HomeMy Public PortalAboutAB 20-167 Park St & Thompson Ave PH1 Reconstruction Bid RecommendationMcCALL CITY COUNCIL 216 East Park Street AGENDA BILL McCall, Idaho 83638 Number AB 20-167 Meeting Date June 4, 2020 AGENDA ITEM INFORMATION SUBJECT: Request to Reject the Park Street and Thompson Avenue Reconstruction – Phase 1: Recommendation for Contract Award Department Approvals Initials Originator or Supporter Mayor / Council City Manager Clerk Treasurer Community Development Police Department Public Works Originator Golf Course COST IMPACT: Approximately $550,000 Parks and Recreation FUNDING SOURCE: Tourism LOT Grant Streets Fund Thompson Place Development Airport Library TIMELINE: May – September 2020 Information Systems Grant Coordinator SUMMARY STATEMENT: Public Works and Crestline Engineers, in collaboration with the Thompson Place PUD development, completed the final engineering design for the reconstruction of Park Street and Thompson between Ann Street and 4th Street. Attached are pertinent sections of the civil plans set. Formal bidding was conducted in May, with the bid opening occurring on 5/15/20. The bid was divided into two alternatives. The City received one responsive bid. The received bid, by Granite Excavation was as follows: • Bid Alternative 1 (Thompson from Ann to Park) = 475,951.64 (Engineer’s Est. = $342,532.65) • Bid Alternative 2 (Park from Thompson to 4th St) = $321,021.38 (Engineer’s Est. = $259,228.65) Granite’s bid for both bid alternatives are significantly higher than the Crestline Engineer’s estimate for the project. Additionally, revenue projections for the Tourism LOT, Streets LOT and other applicable City funds for FY20 suggest that programmed budgets for this project will not be available to fund this project. Staff is continuing to work with the Thompson Place developer to evaluate an alternative approach to completing the street reconstruction improvements on Park (between Park and Ann) in Summer 2020 that will be more cost effective for the City. RECOMMENDED ACTION: Reject the responsive low bid by Granite Excavation for the Park Street and Thompson Avenue Reconstruction – Phase 1 construction contract. RECORD OF COUNCIL ACTION MEETING DATE ACTION 10-10-2019 AB-19-215: Council approves preliminary engineering design services agreement 4-24-2020 AB-20-106: Council approves final engineering design services agreement