Loading...
HomeMy Public PortalAbout2-Airport Department Report - June 2020Memo To: City Council From: Richard M. Stein, Airport Manager CC: Anette Spickard, City Manager Date: 06/30/20 Re: Monthly Department Report — June 2020 City of McCa11 1. Taxiway Relocation Project Phase 1 of the project will start on July 6th and continue until August 2th. Phase 1 will close the north end of Taxiway A, the western portion of the main ramp. Due to a change in the construction haul route, the Diagonal Taxiway will remain in service during this phase. Permanent closure of the Diagonal is scheduled for August 3rd. Maps showing taxi routes have been created and distributed. 2. Airport Master Plan (AMP) The AMP project continues. Some portions of the project are underway, including: a 2-week long survey of airport facilities and navigational aids — and an inventory of existing facilities. The first public meeting of the Master Plan is scheduled to be held on Tuesday, July 21' at 7:00 p.m. location to be determined 3. Taxiway Centerline Marking The centerline and "T" tie -down marking projects have been completed. The lines were painted with a mix of "Type-1" reflective beads for increased visibility at night. 4. Airport Pavement Survey Every 5 years, the Idaho Transportation Department undertakes to survey all airport pavements state-wide. The survey is provided free to the City of McCall. The results of the survey will determine priorities, and funding availability, to repair/rehabilitate airport runways, taxiways and ramps. This survey will be undertaken sometime in late July. 5. United States Forest Service The United States Forest Service has executed a contract to improve the McCall Airbase on the west side of the airport. This work will include asphalt and concrete paving, and fencing, on their leased property west of the runway. The north end of the USFS ramp has been newly paved, and the contractor has moved to the south USFS ramp. The project should be completed by the end of August. Monthly Department Report — Airport