INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract information Contract No.; R -35686 Letting Date:12/1012014
District:GREENFIELD DISTRICT AE:Anthony, Oliver R. PE/S:Newkirk, Eric Status:Pending
Change Order Information
Change Order No.: 012 EWA: Y or Force Acct: N
Date Generated: 01/15/2016
Date Approved: 00/00/0000
Reason Code: CHANGED COND, Quantity Related
Description: Extra work unforseen foundation removals 8/26115 - 9/21/15
Original Contract Amount
$ 2,648,720.86
Current Change Order Amount
$ 3,246.97 Percent: 0.123 %
Total Previous Approved Changes
$ 86,649.12 Percent: 3.271 %
Total Change To -Date
$ 89,896.09 Percent: 3.394 %
Modified Contract Amount
$ 2,738,616.95
Time Extension Information
Date initiated 01/06/2015 Date Completed 01/08/2016
Original Contract Time SS Completion Date 00/0010000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 2 SP Days Value $ 0.00
Previous Time Approved SS Days by AE: DCE: SCE: DDCM:
SS Days _ SP Days Value $
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:R -35686
INDIANA Department of Transportation
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority
($ per Change Order)
(Days per Contract)
Verbal Approval Required?
Total Change To-Date>5%?
Scope/Design Recommendation
Required?
Change Order No.: 012
Page: 2
AE: DCE: SCE: * DDCM:
(-LE$250K-)(-LE$750K-)(—LE$2M—)(--GT$2M—)
( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days)
Y / N If Y, by Date issued
Y / N If Y, Copy to Program Budget Manager
Y / N If Y, Referred to Project Manager(PM)
Date to PM Date Returned
Approval Authority Concurs with PM? Y / N If Y, Concurrence by Date
If N,Resolution: Approved Disapproved
Resolved by
Date
LPA Signatures Required? Y / N If Y, Date to LPA Date Returned
FHWA Signatures Required? Y / N If Y, Date to FHWA Date Returned
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer c'—,&— �< <t- Date
Comments:
Contract No:R -35686 INDIANA Date:01121/2016
Change Order No:012 Department of Transportation Page: 3
Contract: R -35686
Project: 0810267 - State:0810267
Change Order Nbr: 012
Change Order Description: Extra work unforseen foundation removals 8126/15 - 9/21/15
Reason Code: CHANGED COND, Quantity Related
CLN PCN PLN Item Code Unit Unit Price Co OV Comment Amount Change
0110 0810287 0110 202-01000 LS 3,246.970 1.000 C Amount:$ 3,246.97
Item Description: STRUCTURES AND OBSTRUCTIONS REMOVE
Supplemental Descriptionl: Removal of unforseen foundations and slabs
Supplemental Description2:
Total Value for Change Order 012 = $ 3,240.97
Milestone Time Adjustment
Milestone Nbr: 02
Milestone Description: INTERMEDIATE COMPLETION DATE 2
Original Completion dt: 12/18/2015 Adj compl dt 01/08/2016 Adj No. of Days 2
Explanation: This work was not included in the original contract and considered extra work, therefore an additonal 2 days are added to
Intermediate Completion Date 2.
Whereas, the standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
This work includes the removal of buried and unforseen concrete foundations or slabs that were removed or modified due to construction
oonitids for period 8-2845 through 9-21-15. It was agreed to pay labor costs plus labor burden plus 20% prolft, and pay equipment costs per
Equipment Watch plus 12%, and pay any materials plus 12% and pay costs for subs plus 10% of first $3000 and 7% of any remaining sub costs.
Change Order Explanation for Specific Line Item
1k1�M�f�Mf�M1i�NNfkHNMM�MMNtI�MN�MMHNMHMMNIM��MM�Nf#��HM�NNf IM11�fNlNMe��M�MIMM�N���
it is the Intent of the parties that this change order Is full and complete compensation for the work describe above.
Notification and consent to this change order Is hereby acknowledged.
Contractor. !)yKLS j ,S Signed By: �✓
NOTE: Other required State and FHWA signatures wig be obtained electronically through the SiteManager system.
Contract No:R -35686 INDIANA
Change Order No:012 Department of Transportation
NffNN.M.NfNfMNfNflflNfMNtMfffN/H1MN4Hf MfNN1f*ffffNlf Mf Nf.NN.N1f1f NN/Nf«NfNNIf NNf«fNf N
A/nPPR�O�VE"D,/�FOpR LOCAL PUBLIC AGENCY
(TITLE)
(TITLE)
SUBMITTED FOR CONSIDERATION
PE,S �• C �� /C.�
ffffff«f«f«fffNffff«ffftffMlff« ffffffffNfMlfMf«Mff►f««ffffffffffN«f«fNf«Nff«ff
Date: 01 /21 /2016
Page:.4
/— z 8 /h
(DATE)
(DATE)
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Approval Level Name of Approver Date Status
Project Engineer/Supervisor Newkirk, Eric 01/19/2016 Approved