1. Snowfall:
According to the National Center for Environmental Information, a branch of the National Oceanic
and Atmospheric Administration, McCall received 71 inches of snowfall in February. There was one
half day closure of the runway due to snow over ice conditions, but no known operations were
impacted. Currently, Iām working to assess the overall impact to budget. A reallocation of funds from
other line items will need to be done to cover expenses for both overtime pay and fuel. Should a snow
event over 3ā occur prior to significant melt, we will incur above normal costs for removal as we have
filled our normal snow storage areas and will have to move the snow to another location.
2. Parallel Taxiway Relocation:
T-O Engineers continues work to assess the various taxiway separation costs which will drive the
scope of an environmental study update. Statement of work has been re-submitted to Federal Aviation
Administration (FAA) following comment for pre-design actions. An independent fee estimate must
be developed prior to approving a design contract.
3. Land Acquisition Reimbursement:
The final closeout for both Airport Improvement Program Grants was submitted to the FAA and
awaiting concurrence. Upon concurrence, the closeout will be presented to Council for approval to
formally submit and signatures.
4. Airport Zoning:
Draft copies of code amendments impacting the airport zone were sent to the FAA and Idaho
Transportation Department Aeronautics for comment prior to the March 5 Planning & Zoning work