2471 S. Titanium Place, Meridian, ID 83642 Phone (208) 323-2288 Fax (208) 323-2399 www.to-engineers.com
Aviation | Transportation | Land Development | Wastewater | Municipal | Water Resources | Surveying
April 9, 2020
Richard M. Stein, A.A.E.
Airport Manager
McCall Municipal Airport
336 Deinhard Lane
McCall, Idaho 83638
RE: Recommendation of Award
AIP 3-16-0023-027-2020
Relocate Parallel Ta xiway A
Rick,
Sealed bids for relocation of Parallel Taxiway A at the McCall Municipal Airport were
received and opened by the McCall City Clerk at 11 :00 a.m., Wednesday, April 8, 2020.
Two bids were received for the project. The bid results are summarized in the following
table:
Schedule A:
Contractor Location Bid
M. A. DeAtley Construction, Inc. Clarkston, Washington $6,643,177.50
Knife River Corporation – Mountain West Boise, Idaho $6,633,584.00
Knife River Corp. submitted the apparent low bid. The Engineer’s estimate was
$8,660,253.00. A copy of the detailed bid tabulation is enclosed for your records.
The bid submitted by Knife River Corp. was reviewed for bid submittal requirements and
appears to be responsive. This company is a licensed public works contractor in the State
of Idaho with the appropriate license category for the type of construction anticipated
during this project.
Knife River Corp. has indicated that will perform the excavation, aggregate production
and placing as well as asphalt paving. Work to be subcontracted includes airfield electrical
improvements. The total value of subcontracted work is approximately $181,405.00.
There is no construction Disadvantaged Business Enterprise (DBE) goal for this project
and Knife River Corp. has indicated they do not anticipate using DBE subcontractors.
April 9, 2020
Page 2 of 2
2471 S. Titanium Place, Meridian, ID 83642 Phone (208) 323-2288 Fax (208) 323-2399 www.to-engineers.com
Aviation | Transportation | Land Development | Wastewater | Municipal | Water Resources | Surveying
Based on the bid evaluation, T-O Engineers recommends award of Schedule A to Knife
River Corp. in the amount of $6,633,584.00. Award should be made contingent on
concurrence of the FAA and the availability of federal grant funds.
We will forward the Notice of Award and Agreement to you under a separate cover. The
City of McCall will be required to send a copy of this letter to the FAA with a letter from
the City seeking concurrence with our recommendation.
If you have any questions regarding the bid, bid results and subsequent award process,
please contact me.
Sincerely,
T-O ENGINEERS, INC.
Kevin R. Bissell, P.E.
Aviation Project Manager
enclosure
cc: Gary Gates, FAA