HomeMy Public PortalAboutPSR #3C:\Documents and Settings\bwagner\Local Settings\Temporary Internet Files\OLK19\PSR #3.doc February 2, 2009
PROJECT STATUS REPORT
Client: John Anderson, Airport Manager PSR No: 003 (01-06-2009 thru 02-02-2009)
Project: McCall Airport Date: February 2, 2009
Environmental Assessment
Project No: 034256 From: Rainse Anderson, P.E.
Project Manager
Distribution: US Mail and E-Mail
PROJECT STATUS:
WHPacific has:
• Submitted Amendment #1 address the Northern Idaho Ground Squirrel issue.
• Submitted revised FAA reimbursement request to City.
• Drafted the preliminary engineering design report, which includes cost estimates, to assist
in selecting the Preferred Alternative.
• Scheduled AEAC #2.
WORK TO BE COMPLETED NEXT PERIOD:
WHPacific will:
• Update the Alternatives section to include the preliminary engineering design report.
• Receive biological and archaeological reports from subconsultants.
• Submit Alternatives packet, with complete design report, to the City, FAA, and AEAC
for review.
• Conduct AEAC #2.
• Assist the City in selecting a Preferred Alternative.
ACTION REQUIRED:
Item: Description: Action Req’d By: Action Req’d
Date:
Completed
Date:
1 Review/approve contract
amendment #1
City 02/16/2009
2 Submit field investigation
reports for review
WHP and subconsultants 02/16/2009
3 Update draft alternatives, with
engineering data
WHP 02/18/2009
4 Transmit alternative chapter
to City and AEAC
WHP 02/18/2009
5 Conduct AEAC #2 WHP 03/04/2009
6 Selection of Preferred
Alternative
City, FAA, and WHP 03/13/2009