To: David Lyle February 5, 2014
CC: Steve Fox
CC: George Reese
CORRECTIVE ACTIONS TAKEN FOLLOWING THE SPILLS ON 30 JUNE, 2013 AND 13 JULY, 2013
• The force mains to sewer lift stations 3 and 4 has been replaced and upgraded, at a total cost of
$278,875. There were 3,600 linear feet of 10 inch C-900 PVC installed for #3 and 1,800 linear feet of 8
inch C-900 PVC, installed for #4.
• The city is scheduled to replace 6,300 linear feet of 12 inch DI Force Main with new C-900 PVC, along
Jones Avenue, Solomon Avenue and Polk Street, the projected cost estimate is $600,000.00. Engineering
for #6 Force Main is 100%complete. GEFA funding has been applied for and bids for the project are due
in February 2014. #6 Force Main will take 6 to 9 months to complete after it has been awarded to a
contractor.
• The city has been testing our outfalls for Enterococci and intends to it in the future.
Please let us know if any of these projects are acceptable to you.
Thank You
Stanley C. Bearden
Wastewater Superintendent
P.O.Box 2749—403 Butler Avenue,Tybee Island,Georgia 31328-2749
(866) 786-4573—FAX(866) 786-5737