HomeMy Public PortalAboutPW December 2010 For Period Ending: Decembers 31, 2010
Department
Project
Comments
Status
PUBLIC WORKS DEPARTMENT:
Administrative/Engineering
Deinhard Lane Reconstruction/ARRA Grant
CH2M Hill is completing a new task order and manhhour estimates for review by LHTAC. Design will begin the first part of January and is to be completed by the end of March.
New
Administrative/Engineering
ARRA pedestrian Access Walkways
Provided engineering/construction/ contract management for project.
Ongoing
Administrative/Engineering
Development Project Acceptance
Prepared updated infrastructure punch lists for Aspen Ridge Phase III, Greystone Village, Crystal Blue Condominiums
Ongoing
Administrative/Engineering
Engineering Specifications/Code Revisions
Public Works has started developing code revisions for the water and wastewater utilities, revising engineering and drainage standards and specifications.
Ongoing
Administrative/Engineering
Hwy 55 Speed Study
Public Works reviewed the speed study conducted by ITD on Highway 55. Public Works will conduct additional speed studies this winter, spring and summer and provide additional information
to City Council.
Ongoing
Administrative/Engineering
Land Use Application Reviews
Provided engineering review and approval for various DR, CUP, and PUD preliminary and final design plans.
Ongoing
Administrative/Engineering
Legacy Sundial
Provide engineering review and project management for Urban Renewal and Parks and Recreation Department.
Ongoing
Administrative/Engineering
Lift Station 7
Public Works is working with CH2M Hill on picking a design alternative for Lift Station 7.
Ongoing
Administrative/Engineering
Mill Street Parking Lot Bathroom
Provided engineering assistance to the Parks and Rec. Dept for project plans, specifications and contract documentation/award.
Ongoing
Administrative/Engineering
Pavement Management
Initial Streets CIP was approved by City Council. Public Works conversion to IWorqs software for pavement management is complete.
Ongoing
Administrative/Engineering
Pavement Management
Initial Streets CIP was approved by City Council. Public Works conversion to IWorqs software for pavement management is complete.
Ongoing
Administrative/Engineering
Pre-Chlorination Building
Conceptual alternatives for chlorinating raw water supply are being looked at. CHM2Hill is assisting with preparing an outline of alternatives, and additional work will continue.
Ongoing
Administrative/Engineering
Recycle Center
Valley County Commissioners have approved the Recycle Center Lease. Construction will begin in the spring of 2011.
Ongoing
Administrative/Engineering
Riverfront Park
Assisted Parks and Recreation on the survey and development of a preliminary cul-de-sac/parking plan near sheep bridge (to be constructed in Spring 2011)
Ongoing
Administrative/Engineering
Safety Manual
Public Works is developing a comprehensive safety/policy manual specific to Public Works.
Ongoing
Administrative/Engineering
Software Evaluation
Public Works has purchased fleet management software from IWorqs and is in the process of implementing this software by collecting data on all City vehicles and major equipment. Public
Works will continue to purchase additional modules in the coming months to better document Public Works maintenance activities, work orders and customer complaints.
Ongoing
Administrative/Engineering
Urban Renewal
Assist the Urban Renewal Board in construction management for the 2010 Improvement Project.
Ongoing
Administrative/Engineering
Development Project Acceptance
Final inspections and public infrastructure acceptance/approvals for Whitetail Cabin Sites, Spring Mountain Ranch Phase 5, Crystal Blue Condominiums
Completed
Streets
Snow Removal
Crews performed snow removal & street widening during and after any snow fall of 3 inches or more. Due to current storm, assisted businesses in removal of large accumulation of snow
& ice next to curbs.
New
Streets
Snow Removal
Crews performed snow removal & street widening during and after any snow fall of 3 inches or more. Due to current storm, assisted businesses in removal of large accumulation of snow
& ice next to curbs.
New
Streets
Winter Maintenance
Began cleaning snow away from fire hydrants when time allows, as well as checking and replacing roadway delineators.
New
Streets
Building Maintenance
Assisted where needed
Ongoing
Streets
Customer Service
Addressed numerous customer complaints on snow removal issues. Making contact with private snow removal contractors placing snow out of driveways and sidewalks in to our roadways.
Ongoing
Streets
Emergency Call ins
One call in for street sanding. Also assisted with tree removals after high winds.
Ongoing
Streets
Equipment Maintenance
Crews assisted with minor equipment maintenance and chain repairs.
Ongoing
Streets
Sanding
Continue to sand the streets as needed
Ongoing
Streets
Stormwater Drains
Still monitoring drains to make sure all are clear from ice, when time allows
Ongoing
Streets
ROW maintenance
Performed additional trimming of trees in right-of-way to allow for snow storage.
Completed
Streets
Road repairs
Continue to cold patch street pot holes and road edges as required.
Suspended until spring
Collection/Distribution
Springs Apartments
City has granted substantial completion approval of the water and sewer infrastructure, with a punch list to be addressed and completed in the spring by developer.
New
Collection/Distribution
Emergency Call outs
Crews responded to three emergency call out for broken water lines in houses. Meters were turned off until repairs can be made by owners.
New
Collection/Distribution
Knowles Road Booster Station
Power spike blew out voltage protection, shutting down station for three days while repairs were being made. Damaged part ordered and will be installed when received.
New
Collection/Distribution
Knowles Road Booster Station
Power spike blew out voltage protection, shutting down station for three days while repairs were being made. Damaged part ordered and will be installed when received.
New
Collection/Distribution
Hydro Cleaning
Crew continues to flush Park Street sewer line until line can be replaced. Currently this is being performed weekly to prevent back- ups.
Ongoing
Collection/Distribution
Lifts Stations
Crews continued wet well cleaning and inspections in preparation of winter.
Ongoing
Collection/Distribution
Water Meters & MXU’s
Crews continue to check water meters, and adjusted those where there have been some ground shifting or homeowners changes to surface affecting accessibility.
Continue to investigate any meter not reading to determine cause of failure. Once the problem is diagnosed repairs or replacement are performed. Working with Census to replace all MXU’s
that are under warranty.
Ongoing
Collection/Distribution
Lift Station 8
Final Punch List completed, pending receipt of replacement parts from Smith & Loveless.
Completed
Wastewater Treatment
Aeration Blowers
Winter time service work on blower #2 & #3.
Ongoing
Wastewater Treatment
J Ditch
Additional winterization to be completed shortly. Valves will be opened to keep the ice broken up.
Completed
Water Treatment
Air Leak
Repairs completed.
Completed
Water Treatment
Boiler/water plant
Service call on boiler #2. System keeps shutting down. Pending for repair quote.
Completed