HomeMy Public PortalAboutAB 20-119 Knife River Construction Agreement AIP 27 Taxiway
McCALL CITY COUNCIL 216 East Park Street
AGENDA BILL McCall, Idaho 83638
Number AB 20-119
Meeting Date April 23, 2020
AGENDA ITEM INFORMATION
SUBJECT:
Request to Approve the Agreement with Knife
River Corporation for the Taxiway Relocation
Project
Department Approvals Initials
Originator
or
Supporter
Mayor / Council
City Manager
Clerk
Treasurer
Community Development
Police Department
Public Works
Golf Course
COST IMPACT: $ 0 Parks and Recreation
FUNDING
SOURCE:
100% FAA grant funded Airport Originator
Library
TIMELINE: Information Systems
Grant Coordinator
SUMMARY STATEMENT:
On April 8, 2020, sealed bids were opened for the Airport Taxiway Relocation Project AIP 27. Two
proposers responded:
M.A. DeAtley $6,643,177.50
Knife River $6,633,584.00
Knife River Corporation was the lowest bidder at $6,633,584.00. T-O Engineers has reviewed the bids and
has recommended approval. The Federal Aviation Administration (FAA) also reviewed the bids and has
approved. The agreement has been reviewed and approved by to the City Attorney. Funding will be provided
by the FAA under AIP 27 at a 100% reimbursement rate. The Notice of Award and the Construction
Agreement are attached.
This agreement will provide the construction work portion of the project. Construction will consist of
demolition of existing pavement, earthwork, drainage, electrical systems, fence work, and rebuilding a new
taxiway 300 feet east of the current taxiway. Construction is expected to commence on July 6th, with an
estimated completion in mid-October. The project will be completed in 5 phases to minimize impact on
airport users, including the US Forest Service. Coordination with all airport users will continue during the
construction.
RECOMMENDED ACTION:
Approve the Agreement with Knife River Corporation for the Taxiway Relocation Project and authorize
the Mayor to sign all necessary documents.