HomeMy Public PortalAbout060_DPW Qtr 3 Report 2011DPW Quarter 3, FY 2011
Projects
1) McKenzie Street Drainage
Man Hrs Equipment Materials Labor Total
416 $7,800.00 $2,023.10 $10,400.00 $20,223.10
2) Install New Palms at 14th Street
Man Hrs Equipment Materials Labor Total
368 $5,250.00 $7,268.00 $9,200.00 $21,718.00
3) 11th Street Drainage
Man Hrs Equipment Materials Labor Total
160 $3,000.00 $2,000.19 $4,000.00 $9,000.19
4) Polk Street Drainage
Man Hrs Equipment Materials Labor Total
240 $4,500.00 $714.03 $6,000.00 $11,214.03
5) Police Department Renovations
Man Hrs Equipment Materials Labor Total
440 $0.00 $2,109.52 $11,000.00 $13,109.52
Maintenance
Clean, Restock, and Maintaining Facilities, Restrooms, and Parks
Man Hrs Equipment Materials Labor Total
657 $750.00 $1,498.05 $16,425.00 $18,673.05
Cutting grass, Ditches, Trimming and Landscaping
Man Hrs Equipment Materials Labor Total
1,547 $12,367.50 $612.00 $38,675.00 $51,654.50
Cleaning up Street Trash and Barrels (including street sweeper)
Man Hrs Equipment Materials Labor Total
271.5 $10,290.00 $0.00 $6,787.50 $17,077.50
Cleaning up Beaches and Trash
Man Hrs Equipment Materials Labor Total
144 $1,800.00 $0.00 $3,600.00 $5,400.00
Fixing, Replacing, and Installing New Signs
Man Hrs Materials Materials Labor Total
12 $0.00 $0.00 $300.00 $300.00
Island-wide Road Repair & Maintenance
Man Hrs Equipment Materials Labor Total
72 $1,350.00 $1,041.12 $1,800.00 $4,191.12
Maintaining Beaches (Swings, Mobi-Mats, and Crossovers)
Man Hrs Equipment Materials Labor Total
120 $0.00 $0.00 $3,000.00 $3,000.00
Drainage Maintenance
Man Hrs Equipment Materials Labor Total
96 $1,800.00 $0.00 $2,400.00 $4,200.00
Holidays & Festivals
Removal of December Holiday Lighting and Decorations
Man Hrs Equipment Materials Labor Total
114.5 $0.00 $0.00 $2,862.50 $2,862.50
Mardi Gras
Man Hrs Equipment Materials Labor Total
16 $560.00 $0.00 $400.00 $960.00
Irish Heritage Festival
Man Hrs Equipment Materials Labor Total
22 $50.00 $450.00 $550.00 $1050.00
Work Orders
DPW, Building Maintenance and Parks & Rec. have completed 92 Work Orders for the following departments this quarter:
YMCA - 6
Campground - 9
Police Dept. - 6
M.S.C. - 9
Fire Dept. / TEMA - 9
DPW - 18
Facilities, Parks, and Restrooms - 9
Parking -7
City Hall & Resident Requests and Observations - 19
Fleet Department
The Fleet Department has completed 96 Service and Repair Orders for the following departments this quarter:
Campground - 2 Parts: $69.58 Labor: $181.25
DPW - 51 Parts: $7,033.72 Labor: $2,937.50
Fire Department - 9 Parts: $838.63 Labor: $612.50
Parking - 4 Parts: $229.82 Labor: $300.00
Police Dept. - 23 Parts: $2,416.81 Labor: $3,600.00
Water/ Sewer - 7 Parts: $377.13 Labor: $400.00
Totals: Parts: $10,965.69 Labor: $8,031.25 Total: $18,996.94
Total time spent on research, ordering parts, picking up parts, inventory, paperwork and filing, and cleaning the shop:
Man hours 558.25 Cost in labor: $13,956.25
Purchasing
243 Purchase Orders have been made this quarter amounting to $96,498.11
Major Purchases
-2nd Ave. Mobi-Mat from Deschamps $19,999.00
-HVAC and Electrical repairs to YMCA Gym by Weather Doctors and C.S. Hurd Electrical $9,961.00
-New Palms for 14th St (including auger rental) $7,268.00
-Repair fan in street sweeper $5,092.70
- Set up for new re-used oil system in fleet garage from Northern Tool $3,337.74
Completed Training:
One Employee is currently enrolled in Schools or Colleges outside of work –
Jackie Cary
Turf Maintenance Class – Sandy Herring, Matt Moses, Megan Thurkins, Chris Shook
Tree Care Seminar – Chris Shook, Megan Thurkins, Adam Worrell
Master Gardener Classes began – Sandy Herring, Justin Price