________________ Attention: ______________ (Tel.) _____________ (Fax) _____________ Notice will be deemed effective on the date personally delivered or transmitted by facsimile. If the notice is mailed, notice will be deemed given three days after deposit of the same in the custody of the United States Postal Service, postage prepaid, for first class delivery, or upon delivery if using a major courier service with tracking capabilities. Any Party may change its notice information by giving notice to the other Party in compliance with this section. CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 55 of 63 13 IN WITNESS WHEREOF, the parties hereto have caused this contract to be executed on the _____ day of _____________________, 20__, by their respective officers duly authorized in that behalf. CITY OF TEMPLE CITY, a municipal corporation ATTEST: By______________________________ ___________________ _______________________________ Peggy Kuo, City Clerk Date: APPROVED AS TO FORM: ___________________________________ Eric S. Vail, City Attorney _____________________, a [state type of entity] By______________________________ _____________________, ________ By______________________________ _____________________, ________ CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 56 of 63 14 LA #4847-5837-1653 v1 DRAFT 3/23/17 CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 57 of 63 15 LA #4847-5837-1653 v1 DRAFT 3/23/17 CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 58 of 63 Appendix B PROJECT PLANS CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 59 of 63 CITY OF TEMPLE CITY PUBLIC WORKS AND ENGINEERING DEPARTMENT LOCATION MAP INDEX TO PROJECT DRAWINGS VICINITY MAP 1.UNLESS OTHERWISE NOTED, ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE "STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION", LATEST EDITION WITH ALL CURRENT SUPPLEMENTS, AND ALL APPLICABLE STANDARDS AND SPECIFICATIONS TO THE SATISFACTION OF THE ENGINEER. 2. PRIOR TO BEGINNING OF ANY WORK, THE CONTRACTOR SHALL OBTAIN A PERMIT FROM THE CITY OF TEMPLE CITY. 3. ALL WORK COVERED BY THIS PLAN SHALL BE INSPECTED BY THE CITY ENGINEER. 4. THE CONTRACTOR SHALL NOTIFY UNDERGROUND SERVICE ALERT (U.S.A.) 48 HOURS PRIOR TO THE START OF WORK. UPON EXPOSING ANY UTILITY'S UNDERGROUND FACILITY, THE CONTRACTOR SHALL NOTIFY UTILITY IMMEDIATELY. 5. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO LOCATE ALL UTILITIES OF EVERY NATURE, WHETHER SHOWN HEREON OR NOT, TO PROTECT THEM FROM DAMAGE WITHIN THE ALIGNMENT OF THE PROPOSED IMPROVEMENTS. THE CONTRACTOR SHALL BEAR THE TOTAL EXPENSE OF REPAIR OR REPLACEMENT OF UTILITIES DAMAGED BY OPERATIONS IN CONNECTION WITH THE PROSECUTION IF THE WORK. 6. THE CONTRACTOR SHALL NOT CONDUCT ANY OPERATIONS OR PERFORM ANY WORK PERTAINING TO THE PROJECT BETWEEN 5:00 P.M. AND 7:30 A.M. ON ANY DAY NOR ON SATURDAY, SUNDAY, HOLIDAY AT ANY TIME EXCEPT AS APPROVED BY THE ENGINEER. 7. THE CONTRACTOR SHALL PROTECT AND RESTORE EXISTING UTILITIES AND IMPROVEMENTS AS PER SECTION 5-1, 5-2- AND 7-9 OF THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION. 8. THE CONTRACTOR IS ADVISED THAT UNLESS NOTED OTHERWISE IN THE CONTRACT DOCUMENTS, ALL MATERIALS REMOVED UNDER CLEARING AND GRUBBING SHALL BECOME THE PROPERTY OF THE CONTRACTOR AND SHALL BE REMOVED DISPOSED FROM THE JOBSITE UNLESS INSTRUCTED BY THE ENGINEER TO DO OTHERWISE. 9. THE CONTRACTOR SHALL BE RESPONSIBLE TO PROVIDE FOR PUBLIC SAFETY AND CONVENIENCE AND SECURE THE PROJECT AS WELL AS ADJOINING PROPERTIES DURING THE DURATION OF PROJECT. 10. THE CONTRACTOR SHALL ADJUST MANHOLE FRAME AND COVER AND WATER VALVE CANS TO FINISH GRADE UNLESS NOTED OTHERWISE ON THE PLAN. 11. THE CONTRACTOR SHALL PROVIDE A TRAFFIC CONTROL PLAN FOR THE COMPLETION OF THE PROPOSED IMPROVEMENTS PER CA MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD) TO THE SATISFACTION OF THE ENGINEER. A MINIMUM OF ONE LANE OF TRAFFIC SHALL BE MAINTAINED AT ALL TIMES DURING WORKING HOURS. ALL LANES SHALL BE RESTORED AFTER WORK HOURS UNLESS APPROVED OTHERWISE BY THE ENGINEER. 12. THE CONTRACTOR SHALL PROVIDE 72-HOUR NOTIFICATION TO THE AFFECTED PROPERTIES, POLICE DEPARTMENT AND FIRE DEPARTMENT IN THE EVENT OF A CHANGE IN STREET CLOSURE TO TRAFFIC AND/OR PUBLIC SAFETY VEHICLES, PARKING RESTRICTION, AND ON EACH MONDAY DURING THE CONSTRUCTION PERIOD. 13. AS REQUIRED BY THE ENGINEER, THE CONTRACTOR SHALL FURNISH AND OPERATE A SELF-LOADING MOTOR SWEEPER WITH SPRAY NOZZLES AT LEAST TWICE EACH WORKING DAY TO KEEP PAVED AREAS ACCEPTABLY CLEAN WHEREVER CONSTRUCTION, INCLUDING RESTORATION THAT IS INCOMPLETE. 14. ALL EXISTING PORTLAND CEMENT CONCRETE (P.C.C.) AND ASPHALT CONCRETE PAVEMENT SHALL BE SAWCUT, FULL DEPTH, TO A TRUE LINE WHERE NEW CONCRETE PAVEMENT IS TO JOIN. 15. ALL EXCAVATION SHALL BE BACKFILLED AT THE END OF EACH WORKING DAY AND ROAD OPEN TO VEHICULAR TRAFFIC UNLESS APPROVED BY THE ENGINEER. 16. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO NOTIFY AND COORDINATE WITH ALL AFFECTED UTILITY PURVEYORS OF THE WORK REQUIRED TO ADJUST AND/OR RELOCATE UTILITY FACILITIES. 17. THE FOLLOWING IS A LIST OF THE UTILITY COMPANIES AND CONTACTS: JOHANNA MUNOZ (626) 303-8473 SOUTHERN CALIFORNIA EDISON CARLOS SANCHEZ (626) 397-4970 SOUTHERN CALIFORNIA GAS COMPANY ANNA LIMAS (626) 570-5314 AT&T JESSE GONZALES (626) 430-3570 CHARTER COMMUNICATION LA COUNTY SEWER MAINTENANCE DISTRICT (626) 300-3399 WAYNE GOEHRING (626) 793-6189 EAST PASADENA WATER COMPANY (GARABALDI AVE TO E. CAMINO REAL AVE) TROY (626) 287-5238 SUNNY SLOPE WATER COMPANY (LIVE OAK AVE TO GARIBALDI AVE.) LOUIE ROMERO (626) 614-2534 CALIFORNIA AMERICAN WATER CO (BLACKLEY ST TO LIVE OAK AVE) (ELLIS LANE TO LOWER AZUSA RD.) BOB NILA (626) 446 1547 GOLDEN STATE WATER CO LOWER AZUSA RD TO BLACKLEY ST GENERAL NOTES FOUR PROJECT SITE 1. 2. ALL TRAFFIC CONTROL WORK FOR CONSTRUCTION SHALL CONFORM TO PART 6- TEMPORARY TRAFFIC CONTROL OF THE CA-MUTCD, ADDENDUMS, LATEST EDITIONS, AND ALL O.S.H.A. REQUIREMENTS. 3. THE CONTRACTOR SHALL HAVE ALL TRAFFIC CONTROL SIGNS, DELINEATORS, ETC., PROPERLY INSTALLED PRIOR TO COMMENCING CONSTRUCTION. 4. THE CONTRACTOR SHALL MAINTAIN ALL TRAFFIC CONTROL SIGNS, DELINEATORS, ETC., TO ENSURE PROPER FLOW AND SAFETY OF TRAFFIC WHILE WORKING IN THE STREET. 5. ADDITIONAL TRAFFIC CONTROL DEVICES MAY BE REQUIRED IN THE FIELD. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY ADDITIONAL TRAFFIC CONTROL DEVICES REQUIRED BY THE CITY INSPECTOR/REPRESENTATIVES TO ASSURE PUBLIC SAFETY AT ALL TIMES. NO ADDITIONAL COMPENSATION WILL BE ALLOWED. 6. THE CONTRACTOR SHALL UTILIZE A FLAGMAN DURING CONSTRUCTION WORK AS DEEMED NECESSARY BY THE AGENCY REPRESENTATIVE. ARROW BOARDS SHALL BE USED ON ANY LANE CLOSURE ON ARTERIAL STREETS. STRIPING SHALL BE CAT TRACKED AND APPROVED BY THE AGENCY REPRESENTATIVE PRIOR TO FINAL INSTALLATION.7. MAINTAIN TWO TRAFFIC LANES ON BOTH DIRECTIONS AT ALL TIMES.8. ALL TRAFFIC LANES MUST BE OPEN ON WEEKENDS AND HOLIDAYS.9. ANY DEVIATION TO THE TRAFFIC LANE REQUIREMENTS SHALL REQUIRE THE CITY ENGINEER'S APPROVAL. A MINIMUM 2410. HOURS ADVANCE NOTICE IS REQUIRED. PAVEMENT MANAGEMENT PROGRAM PROJECT PHASE 2 CITY PROJECT ID: P 20-07 GENERAL SIGNING, STRIPING AND MARKING NOTES:TEMPLE CITY BLVD13367 BENSON AVE. CHINO, CA. 91710 (909) 595 8599 PAVEMENT MANAGEMENT PROGRAM CITY PROJECT ID: P 20-07 STREET RESURFACING PROJECT PHASE 2 1 4 TITLE SHEET LAS TUNAS D R TRAFFIC CONSTRUCTION NOTES PARKING TEE DETAIL STREET IMPROVEMENT CONSTRUCTION NOTES –SULTANA AVEROWLAND AVECC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 60 of 63 STOPLAS TUNAS DR LAS TUNAS DR 13367 BENSON AVE. CHINO, CA. 91710 (909) 595 8599 PAVEMENT MANAGEMENT PROGRAM CITY PROJECT ID: P20-07 STREET RESURFACING PROJECT PHASE 2 150' 80' – TRAFFIC CONSTRUCTION NOTES 2 4 ROADWAY IMPROVEMENT PLANSLIMIT OF WORKLI M I T LIMIT LIMIT LIMIT STREET IMPROVEMENT CONSTRUCTION NOTES LIMIT LIMIT LIMIT LIMIT LIMIT CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 61 of 63 LAS TUNAS DR LAS TUNAS DR 13367 BENSON AVE. CHINO, CA. 91710 (909) 595 8599 PAVEMENT MANAGEMENT PROGRAM CITY PROJECT ID: P20-07 STREET RESURFACING PROJECT PHASE 2 STREET IMPROVEMENT CONSTRUCTION NOTES 3 4 ROADWAY IMPROVEMENT PLANS 50' TRAFFIC CONSTRUCTION NOTES – LIMIT LIMIT LIMIT LIMIT LIMIT LIMIT LIMIT LIMIT LIMIT CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 62 of 63 STOPSTOP LAS TUNAS DR STOPSTOP LAS TUNAS DR 13367 BENSON AVE. CHINO, CA. 91710 (909) 595 8599 PAVEMENT MANAGEMENT PROGRAM CITY PROJECT ID: P20-07 STREET RESURFACING PROJECT PHASE 2 4 4 ROADWAY IMPROVEMENT PLANS LIMIT LIMIT LIMIT LIMIT LIMIT LIMIT TRAFFIC CONSTRUCTION NOTES – STREET IMPROVEMENT CONSTRUCTION NOTES LIMIT LIMIT CC STAFF REPORT ATTACHMENT A - PLANS (DRAFT BID PACKAGE) NOT AUTHORIZED FOR BID RELEASE July 15, 2020 Document Control Page 63 of 63 QUANTITY NO. UNITS UNIT MEAS. 1 3" COLD MILL ASPHALT PAVEMENT 360,000 SF $1.00 $360,000.00 2 CONSTRUCT ASPHALT RUBBER HOT MIX-GAP GRADE (ARHM-GG-C)4,700 TONS $120.00 $564,000.00 3 CONSTRUCT ASPHALT CONCRETE TYPE B-PG 64-10 2,700 TONS $110.00 $297,000.00 4 SAWCUT AND REMOVE 10" THICK AC/BASE PAVEMENT SECTION AND RECONSTRUCT 10" AC PAVEMENT SECTION CONSISTING OF 2" AHRM ON 2" AC (TYPE B-PG 64-10) ON 6" CAB (AREA TO BE DETERMINED BY THE ENGINEER DURING CONSTRUCTION) 10,000 SF $10.00 $100,000.00 5 REMOVE EXISTING MARKINGS AND STRIPING IN EXISTING PCC CONCRETE SURFACES ON LAS TUNAS (WEST ND EAST OF TEMPLE CITY), AND REINSTALL NEW STRIPING MARKINGS. (ALL STRIPING SHALL COMPLY WITH CURRENT STANDARDS, AND SHALL HAVE RAISED MARKERS AS SHOWN ON GOOGLE AERIALS.) 1 LS $4,500.00 $4,500.00 6 RESTORE ALL MARKINGS AND STRIPING (ALL STRIPING SHALL COMPLY WITH CURRENT STANDARDS, AND SHALL HAVE RAISED MARKERS AS SHOWN ON GOOGLE AERIALS.) 1 LS $150,000.00 $150,000.00 7 REMOVE AND RESTORE TRAFFIC LOOP DETECTOR (WITH VARYING, SHAPE & SIZES)85 EA $800.00 $68,000.00 8 ADJUST STORM DRAIN/SEWER MANHOLE FRAME AND COVER TO GRADE 16 EA $700.00 $11,200.00 9 ADJUST VALVE COVER TO GRADE . THIS ITEM WILL ONLY PAY IF THE WORK IS PERFORMED BY THE CONTRACTOR. IF THE WORK IS PERFORMED BY THE OWNER OF A VALVE (UTILITY OWNER) NO PAYMENT WILL MADE TO THE CONTRACTOR. 70 EA $100.00 $7,000.00 10 TRAFFIC CONTROL 1 LS $150,000.00 $150,000.00 11 THIS IS A CITY ESTABLISHED ALLOWANCE FOR MISC. PCC SIDEWALK REPAIRS IF SUCH WORK IS APPROVED BY THE CITY. THIS AMOUNT MAY ONLY BE USED AT CITY'S DISCRETION. 1 LS $50,000.00 $50,000.00 $1,761,700.00 10%$176,170.00 $1,937,870.00 20%$387,574.00 $2,325,444.00Total CC STAFF REPORT ATTACHMENT B - PROJECT COST ESTIMATE ITEM NO.UNIT PRICE TOTAL PRICE LAS TUNAS BLVD PAVEMENT REHABILITATION, PHASE 2 FROM SULTANA AVE TO EAST CITY LIMIT (West of Baldwin Ave) CITY PROJECT ID: P-20-07 City of Temple City DESCRIPTION OF ITEM Sub Total Industry Standard Contingency Allocation Total Industry Standard Soft Cost Allocation CC STAFF REPORT ATTACHMENT B -PROJECT COST ESTIMATE PAGE 1 OF 1 ATTACHMENT B