PUBLIC WORKS DEPARTMENT:
Administrative/Engineering
City Campus Survey/City Hall backup power
Coordination w/IT for site survey of City campus in preparation for City Hall backup power station
New/Ongoing
Administrative/Engineering
Crystal Beach sidewalk design
Preliminary survey conducted for future sidewalk along Crystal Beach Property on SH-55
New/Ongoing
Administrative/Engineering
City GIS control network
Coordination with GIS department for fieldwork and data reduction for new survey control network/database
New/Ongoing
Administrative/Engineering
Deinhard/Thula sewer line manhole
Project design and management for new, 60” dia. manhole connecting Thula and Deinhard sewer mains
New/Completed
Administrative/Engineering
Sign Management
Secured grant funds from LHTAC to have our regulatory/warning signs inventoried. I conjunction with the work associated with pavement management all remaining sign will be inventoried.
Then all signs will be checked for compliance with reflectivity standards and readied for downloading into our I-Worq sign program.
New
Administrative/Engineering
SH-55 Lane Striping
Coordination w/ITD to revise striping to include 11’ lanes, 12’ turn lanes within portions of the City following chip sealing
New/Ongoing
Administrative/Engineering
Highway 55 Sidewalks
The City of McCall received $50,000 Cash for Towns from ITD for safety related improvements to sidewalks and handicap ramps along 3rd Street. Plans are being prepared for construction
bids and work to occur late in August and in September.
New
Administrative/Engineering
Whitetail PUD
Assisting staff in the review of PUD development agreements to determine if all required public infrastructure has been completed
Ongoing
Administrative/Engineering
Whitetail PUD
Assisting staff in the review of PUD development agreements to determine if all required public infrastructure has been completed
Ongoing
Administrative/Engineering
Centennial Committee/Park
Prepared base map of Railroad/SH-55 ROW and parking area for sculpture park sub-committee. Public Works will be project managers for this project.
Ongoing
Administrative/Engineering
CDBG Grant Application
Working with City staff on development of grant application for streetscape improvements for 3rd Street
Ongoing
Administrative/Engineering
Deinhard Lane Reconstruction/ARRA Grant
Construction will start August 1 and substantial completion is scheduled for August 19.
Ongoing
Administrative/Engineering
Deinhard Pathway
Construction on the pathway began on July 20th. Ongoing construction management.
Ongoing
Administrative/Engineering
Development Project Acceptance
Continued site inspections and infrastructure acceptance for The Springs, Greystone Village, Crystal Blue Condos, Aspen Ridge PH-3, and MDHS.
Ongoing
Administrative/Engineering
Engineering Specifications/Code Revisions
Public Works has started developing code revisions for the water and wastewater utilities, revising engineering and drainage standards and specifications.
Ongoing
Administrative/Engineering
Hwy 55 Speed Study
Public Works will conduct additional speed studies this August and look at vehicle speeds through the downtown area and provide additional information to City Council.
Ongoing
Administrative/Engineering
Land Use Application Reviews
Payette Lakes Middle School, Odmark Remodel, Woody’s sidewalk,491 Chula Road, 2005 Warren Wagon Road, and Dr. Charles sidewalk design.
Ongoing
Administrative/Engineering
Lift Station 7
Application has been submitted to the US Fish & Wildlife Service and we are awaiting comments. A NEPA study will have to be conducted late summer and early fall for review by the USFWS
before further work can be done. Approval to move forward with design will not be until Spring 2012.
Ongoing
Administrative/Engineering
Lift Station 7
Application has been submitted to the US Fish & Wildlife Service and we are awaiting comments. A NEPA study will have to be conducted late summer and early fall for review by the USFWS
before further work can be done. Approval to move forward with design will not be until Spring 2012.
Ongoing
Administrative/Engineering
Pavement Management
Inventory and assessment of all city streets will occur during the late summer/early fall 2011 to update the pavement management system.
Ongoing
Administrative/Engineering
Pre-Chlorination Building
Conceptual alternatives for chlorinating raw water supply are being looked at.
Ongoing
Administrative/Engineering
Policy/Safety Manual
Public Works is developing a comprehensive safety/policy manual specific to Public Works. This manual is due to be completed by the end of August.
Ongoing
Administrative/Engineering
Sewer Infiltration and Inflow
Staff is compiling information regarding lift station pump hours, historical I & I monitoring/remediation documentation, etc in preparation for future engineering task order to monitor
and report issues
Ongoing
Administrative/Engineering
Software
Public Works has fully implemented fleet management software from I-Worq. Additional software for managing sidewalks and sewer infrastructure are being evaluated.
Ongoing
Administrative/Engineering
Technical Advisory Group (TAG)
The TAG has requested an extension to the July 29, 2011 deadline for the written recommendation report. Additional information is required from DEQ and about water rights issues before
a report can be finalized.
Ongoing
Administrative/Engineering
Urban Renewal
Assist the Urban Renewal Board in construction management for the 2010 Improvement Project.
Ongoing
Administrative/Engineering
Parks and Recreation Fir Street Bathroom
Providing construction and overall project management for new bathroom at intersection of Mill and Fir Streets. Substantial completion 6-30-11.
Ongoing/Completed
Administrative/Engineering
Consulting engineer Request for Qualifications (RFQ)
Selected Horrocks Engineers for General Engineering Services.
Completed
Administrative/Engineering
Consulting engineer Request for Qualifications (RFQ)
Selected Horrocks Engineers for General Engineering Services.
Completed
Administrative/Engineering
Deinhard Lane Utility Underground
Financing approval and construction coordination w/Idaho Power to underground existing power and cable TV from the US Post Office to the east side of Samson Trail
Completed
Administrative/Engineering
Legacy Sundial
Final completion and acceptance of project completed on 7-27-11
Completed
Streets
Repair patches
Contracted to have patch repaired per ITD in front of Paul’s Market. The original patch done last fall was due to a water main leak and it sunk. Working with ITD for contribution.
Additional patching completed on 1st St., Saddlehorn, Buckboard, Jacob St., Mission, and Lake Side Ave.
New/Ongoing
Streets
West Lake Street
Repaired patches in roadway at State & West Lake per ITD. Will be going back to original contractor for reimbursement.
New/Completed
Streets
Street Painting
Painting of parking lots, stop bars, & handicap markings.
Ongoing
Streets
Brushing
Continued brushing along roadways as time allows between major projects.
Ongoing
Streets
Customer Service
Address complaints surrounding driveway culverts, ditches and overall road conditions. All complaints are addressed after the area’s are personally inspected.
Updated/Ongoing
Streets
Emergency Call-ins
Received 3 emergency call outs during the month, one due to missing stop sign, and twice to reset the traffic light at 3rd & Deinhard.
Updated/Ongoing
Streets
Inspections
Assisting City Engineer with site inspection on any new construction projects that are located in our right of ways.
Ongoing
Streets
Road Maintenance
Continued grading, watering and applying dust oil as needed to roadways. Repairs of road shoulder and drainages continue.
Ongoing
Streets
Road repairs
We continue to monitor the temporary road repairs, completed in previous months.
Ongoing
Collection/Distribution
Hydro Cleaning
Crew has cleaned all sewer lines west of the river and will start repairs to manholes that were found to need it.
New
Collection/Distribution
Lift Station 9
Lost motor controller. A.M.E. contractor will be onsite to check out or replace.
New
Collection/Distribution
Line Replacement
Crew replaced three sections of water lines during the month (1515 Louisa, Idaho St., and 305 West Lake).
New
Collection/Distribution
Manhole/water valve/meter pit maintenance
Crew replaced two (2) water valves & meter pits, and repaired 2 manholes that were damaged this winter.
New/Ongoing
Collection/Distribution
Misc. Issues
Crew pulled pump motors at LS #4 due to blockage caused by plastics and other items.
New/Completed
Collection/Distribution
Sewer Blockage
Crew cleaned out sewer line blockage in the Rio Vista subdivision. The blockages are being caused by roots intruding into our lines and are scheduled to be cleaned out by Pipeline
Services next week.
New/Ongoing
Collection/Distribution
Hydro Cleaning
Crew continues to flush Park Street sewer line until line can be replaced. Currently this is being performed weekly to prevent back- ups. Also, cleaning all known slow or trouble
lines.
Ongoing
Collection/Distribution
I & I
In correlation with the manhole inspections the crews are noting extensive I & I. At this time it appears to be coming from homeowner’s sump pumps used to lower crawl space water levels,
which is then being pumped directly into our sewer lines. The crews will keep a close watch on this.
Ongoing
Collection/Distribution
Water Meters
To date all but 30 MXU’s have been replaced. Additional replacements will be completed after the water read in July.
Ongoing
Collection/Distribution
Water Meters
To date all but 30 MXU’s have been replaced. Additional replacements will be completed after the water read in July.
Ongoing
Wastewater Treatment
J-Ditch
The ditch has been online since June 21st. Water level is high due to excess moisture this spring.
Ongoing
Wastewater Treatment
Leak Test
Keller Associates report received and is inconclusive. Minor repairs may be needed.
Ongoing
Wastewater Treatment
Irrigation Pump
Pump installed and is operational.
Completed
Water Treatment
Lead Copper testing
In the middle of obtaining lead/copper water sampling. This covers about 25 different homes in the water system. The sampling is required by DEQ/EPA every three years.
New/ongoing
Water Treatment
Computer system
The new motor control center screen is ordered. Project should be completed by mid August. This system monitors about 15 major pumps & motors.
Ongoing
Water Treatment
Water plant pumps
Both pumps have been repaired.
Completed