Building Envelope Replacement Project Phase 2:
Contract between the City of McCall and Falvey’s Earthworks, LLC.- Amendment
Department Approvals
Initials
Originator
or
Supporter
Mayor / Council
City Manager
Clerk
Treasurer
Community Development
Police Department
Public Works
Golf Course
COST IMPACT:
$72,493.80
Parks and Recreation
FUNDING SOURCE:
FY15 $57,394 remaining budget
FY15 $15,139.80 Future Capital line item
Airport
Library
TIMELINE:
May 2015 – July 2015
Information Systems
Grant Coordinator
SUMMARY STATEMENT:
At the May 14, 2015 Council meeting, the Council approved the contract as amended to reflect the work not to exceed the cost of $57,394 until additional funds were accounted for. After
careful review of the FY15 budget, the Treasurer determined that there was unaccounted for moneys budgeted in the future capital line that could be used for this project. Attached are
an amendment to the original contract and the amendment.
RECOMMENDED ACTION:
Approve the amendment to the contract in the amount of $15,139.80 between the City of McCall and Falvey’s Earthworks, LLC and authorize the Mayor to sign all necessary documents.