PROJECT STATUS REPORT
Client: John Anderson, Airport Manager PSR No: 002 (11-04-2008 thru 01-06-2009)
Project: McCall Airport Date: January 6, 2009
Environmental Assessment
Project No: 034256 From: Rainse Anderson, P.E.
Project Manager
Distribution: US Mail and E-Mail
PROJECT STATUS:
WHPacific has:
• Cultural and archaeological field investigation completed.
• Contacted agencies and surveyor regarding Northern Idaho Ground Squirrel
• Conducted first Airport Environmental Assessment Committee Meeting for December
3rd, 2008.
WORK COMPLETED THIS PERIOD:
WHPacific has completed:
• Prepared Amendment #1 to address Northern Idaho Ground Squirrel issue
• Completed cultural and archaeological field investigation, report pending from
subconsultant
• Airport Environmental Assessment Committee meeting #1, prepared FAQs for City’s
website, along with meeting presentation
ACTION REQUIRED:
Item: Description: Action Req’d By: Action Req’d
Date:
Completed
Date:
1 Submit field investigation
reports for review
WHP 1/19/2008
2 Prepare draft alternatives
section of EA
WHP 2/2/2009