HomeMy Public PortalAbout2019-03 Authorizing to issue a work order to the Corradino Group for the Signalization ProjectRESOLUTION NO. 2OI9-3
A RESOLUTION OF THE VILLAGE COUNCIL OF THE
VILLAGE OF KEY BISCAYNE, FLORIDA,
AUTHORIZING THE VILLAGE MANAGER TO ISSUE A
\ryORI( ORDER TO THE CORRADINO GROUP, INC. FOR
AS-BUILT PLANS FOR THE VILLAGE'S TRAFFIC
SIGNALIZATION PROJECT; AND PROVIDING FOR AN
EFFECTIVE DATE
WHEREAS, the Village of Key Biscayne ("Village") issued Request for Qualifications
No. 2016-02-09 ("RFQ") for continuing professional engineering services; and
WHEREAS, pursuant to the RFQ, the Village Council selected the Conadino Group,
Inc. (the 'oConsultant") as one of the consultants to provide continuing professional services
relating to general civil engineering, transportation planning and engineering, environmental
engineering, and landscape architecture, and authorized the Village Manager to execute an
agreement with the Consultant; and
WHEREAS, Consultant has provided a proposal, attached as Exhibit "A," (the
"Proposal") to provide signalization analysis and as-built plans for the Village's traffic
signalization project (the "Project"); and
WHEREAS, the Village Council desires to authorize the Village Manager to issue a
work order for the Project consistent with the Proposal and the professional services agreement
entered into between the Village and Consultant; and
WHEREAS, the Village Council finds that this Resolution is in the best interest and
welfare of the residents of the Village.
NO\il, THEREFORE, BE IT RESOLVED BY THE VILLAGE COUNCIL OF
THE VILLAGE OF KEY BISCAYNE, FLORIDA AS FOLLOWS:
Section 1. Recitals. That each of the above-stated recitals are hereby adopted,
confirmed, and incorporated herein.
Section 2. Authorization. That the Village Manager is hereby authorized to issue a
work order to Consultant for the Project that is consistent with the Proposal in an amount not to
exceed $42,000.00.
Section 3. Effective Date. That this Resolution shall be effective immediately upon
adoption.
PASSED and ADOPTED this 15th day of January, 2019.
W. DAVEY, MAYOR
MEDINA,
VILLAGE CLERK
APPROVED AS TO FORM AND LEGAL S
A
VILLAGE ATTORNEY
2
oz
c)
u.
M
O
U
EXHIBIT ''A''
THE CORRADINO GROUP lNc.
ENGINEERS , PLANNERS . PROGRAM MANAGERS . ENVIRONMENTALSCIENTI'TS
December 4,2018
Charles R. Press
Police Chief
Village of Key Biscayne
Public Works Department
88 West Mclntyre Street
Key Biscayne, FL 33149
Re: Crandon Boulevard Plans for Signalizatlon Upgrades
Dear Chief Press,
I. GENERAL
The general objective for the Consultant is to províde all project management and professional
engineering services required for the design and preparation of Signafization Upgrade Plans
which consist of the following (refer to Exhibit t):
1. Ocean Drive (Asset 3545) - Four (4) new VDCs proposed to replace the 4 existing ones
and one blueTOAD to be added to the upright for the mast arm on the SE cornel
2. W. Mclntyre (Asset 3834)
a, Mast arm on the NE corner - One (1) new VDC is proposed (structural analysis
required)
b. Mast arm on SW corner - Two (2) VDCs to replace the 2 existing (Econolite will
revise drawings from the currently 3 proposed to only 2)c, Mast arm on SE corner - One (1) proposed VDC replacing the existing one
3. Sonesta Drive (Asset 6316) - Four (a) VDCs proposed to replace the 4 existing ones
4. Key Colony (Asset 4578)- The exiting Wavetronix will remain, only a controller will be
installed
5. West Wood Drive (Asset 5038)- Four (4) VDCs proposed to replace the 4 existing ones
Elements of work shall include Signafization analysis, Signalization Plans and Structural Analysis.
Permitting with Miami-Dade County, Department of Transportation and Public Works Traffic
Signals and Signs Division is not included as part of this contract and will be cönducted by
Econolite. All plans and design documents are to be prepared with Standard English values iñ
accordance with all applicable engineering manuals and guidelines.
The Work detailed in this Proposal can be completed within ten (10) weeks from your notice to
proceed (please refer to Section lll for a submittal schedule) for a total fee of $41 ,3ß7.20
SCOPE OF WORK
Prolect Activitv 3: General
Task No. 3.6 Prime Gonsultant Project Manager Meetings
lncludes all efforts required for Project Manager coordination meetings and field review.
40-5i NW97 lll¡\Vl:Ntilì StJlll. :],(lft ,MlAMl. lrt- 33 178
il jt 80(| 337 i.i5l 30.i,51).t.{)715
liAX 305.-s94,0755
www,coRRAt)tNO.('i)kt
Proleôt Actlvltv 18: Structures -Miscellaneous fRElì
Conduct structural analysis (By Botas Engineering, lnc.) of the existing mast arm at the NE corner
of W, Mclntyre Street with Crandon Boulevard with the addition of the proposed Econolite Video
Camera. As no as-builts are available, it will be considered that the existing mast arm complies
with the Miami Dade County mast arm standards.
Prolect Activltv 2{: Slsnalizatlon Analvsls
Task No. 21.5 Reference and Master Design File
lncludes all efforts required per intersection for establishing the signal master design file
Task No. 21.10 Quantities
lncludes all work required to determine the quantitíes for each signalized intersection
Task No. 21.11 Cost Estimate
lncludes preparing an Engineers Estimate and updating as necessary
Task No. 21.14 Field Revlews
lncludes I field review for 5 intersections, includes travel time
Proleot Activitv 22: Slsnalization Plans
Task No. 22.1 Key Sheet
lncludes tíme to develop key sheet
Task No, 22.3 Tabulation of Quantities
lncludes time to place pay item numbers, descriptions, quantities and totals
Task No. 22.4 General Notes/Pay ltem Notes
lncludes time to place provide general notes and pay item notes
Task No. 22.5Plan Sheet
lncludes all efforts required to create the signalization sheets.
Task No. 22.9 Special Details
lncludes time to create special details
II. ADDITIONALSERVICES
Additional Services, Permitting, Permitting Fees and Post Design Services are not part of this
contract.
III. SCHEDULE OF WORK - TIME OF PERFORIVIANCE
Consultant shall submit the Deliverables and perform the Work as depicted in the tables below
be added as
SCHEDULE OF DELIVERABLES
Task, Sub.task,
or Activity lD #
Major Task, Sub-Task, Activity,
or Deliverable
Duration
(specify weeks
or calendar
davsl
Delivery Datet
(cumulative weeks or
calendar days)
1 Phase I Submittal-90% Plans 6 weeks**NTP + 6 weeks
2 Phase 2 Submittal - Final Plans &
FinalPermitting
4 weeks***NTP + 10 weeks (pending
on timely response from
MDC Traffic & Signals
Division)
,14381 Key Bisc¡yne\Signaliza(ion\TWO l0_CrÐdon Boulevûd_Signal Upgrades_Rev2-Fínol,docx
RE1 Structural Analvsis/Reoort I week NTP +,week
* An updated schedule, indicating actualdelivery dateìC, bas
to the Village upon rcceipt of the NTP and will be submitted to the Village of Key Biscayne.**lncludes time for coordination with MiamLDade County Public Works Traffic Signats and Sþns Division*l*Muy vary based on review delays from Village as well as by the Miami-Dade County Public Works
Depadme¡it fafi?c Slgna/s and Srþns Division, .
IV, SUB.CONSULTANTS
The below listed sub-consultants will assist in the performance of the work.
Sub-Consultant Name Specialty or Expertise
Botas Engineering, lnc.Structures
V GOMPENSATION
consultant shall perform the work detailed in this proposal for a Total fee of $4j,367.20. The
Village shall not be liable for any fee, cost, expense or reimbursable expense or other
compensation beyond this amount. Said fee shall be negotiated with the Village as Additional
Services (refer to Section ll).
*Nofe;should match the and/or
VI. PROJECT MANAGER
CONSULTANT'S Project Manager for this Work Order assignment will be Cecilia Villoria, p.E.
Submitted by Reviewed and approval in concept
recommended by;
Joseph M, Corradino, AICP
President
The Corradino Group, lnc.
Charles R. Press
Police Chief
Village of Key Biscayne
RYOFCöMP
Task o¡
Actfvlty
tD#_I[glo.de!k Name and/or Activíty Description Fes Amount Fse 8¿sis
1 Phase I Submittal- 90% Ptans 30,814.56 Lump Sum
2 FinalSubmitta - 100% Contract Plans i 7.703.64 Lump Sum
;38.ı18.20 Lump Sum
REI Structures i upon completion)$2,849.00 Lump Sum
TOTAL 41,367.20
J:\4r8¡ Key Bisc¡yre\Signd¡z¡t¡on\TWO I O* Crmdon Boulevud_signol Upgrodcs_Rov 2-Find doø