HomeMy Public PortalAbout2017-19 Amending the Building Zoning and Planning Fee ScheduleRESOLUTION NO. 2017-19
A RESOLUTION OF THE VILLAGE COUNCIL OF THE
VILLAGE OF KEY BISCAYNE, FLORIDA, AMENDING THE
BUILDING, ZONING, AND PLANNING FEE SCHEDULE
APPROVED BY RESOLUTION NO. 2002-45; AND
PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the Village of Key Biscayne ("Village") adopted its existing Building, Zoning,
and Planning Fee Schedule via Resolution No. 2002-45 ("Fee Schedule"); and
WHEREAS, on February 21, 2017, the Village's Building, Zoning, and Planning Director
("Director") recommended that the Village amend its Fee Schedule; and
WHEREAS, on February 21, 2017, the Village Council approved the Director's
recommendations and added its own revisions to the Fee Schedule; and
WHEREAS, the Village Council desires to ratify the actions taken at the February 21, 2017
Council meeting and amend the Fee Schedule as reflected in Exhibit "A" attached hereto and
incorporated herein; and
WHEREAS, in accordance with Section 6-3 of the Village Code of Ordinances, the Village
Council held a public hearing on February 21, 2017 prior to adopting this Resolution; and
WHEREAS, the Village Council finds that this Resolution is in the best interest and welfare
of the residents of the Village.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE VILLAGE
OF KEY BISCAYNE, FLORIDA, AS FOLLOWS:'
Section 1. Recitals Adopted. That each of the recitals stated above is hereby adopted
and confirmed.
Notk: 6ta,k.:th ongl, wc,r s are deletions to the existing Fee Schedule. Highlighted underlined words are additions to the existing words in the Fee
Schedule.
Section 2. Amending Fee Schedule. That the Fee Schedule adopted by Resolution No.
2002-45 is amended as shown on Exhibit "A" attached hereto and incorporated herein.
Section 3. Effective Date. That this Resolution shall be effective immediately upon
adoption hereof. However, the fee schedule adopted by this Resolution shall be retroactively
effective as of February 22, 2017.
PASSED and ADOPTED this 18`h day of April 2017.
MA AYRA PEA LI AY
ATT
4AV/a0/6,
NCHITA H. ALVAREZ, MMC, VILLAGE CL
APPROVED AS TO FORM AND
LEGAL SUFFICIENCY
VILLAGE ATTORNEY
2
EXHIBIT "A"
VILLAGE OF KEY BISCAYNE
BUILDING, ZONING AND PLANNING FEE
SCHEDULE
Adopted by the Village Council
September 24, 2002
Resolution No.: 2002-45
Amended on February 21, 2017 and ratified by
Resolution No. 2017 -
For additional information contact:
Building, Zoning, and Planning Department 88
West McIntyre Street Key Biscayne,
Fl 33149
305 365 5512
305 365 5556 (fax)
www.keybiscayne.fl.gov
TABLE OF CONTENTS
A. General Information on Special Fees, Refunds, Extensions, and
Cancellations 1
1. Double Fees 1
2. Re -inspection Fees 1
3. Lost and Revised Plans Fee 1
4. Refunds, Time Limitation, and Cancellations for Expired Permits .... 2
5. Special Projects 3
6. General Information 4
7. Inspections Requiring Overtime 4
8. Fees Based on Estimated Cost - Documentation Required 4
9. Building Permit Processing Fee 4
10. Contractors Registration Fee 4
11. Zoning Plan Review Fee 4
12. Site Plan Review Fee 5
B. Building Permit Fees 5
1. Up - Front Processing Fee 5
2. Minimum Building Permit Fee 5
3. New Buildings and Additions 5
4. Roofing and Re -Roofing for any Building 6
5. Fences and/or Wall, Perimeter 7
6. Ornamental Iron 7
7. Swimming Pools, Spas, and Hot Tubs 7
8. Temporary Platforms and Temporary Bleachers to be used for Public
Assembly 7
9. Demolition of Buildings 7
10. Demolition of Signs, Fences, and/or Wall Structures other Buildings . 7
11. Shop Drawing Review 8
12. Installation or Replacement of Windows or Doors 8
13. Screen Enclosures, Canopies, and Awnings 9
14. Trailer Tie Down 9
15. Sign Permit Fees 9
16. Satellite Dish, Antenna, or Device used to Receive or Transmit a Signal
through the Air 10
17. Tie Down Re -Inspection 10
C. Plumbing Permit Fees 10
1. Minimum Plumbing Permit Fee 10
2. Residential Plumbing (Group R) 10
3. All Groups Except Group Single Family and Duplex Group R 11
4. Septic Tank, Settling Tanks, Gas and Oil Interceptors, and
Grease traps 11
5. Sewer ..11
6. Condensate Drain (Air Conditioning) 11
7. Water Piping 12
8. Wells . ... ... . . . .. . ... . . . . .. ... . . . ... ... . . . . . . ... ... ... ... ... . .. . . . . . . . .. 12
9. Natural Gas or a Liquefied Petroleum 13
10. Water Treatment Plants, Plumbing Stations, Sewerage Treatment Plant and
Lift Stations 14
11. Water and Gas Mains 14
12. Storm and Sanitary Utility and/or Collection for Lines and Building Drain
Fields 14
13. Temporary Toilets - Waterborne or Chemical 14
14. Dental Vacuum Lines 14
15. Construction Trailer or Manufactured Home Connections 14
D. Electrical Permit Fees 15
1. Minimum Electrical Permit Fee Including Repair Work for Permit ... 15
2. Permanent Service to Buildings - New Work Only 15
3. Feeders 15
4. Agricultural Service 15
5. Temporary Service for Construction 15
6. Trailer Service (Residential) 15
7. Trailer Service (All other groups) 15
8. Temporary Service for Test 16
9. Residential Wiring 16
10. All Other Wiring 16
11. Lighting Fixtures 17
12. Signs and Architectural Features (indoor neons) 18
13. Temporary Work on Circuses, Carnivals, Fairs, Christmas Tree Lots,
Fireworks, Tents, etc 18
14. Fire Detection System 18
15. Master Television Antenna and Radio System 18
16. Burglar Alarm System 19
17. Intercom System 19
18. Energy Management 19
19. Swimming Pool, Electrical 20
20. Free Standing Service 20
E. MECHANICAL PERMITS
1. Minimum Mechanical Permit Fee 20
2. Air Conditioning and Refrigeration, including the Relocation of Equipment
21
3. Mechanical Single Family Residences and Duplexes Group R (Includes
Categories (R1, R2, R3, and R4) 21
4. Furnaces and Heating Equipment, including Commercial Dryers, Ovens and
other Fired Objects not Elsewhere Classified 22
5. Fire Sprinkler System 22
6. Storage Tanks for Flammable Liquids 22
7. Internal Combustion Engines 22
I!
8. Commercial Kitchen Hoods 22
9. Other Fees 22
ELEVATORS, ESCALATORS, AND OTHER LIFTING APPARATUS 20
1. Amusement Rides and Devices 20
BOILERS AND PRESSURE VESSELS 23
1. Boilers 23
2. Fees for Periodic Re -Inspection 23
CERTIFICATE OF USE AND OCCUPANCY AND CERTIFICATE
OF COMPLETION 24
1. Residential 24
2. Business, Wholesale, and Retail 25
3. Unusual Uses, Special Permits, Business, and Industrial Uses .. .. 25
4. Trailer Use Certificates 25
5. Change of Use or Name 25
6. Refunds 26
7. Occupancy Without a Certificate of Occupancy 26
8. Certificate of Completion (C.C.) 26
9. Temporary CO. "Up -Front Fee 26
10. Letter of Omission Fee 26
11. Shutter Certification 26
PLANNING AND ZONING APPLICATION FEES 27
1. Planning and Zoning Fee Schedule 27
2. Appeals of Village Council Decisions 28
3. Preparation of Certified Record for Court 28
COST OF PUBLICATIONS AND RECORDS 28
1. Florida Building Code, Other Code Books, Supplements, and Departmental
Publication Fees 28
2. Cost of Departmental Records 28
PREMISS PERMIT FEES 29
40 -YEAR RECERTIFICATION FEES 30
STRUCTURAL GLAZING SYSTEMS - RECERTIFICATION FEES 30
PERMIT SYSTEM FEES 30
FIRE INSPECTION FEES 26
Hi
BUILDING, ZONING AND PLANNING FEE SCHEDULE
GENERAL INFORMATION ON SPECIAL FEES, REFUNDS, EXTENSIONS AND
CANCELLATIONS
DOUBLE FEES: When work for which a permit is required is commenced prior to
the obtaining of a permit, the permit applicant shall be required to pay one hundred
twenty five dollars ($125.00) plus a double permit fee. In no event shall the applicant
pay less than one hundred and seventy dollars ($170.00). The payment of the
required fee shall not relieve any person, firm of corporation from fully complying with
all of the requirements of all applicable regulations and codes, nor shall it relieve
them from being subject to any of the penalties therein. The double fee requirements
shall be applicable to all divisions of the Building, Zoning and Planning Department.
For second offense of doing work without a permit, the permit applicant shall be
required to pay twice the double permit fee plus two hundred and fifty dollars
($250.00). For each offense thereafter, the permit applicant shall be required to pay
twice the double permit fee plus five hundred dollars (S500.00).
REINSPECTION FEES: When extra inspection trips are necessary due to (1) wrong
address being given on call for inspection, (2) prior rejection of work due to faulty
construction, (3) work not being ready for inspection at time specified, (4) failure to
call for final or other inspections, (5) required corrections not being made or
completed at time specified, a fee of seventy five dollars ($75.00) for each
reinspection shall be charged to the permit holder in the trade concerned. If it is
determined by the field inspector concerned, that the job has the same problem after
the reinspection fee is assessed and paid, then a second reinspection fee of one
hundred and fifty dollars ($150.00) shall be charged. The reinspection fee
requirement shall be applicable to all divisions of the Building, Zoning and Planning
Department. The payment of reinspection fees shall be required prior to requesting
final inspections.
The reinspection fee for inspection of existing buildings by all trades to determine
compliance with the South Florida Building Code, but not annual inspections as
required by 305.1 (d) shall be seventy five dollars ($75.00) per inspection per trade.
LOST AND REVISED PLANS FEE
a. Lost Plans: When plans for new buildings and additions are lost by the owner or
contractor, a recertification fee will be required to review, stamp and approve a
new set of plans as a field copy. Such fee shall be based on thirty percent (30%)
of the original building permit fee, with a minimum fee for Group R (single family
residence) seventy five dollars ($75.00), and a minimum fee for all others of one
hundred twenty five ($125.00).
b. Revised Processing Fees:
1. Major plan revision after permit is issued shall be subject to a fee of twenty
five dollars ($25.00) per page.
21. Minor plan revision shall be subject to a fee at the rate of twelve dollars and
fifty cents ($12.50) per page for each review that takes longer than five
(5) minutes.
3. A fee of one hundred dollars ($100.00) shall be charged for failure to make
required corrections that were provided under a previous review but not
less than 50% of the original application fee for each building trade
including zoning.
c. Lost Building Permit Fee: A replacement fee of thirty dollars ($30.00) shall
be charged for the loss of a Building Permit document after a permit has
been issued.
d. Retrieval of Records Fee: A fee of $1.00 per inspection shall be charged for
copies of inspection results.
4. REFUNDS, TIME LIMITATION, and CANCELLATIONS: The fees charged pursuant
to this schedule, provided the same are for a permit required by Section 105 of the
Florida Building Code, may be refunded by the Director of the Building, Zoning and
Planning Department, subject to the following:
a. No refunds shall be made on requests involving:
1. permit fees of one hundred dollars ($100.00) or less; or
2. permits revoked by the Building Official under authority granted by the
Florida Building Code, or permits canceled by court order; or conditional
permits; or
3. permits which have expired; or
4. permits under which work has commenced as evidenced by any
recorded inspection having been made by the Department; or
5. the original permit holder when there is a change of contractor.
2
b. A full refund less one hundred dollars ($100.00) or fifty percent (50%) of the
permit fee, whichever is greater, rounded to the nearest dollar, shall be
granted to a permit holder who requests a refund provided that:
1. the Department receives a written request from the permit holder prior
to the permit expiration date; and
2. the permit holder submits with the written request the applicant?s
validated copy of said permit; and
3. no work has commenced under such permit as evidenced by any
recorded inspection.
c. Where there is a change of contractor or qualifier involving a permit, the
second permit holder shall pay a fee of one hundred dollars ($100.00) to
cover the cost of transferring the data from the original permit to the second
permit, except when the original permit has expired or the original permit
fee is under one hundred dollars ($100.00), in which case the original
permit feel shall be paid.
d. A fee of sixty dollars ($60.00) shall be paid by the permit holder who
submits a written request for a permit extension as authorized under
Section 105.3.2 and Section 105.4.1.3 of the Florida Building Code.
e. Where a permit has become null and void a credit of fifty percent (50%) of
the original permit fee shall be applied to any reapplication fee for a permit
covering the same project and involving the same plans, provided that the
complete reappiication is made within six (6) months of the expiration date
of the original permit, and provided that no refund had been made as
provided in this section. If reapplication is made after six (6) months of the
expiration date or if this is not the first reapplication made on the project, the
full permit fee shall be charged on the renewal application. The permit
reapplication must be submitted with the plans and the applicant?s validated
copy of the original permit. The amount of this fee shall be at least equal
to or higher than the minimum fee for the trade concerned.
SPECIAL PROJECTS
A fee equal to actual staff time and related costs shall be assessed for special projects
requiring research by the department in order to answer questions proposed by
developers, attorneys, realtors, or municipalities, etc., in connection
3
with the use, re -subdivision, and development of properties, or to determine if any
existing violations are on the property through a review of departmental records. Such
special fee only will be levied for requests outside the scope of normal Department
work. A minimum fee of fifty-five dollars ($55.00) shall be charged. A fee equal to two
dollars ($2.00) per page shall be assessed for pre-programmed computer reports on
department records. The minimum fee shall be fifty five dollars $55.00).
6. GENERAL INFORMATION
a. A $0.01 per square foot fee will be added to building permits for the State
of Florida to study building code requirements for radon gas.
b. For concurrency review, a fee of six percent (6%) of the total permit fee,
Certificate of Use and Occupancy or Zoning application fee, will be added
to original fees where a concurrency review was performed.
c. Impact fees are assessed on certain building permits, including reapplication
on expired permits.
7. INSPECTIONS REQUIRING OVERTIME: Charges for construction inspections,
which are requested in advance and where the permit applicant has requested an
employee to work overtime, shall be 1.5 times the employees hourly rate. The fee
shall be paid to the Village within 48 hours of the inspection.
8. FEES BASED ON ESTIMATED COST -DOCUMENTATION REQUIRED: The
Department may require the permit applicant to submit appropriate documentation
as proof of estimated cost of construction used to compute permit fees.
9. BUILDING PERMIT PROCESSING FEE: A fee of thirty dollars ($30.00) shall be
charged for processing each permit application.
10. CONTRACTOR REGISTRATION FEE: Twenty five dollars ($25.00). An annual fee
of twenty five dollars ($25.00) shall be charged for registering general contractors.
11. ZONING PLAN REVIEW FEE: Twenty five dollars ($25.00) or thirteen cents ($.13
per sq. ft. of floor area), whichever is greater, shall be applied to any building permit
application that requires review for compliance with the Zoning and Land
Development Regulations.
4
12. SITE PLAN REVIEW FEE: Two hundred dollars ($200.00) shall be charged for the
review of a site plan for new construction of any single family or duplex, for an
apartment building, or commercial building or any addition, renovation or repair that
exceeds 50% of the floor area of the present structure.
B. BUILDING PERMIT FEES: Fees listed in section B include only building permit fees and
do not include plumbing, electrical or mechanical fees, certificate of occupancy fees,
zoning, planning or contractor/tradesmen fees which are listed in the following sections:
1. UP -FRONT PROCESSING FEE: When the building permit application is received,
the applicant shall pay an up -front Processing fee equal to 100% of the estimated
cost of the building permit fee including 100% of the Zoning Plan and Site Plan
Review Fees. This processing fee is not refundable, but shall be credited toward the
final building permit fee.
2. MINIMUM BUILDING PERMIT FEE:
Minimum Fee for a Building Permit: This minim m $100.00
does not apply to add on building permits issued s
supplementary to current outstanding permits for he
same job.
3. NEW BUILDINGS OR ADDITIONS:
a. Single Family, Apartments, and Duplex (Group I):
New construction including additions
$0.70 per sq. ft.
Alterations or repairs of existing floor space
$0.07 $ 1.00 of estimated
per value
of--wark,
$0.70 per sq. ft.
Minimum fee $ 100.00
5
b. All Other Construction:
Repairs due to fire damage
$ 0.05 per $ 1.00 of estimated value of
work. Minimum fee of $ 225.00
Storage and industrial use of Group F
and S occupancies
$ 9.25 per 100 sq. ft. or fraction thereof.
Minimum fee of $ 225.00
Shade houses
$ 0.35 per 100 sq. ft. or fraction thereof
Slabs
$ 70.00
New construction other than as specified
herein: (water towers, pylons, bulk
storage -tank found on, unusual limited -
use buildings, marquees, and similar
construction)
$12.25 for each $ 1,000 of estimated cost of
fraction thereof.
Subsoil preparation for each $1,000 of
estimated costs
$5.25
All other construction, alterations,
and repairs
Minimum fee of $250.00 or $18.00
per
$1,000.00 of estimated cost or fraction
thereof, which ever is applicable 1% of
estimated cost, whichever is greater, but not
to exceed $10,000.
4. ROOFING AND RE -ROOFING FOR ANY BUILDING*:
Roofing shingle
$0.13
$ 100.00
per sq. ft.
minimum fee
Roofing tile
$0.13
per sq. ft
$ 100.00
minimum fee
Other types of roofing material
$0.13
per sq. ft.
$ 100.00
minimum fee
* Fees for buildings multiple roofs shall be based on the square footage cost of each type.
6
FENCES AND/OR WALL, PERIMETER:
For each 100 linear ft. or fractional part thereof
$1.92
Minimum fee
$ 100.00
ORNAMENTAL IRON:
Per sq. ft. of coverage
SWIMMING POOLS, SPAS, AND HOT TUBS
Installation or repair
$0.66
$144.00
TEMPORARY PLATFORMS AND TEMPORARY BLEACHERS TO
BE USED FOR PUBLIC ASSEMBLY
For each 100 square feet or fractional part of
platform area
$6.30
For each 100 lineal ft. or fraction part of seats
$5.40
DEMOLITION OF BUILDINGS
For each sq. ft. of floor area
$0.15 per sq. ft. minimum $100.00
DEMOLITION OF SIGNS, FENCES, AND/OR WALL STRUCTURES OTHER
THAN BUILDINGS
Fee
$ 100.00
11. SHOP DRAWING REVIEW
a. Trusses
First 600 sq. ft. or fractional part
For each 100 sq. ft. or fractional part there
of
316.38
b. Precast/prestress
Roof, floor, walls, and similar structures -each
1,000 sq. ft. or fractional part
$8.40
c. Overhead doors, each
$8.40
d. Skylights, each
$8.40
e. Handrails and stair rails per linear ft.
$1.20
f. Storefront/fixed glazing
(Under 8 ft. high x 4 ft. wide) 100 sq. ft. or part
$9.30
g. Walk-in coolers, each
377.04
12. INSTALLATION OR REPLACEMENT OF WINDOWS OR DOORS: Replacement
of windows and exterior doors in all buildings or installation of windows or doors in
building exceeding two stories in height; or storefronts and fixed glass 8 ft. in height
or 4 ft. in vertical mullion spacing; or curtain walls including windows and doors
therein.
For each 100 sq. ft. or fra tional part $8.10
Minimum fee 100.00
8
13. SCREEN ENCLOSURES, CANOPIES, AND AWNINGS
a. Screen enclosures: each 100 sq. ft or fraction
thereof
$11.22
b. Free standing canopies per $ 1000.00 of
estimated cost
$11.22
c. Awnings and canopies attached to structures:
horizontal projection per sq. ft. of area covered
$0.20
d. Storm shutters: per sq. ft. of area covered
$0.20
e. Minimum fee
$ 100.00
14. TRAILER TIE DOWN
Tie down inspection fee: including tie down, plug in of
plumbing and electrical service connections per trailer
(This does not include installation of meter mounts
and service equipment. Separate mechanical
plumbing and related electrical permits are required.
15. SIGN PERMIT FEES
I $96.00
a. Minimum fee
S 100.00
b. Signs: non -illuminated (per sq. ft.)
(Illuminated signs under electrical permit
$1.62
c. Annual renewal of Class C signs on or before
October 1st of each year (per sign)
$38.40
16. SATELLITE DISH, ANTENNA, OR DEVICE USED TO
RECEIVE OR TRANSMIT A SIGNAL THROUGH AIR OR SPACE
Serving a single family home, duplex, or a dwelling
unit for any device that is more than 36 inches in
diameter - One fee total for all trades
$45.00
Serving more than two dwelling units. Per dish,
antenna even if mounted on one pole.
$192.00
17. TIE DOWN RE -INSPECTION
Minimum fee
$ 100.00
C. PLUMBING PERMIT FEES
1. MINIMUM PLUMBING PERMIT FEE
Except as otherwise specified. This minimum does
not apply to add on plumbing permits i sued as
supplementary to current outstanding ermits for the
same job.
RESIDENTIAL PLUMBING ( GROUP R3)
$1
0.00
New single family residence or duplex per sq. ft.
$0.13
Addition or remodeling of existing floor area to
single family residence or duplex per sq. ft.
$0.13
Minimum fee
$ 100.00
ALL GROUPS EXCEPT GROUP SINGLE FAMILY & DUPLEX GROUP R3
Roughing -in Plugged Outlets for: Bathtubs, closets, doctors, dentists, and
hospital sterilizers, autoclaves, autopsy tables and other fixtures,
appurtenances or other appliances having water supply or waste outlet, or both,
drinking fountains, fixtures discharging into traps or safe waste pipes,
10
floor drains, laundry tubs, lavatories, showers, sinks, slop sinks, urinals, water
heaters:
For each roughing -in or plugged outlet
S7.68
Each roughing -in or plugged outlet replaced on old
roughing in: each fixture
$11.22
Pool heaters installed, replaced, or repaired
S 100.00
SEPTIC TANKS, SETTLING TANKS, GAS AND OIL INTERCEPTORS,
GREASE TRAPS
Including tank abandonment, draintile and relay for
same
SEWER
$38.04
Each building storm sewer and each building
sewer where
connection is made to a septic tank, to a collector
line or to an existing sewer or to a city sewer or
soakage pit or to a building drain outside a
building.
$38.52
Sewer capping/demolition
$38.52
CONDENSATE DRAIN (AIR CONDITIONING)
Per outlet
$5.14
Except single not manifolded A/C not exceeding 5
HP
No charge
11
7. WATER PIPING
Water service connection to a municipal or private
water supply system (for each meter on each lot)
$10.20
Water connection or outlets for appliance or
installations not covered by fixture set above
$10.20
Irrigation system, and underground sprinkler
system for each zone
$21.84
Solar water -heater installation, equipment
replacement or repair
$115.56
Swimming pool maintenance, water heater piping, not
including well (new installation of replacement
including service connection
$128.40
Residential
$128.40
All groups excluding residential
$128.40
Sump pump
$10.26
2 inch or less water service backflow assembles
$44.94
2 1/2 inch or less water service backflow
assembles
$70.62
Repairs to water piping: for each $1,000 estimated cost
or fractional part
$7.38
WELLS
All wells
$67.44
9. NATURAL GAS OR LIQUEFIED PETROLEUM
Group R: For each outlet (includes meters and
regulators
$8.64
Group R: For each appliance (does not include warm
air heating units, but does include invented space
heaters and vented wall heaters -No duct work) (See
Fee section E (3) for heating)
$8.64
All other Groups: For each outlet (includes meters and
regulators
$10.92
All other Groups: For each appliance (does not
include warm air heating units, but does include
invented space heaters and vented wall heaters -No
duct work) (See Fee section E (3) for heating)
$10.92
For each meter (new or replacement)
$5.16
For major repairs to gas pipe where no fixture or
appliance installation in involved
$128.40
Underground LP. Gas Tanks
$128.40
Above ground LP. Gas Tanks
$128.40
Change of company (no additional appliances or
outlets
$28.40
10. WATER TREATMENT PLANTS, PUMPING STATIONS,
SEWAGE TREATMENT PLANT AND LIFT STATIONS
Water treatment plant (interior plant piping)
$269.64
Sewage treatment plant (interior plant piping)
$192.60
Lift station (interior station piping)
$308.16
Sewage ejector
$ 75.00
13
11.
WATER AND GAS MAINS
Minimum fee
$120.00
Each 50 ft. or part thereof (On private property and
other than utility easement)
$9.00
12. STORM AND SANITARY UTILITY AND/OR COLLECT FOR LINES AND
BUILDING DRAIN FIELDS
Minimum fee
$ 100.00
Each 50 ft. or part thereof
$9.00
Each manhole or catch basin
$12.84
13. TEMPORARY TOILETS - WATERBORNE OR CHEMICAL
First temporary toilet
$57.78
For each additional
$10.62
Renewal of temporary toilet
Same fee as
original fee
14. DENTAL VACUUM LINES
Each system
$128.4
15. CONSTRUCTION TRAILER OR MANUFACTURED HOME CONNECTIONS
Each unit
$128.40
14
ELECTRICAL PERMIT FEES
1. MINIMUM ELECTRICAL PERMIT FEE INCLUDING REPAIR WORK FOR
PERMIT
Except as otherwise specified. This min
not apply to add on electrical permits issi.
supplementary to current outstanding pei
same job.
mum does
ed as
mits for the
$ 10
PERMANENT SERVICE TO BUILDINGS - NEW WORK ONLY
00
The following fee shall be charged for total
amperage of service: for each 100 amp. or
fraction thereof
$6.48
FEEDERS
Each feeder (Includes feeders to panels, M.C.C.;
switch -boards, generators; automatic transfer
switches, elevators, etc.)
AGRICULTURAL SERVICE
Per Service
TEMPORARY SERVICE FOR CONSTRUCTION
$15.42
$ 53.
>0
Per service
$ 53.50
6. TRAILER SERVICE (RESIDENTIAL)
Per service
$64.20
7. TRAILER SERVICE (ALL OTHER GROUPS)
jj Per amp (per service)
15
$70.62
8. TEMPORARY SERVICE FOR TEST
a. Equipment and service (30 day limit) per
meter
$115.56
b. Elevator (180 day limit) per elevator
$115.56
9. RESIDENTIAL WIRING: New construction of Group R3 and living units of Groups R1
and R2. Applies to all electrical installations except common areas, parking lot
area and/or buildings and house service of Group R1 and R2.
For new construction,
additions, rehabilitation of
existing floor area or new
wiring for each sq. ft. of floor
area.
$0.13
Minimum fee $ 100.00
Alterations or repairs per $
$0.06
1.00 estimated cost or
fractional part
Minimum fee $ 100.00
Common areas of Groups R1 and R2 includes: corridors, public lounges, elevators,
pumps, NC (public area), lights, outlets, house and emergency service, etc. These areas
shall be subject to the fees below:
10. ALL OTHER WIRING
a. Includes boxes, receptacles, switches, sign,
fractional motor, fans, low voltage outlets, empty
outlets for telephone, CTV, each outlet, 110 volt
smoke detectors each outlet box
$2.04
b. Special outlet up to 60 amps
$9.00
c. Special outlet over 60 amps
$16.68
16
d. Commercial equipment VA rated) X-ray outlets,
commercial cooking equipment, presses,
generators. transformers, permanently connected.
For each 10 KW or fractional part
$9.00
e. Motors (Fractional already covered on
general outlet Each motor
$11.58
f. Air conditioning and refrigeration system (new
$7.68
work). Applies to commercial and residential,
agricultural and industrial. Covers related work,
except wall or window units which are covered
under special outlets.
1. Per ton or fraction part thereof
2. Air conditioning and refrigeration
system strip heating, space heating.
For each 10 KW of fractional part
3. Replacement or relocation of existing
NC and refrigeration units (same
size)
a. Per ton
b. PerKW
$8.40
$2.58
$1.07
g. Electrical equipment - replacement (existing
$21.40
facilities) Fee based on cumulative cost of the
$6.00
following components:
$8.40
1. Switchboards, M.C.C., panels,
control boards. For each board
2. Motor replacement for same size
a. From 1 HP to 5 HP for each
motor
b. From 5 HP to 100 HP for each
motor
c. Over 100 HP for each motor
$18.12
11. LIGHTING FIXTURES: Fee based on cumulative cost of the following
components: Includes floodlights, spotlights, parking lights, tennis court lights,
fluorescent and incandescent fixtures, etc.
a. Per fixture
$1.90
17
b. Plugmold, light track, neon strips. Each 5
feet or fractional part
$3.96
c. Per lighting pole (standards) (Fixture to be
charged separately)
Group 1 pole $12.84
Commercial pole
$19.20
12. SIGNS AND ARCHITECTURAL FEATURES (INDOOR/NEONS)
Per outlet
$16.08
Per sq. ft. of sign (non -neon signs only)
$1.62
Repairs and re -connection each
$96.30
Neon strips each 5 ft. or fractional part
$3.20
Minimum fee
$ 100.00
13. TEMPORARY WORK ON CIRCUSES, CARNIVALS, FAIRS,
CHRISTMAS TREE LOTS, FIREWORKS, TENTS, ETC.:
Per ride or structure
$64.20
Minimum fee
$ 200.00
14. FIRE DETECTION SYSTEM: . Includes fire alarm systems, Halon, etc. Does not
include single 110 volt residential detectors.(needs category 04 processing).
a.
Master control, New and upgrades
$161.70
b.
Each device
$4.80
c.
Repairs and additions to existing systems
$120.00
15. MASTER TELEVISION ANTENNA AND RADIO SYSTEM: Does not include
CABLE and telephone empty conduit system. Does include free wiring of same
a. Master
Control
18
S25.68
b. Each
device
16. BURGLAR ALARM SYSTEM
S1.56
a. Installation wiring
$57.78
b. Master control
Installation devices -fee pe device
$57.78
$1.44 per device
c. Complete system
$115.56
d. Repair per system
$57.78
17. INTERCOM SYSTEM: Includes residential, nurse call, paging, etc.
a. Each new system all groups
$115.56
b. Each device
$1.56
c. Repair each system, all groups except
Group R
$128.40
18. ENERGY MANAGEMENT
a.
Per floor
S135.00
b.
Each device
$1.56
c.
Repair per floor
$128.40
19. SWIMMING POOL, ELECTRICAL: Fee based on cumulative cost of the
following components:
a. Residential pool & spa (Group R3)
(Includes motor and pool lights
$200.40
b. Residential combination pool/ spa
(Includes motor and pool lights
$128.40
19
c. Pool deck lights outlets per fixture or outlet
$1.92
d. Pool/spa heater per unit
(residential/commercial
$115.56
e. Commercial and multi -family dwelling pool
and spa
$180.00
f. Commercial and multi -family dwelling
combination pool and spa
$243.60
20. FREE STANDING SERVICE: New meter and service (requires processing). Fee
based on cumulative cost of the following components: Includes lift stations, sprinkler
systems, street lighting, parking lots, etc. that require new service with separate
meter.
a.
Service -per pump
$0.96
b.
Outlet per outlet
$1.92
c.
Lighting fixture, per fixture
$1.92
d.
Motor 105 HP, per motor
$7.68
e.
Over 5 HP to 100 HP, per motor
$10.56
f.
Over 100 HP, per motor
$25.68
g.
Per lighting pole (standards)
$9.00
E.M ECHANICAL PERMITS
1. MINIMUM MECHANICAL PERMIT FEE
Except as otherwise specified. This minimum does not
apply to add on mechanical permits issued as
supplementary to current outstanding permits for the same
job.
20
MECHANICAL SINGLE FAMILY RESIDENCES AND DUPLEXES GROUP R3
a. New construction per sq. ft.
$.13
b. Additions to single family residences and
duplexes per sq. ft.
$0.13
c. Minimum fee
$ 100.00
AIR CONDITIONING AND REFRIGERATION, INCLUDING THE RELOCATION OF
EQUIPMENT: separate permits are required for electrical, water and gas
connections
a. For each ton capacity or fractional part thereof
$19.20
b.
Room NC unit
$44.94
c.
Minimum fee
$ 100.00
FURNACES AND HEATING EQUIPMENT, INCLUDING COMMERCIAL DRYERS,
OVENS AND OTHER FIRED OBJECTS NOT ELSEWHERE CLASSIFIED:
(Includes all component parts of the system except field and electrical lines). For
vented and unvented wall heaters, see paragraph C.
a.
For each KW or fraction thereof
$3.84
b.
Minimum fee
$ 100.00
FIRE SPRINKLER SYSTEM
a.
Per standpipe
$25.68
b.
Per sprinkler head
$1.28
c.
Per hose rack or hose bib
$12.89
d.
Per connection to community supply
$64.20
21
e. Each 50 ft. of underground piping or part
thereof
$25.68
f. Fire pump and/or Siamese connection, each
$96.30
g. Minimum fee
$ 100.00
6. STORAGE TANKS FOR FLAMMABLE LIQUIDS
Per tank
$ 160.00
7. INTERNAL COMBUSTION ENGINES
Stationary, each
$96.30
8. COMMERCIAL KITCHEN HOODS
: Each hood
$160.50
OTHER FEES
a.
Fire chemical halon and spray booths
$134.82
b.
Insulation, Pneumatic Tube, Conveyor
Systems, Pressure and Process Piping,
Sheet al or Fiberglass Air Conditioning
Duct, Cooling Towers, Mechanical
Ventilation Ductwork or Ductless
Ventilation
$13.50
1. For each $ 1,000.00 or fractional of
part of estimated cost
$ 100.00
2. Minimum fee
22
F. ELEVATORS, ESCALATORS, AND OTHER LIFTING APPARATUS
Permits and inspections are provided by Miami -Dade County. If the Village provides
these services, then the fees established by the County shall be used by the Village.
1. AMUSEMENT RIDES AND DEVICES
a. For each portable, ride, or temporary
unit (maximum of 30 day
$121.98
b. For each permanent unit installed or
altered
3404.40
c. Annual inspection for each ride or device at any
location (permanent installation only)
$39.80
G. BOILERS AND PRESSURE VESSELS: Installation permit fees: Including initial
inspections and certificate. Does not include installation or connection of field and water
lines.
1. BOILERS: the following fees apply to each boiler to be installed:
a. Boilers less than 837 MBTU each
$128.40
b. Boilers 837 MBTU to 6,696 MBTSU
each
$128.40
c. Boilers 6,695 MBTSU and up each
$ 133.75
d. Steam drivers prime movers, each
$128.40
e. Steam activated machinery, each
$128.40
23
f. Unfired pressure vessels (operating at
pressures in excess of 60 psi and having
volume of more than 5 cubic feet) each
pressure vessel
$128.40
2. FEES FOR PERIODIC RE -INSPECTION
a. Steam boilers (annual) each
$160.50
b. Hot water boilers (annual) each
$66.78
c. Unfired pressure vessels (annual) each
$60.00
d. Miniature boilers (annual) each
$60.00
e. Certificate of inspection (where
inspected by insurance company) each
$96.30
f. Shop inspection of boiler or pressure
vessels per completed vessel
$96.30
g. Minimum fee $ 165.00 per half day,
regardless of number of vessels inspected
$430.20
CERTIFICATE OF USE AND OCCUPANCY AND CERTIFICATE OF COMPLETION:
The following original fees shall be paid for all uses. The indicated renewal fee applies to
those uses which are required to be renewed annually by Code or by Resolution.
Nonrenewable uses are issued permanent use and occupancy certificates which shall
remain valid for an unlimited time, unless revoked for cause or abandoned and providing
there is no change of use, ownership, or name, or that there is no enlargement, alteration
or addition in the use or structure.
1. RESIDENTIAL (CO.)
Building Type
24
U
=ee Per
it
Duplexes, per unit
Townhouses, per unit
$75.00
Bungalow court
$75.00
Apartment unit or hotel unit (regardless of the type of
ownership)
$100.00 per
unit
Private school, day nursery, convalescent and nursing
home, hospital, ACFL and Developmentally Disabled
home care
$ 96.00
2. BUSINESS, WHOLESALE AND RETAIL
Fee
Per sq. ft. of business area
$0.05
Minimum
$100.00
3. UNUSUAL USES, SPECIAL PERMITS, BUSINESS, AND INDUSTRIAL USES
Use
Fee
All unusual uses , except the following
$252.00
Churches
$0.00
Cabaret, nightclub, liquor, or package store
$312.00
Carnival, circus, or amusement rides
$150.00
4. TRAILER USE CERTIFICATES: Covers administrative and initial field inspection cost
for all types of construction site trailers. Fee also covers cost of site plan review.
a. Construction field offices
$162.00
b. Demolition C. O.
$385.20
5. CHANGE OF USE OR NAME
When there is a change of use or name, the fee shall be the original fee listed for the use
25
proposed.
6. REFUNDS
No refunds shall be made of fees paid for use and occupancy permits. In case of error,
adjustment may be made by the Director of the Building, Zoning and Planning Department.
7. OCCUPANCY WITHOUT A CERTIFICATE OF OCCUPANCY
$192.00 plus double of the CO. fee as set forth in this schedule.
8. CERTIFICATE OF COMPLETION (C.C.)
Type
Fee
a.
Single family residence, townhouse unit.
$50.00
b.
All others
$65.00
9. TEMPORARY CO. "UP -FRONT" FEE
When the temporary CO. (T.C.O.) application is received, the applicant shall pay a fee equal
to the cost of the Certificate of Occupancy.
10. SHUTTER CERTIFICATION
A fee of twenty five dollars ($25.00) will be charged to certify per unit.
26
PLANNING AND ZONING APPLICATION FEES
1. Planning and Zoning Fee Schedule: At the time of filing an application, the appropriate
fee must be paid. The amount of the fee is based on the below schedule (calculation
of the fee is cumulative for each line item):
a. Base application fee for any type of application (double base fee if the
application is the result of a violation).
Supervisory Variance (any type of use) $ 55.00
Single family and duplex (Administrative and
Regulatory Variance) $ 150.00
Multiple Family (Administrative and
Regulatory Variance) $315.00
Commercial and Hotel (Administrative and
Regulatory Variance) $ 500.00
Site Plan Review
Administrative $ 200.00
Village Council $ 500.00
Appeal of an Administrative Decision $ 1,000.00
Amendment to the Zoning and Land
Development Regulations $ 1,000.00
Change of Zoning District $ 1,000.00
Comprehensive Plan, Amendment $ 2,500.00
Comprehensive Plan, Change of Land Use $ 2,500.00
b. Advertising fee if notice in a newspaper
1. published in the Village
2. published in a newspaper that meets the
requirements of Chapter 163 of Florida Statutes
S 300.00
$ 4,500.00
c. Mailing fee: $ .50 per mailing address.
d. Size of property $ 100.00 per 10 acres or any
fraction thereof
27
e. Number of hotel or apartment units $ 55.00 per 15 units or any
fraction thereof
f. Size of buildings - non residential only $ 55.00 per 5,000 sq. ft. or any
fraction thereof
2. APPEALS OF VILLAGE COUNCIL DECISIONS
For every application for an appeal of a decision by the village Council, there shall be paid to
the Building, Zoning and Planning Department, for the processing for each and every
application, a fee of three hundred and fifteen dollars ($315.00), to be paid at the time of
application. Site plan modification, where permitted, to appeal requests will be processed at an
additional cost of three hundred and fifteen dollars ($315.00)
3. PREPARATION OF CERTIFIED RECORD FOR COURT
For the purpose of court appeals, herein the Director for the Building, Zoning and Planning
Department is requested to make available the record upon which the decision of the Council
is based, there shall be paid to the Building and Zoning Department, for the preparation of a
certified copy for the record, a fee of two hundred and sixty five dollars ($265.00) to be paid at
the time of request
J. COST OF PUBLICATIONS AND RECORDS
1. FLORIDA BUILDING CODE, OTHER CODE BOOKS, SUPPLEMENTS, AND
DEPARTMENTAL PUBLICATION FEES:
The charge for each copy of the Florida Building Code, other code books or supplements
thereto or other Departmental Publications shall be assessed by the Building and Zoning
Department in the amount equal to the low bid printing cost plus the demonstrable cost
to the department selling and distributing such code books, code supplements or
departmental publications. The charge for publications of Construction Lien Law
information are limited to five dollars ($5.00) per copy of publication as permitted under
Chapter 713 of the Florida Statute.
2. COPIES OF DEPARTMENTAL RECORDS
Plan Reproductions from microfilm or CD disc:
Plan Reproduction from microfilm or disc -per sheet 5.00
Reproduced Records - per page .15
Double sided copies - per page .20
28
Certified copies - per page
Notary Public Service - per document
Research and Ordering Plans
K. PREMISE PERMIT FEE
1.00
1.00
5.00
In accordance with provisions of the Florida Building Code and Chapter 10 of the Code of
Metropolitan Dade County, each firm or organization in Dade County which performs its own
maintenance work with certified maintenance personnel as well as helpers thereunder may pay
to Village of Key Biscayne an annual Master and subsidiary premise permit fee in lieu of other
fees for maintenance work. Such fee shall be paid to the Building, Zoning and Planning
Department and such permit shall be renewed annually at a fee which is calculated in
accordance with the provisions of this subsection.
1. CALCULATION OF THE INITIAL MASTER PREMISE PERMIT FEE:
Each firm or organization which obtains an annual Master premise permit shall include in their
application for such permit the total number of maintenance personnel, including helpers and
trainees thereunder assigned to building, electrical, plumbing or mechanical work. The Master
Premise Permit fee shall be computed by multiplying the total number of such employees times
fifty dollars ($50.00). The minimum Master premise permit fee shall be nine hundred and forty-
five dollars ($945.00).
2. CALCULATION OF THE INITIAL SUBSIDIARY PREMISE PERMIT FEE:
Each firm or organization which utilizes decentralized locations in addition to the main location
described under point 1 above, may additionally apply for a Subsidiary Premise Permit for each
such decentralized location. Such application for a Subsidiary Premise Permit shall include the
same information required in point 1 above. The Subsidiary Premise Permit Fee shall be
computed by multiplying the total number of such employees times fifty dollars ($50.00). The
minimum Subsidiary Premise Permit fee shall be two hundred and sixty-five dollars ($265.00).
3. RENEWAL OF PREMISE PERMIT:
Prior to each premise permit expiration, the holder will be sent a renewal notice to continue the
premise permit for the next renewal period. The calculation of the renewal premise permit fee
shall be the same as the method used to calculate the original premise permit fee. No
allowances shall be made for late renewal fees or part year renewal fees.
29
L. 40 -YEAR RECERTIFICATION FEES
For every application for 40 -year recertification under Section 8-11 of the Miami -Dade County
Code there shall be paid to the Building, Zoning and Planning Department, for the processing
of each application, a fee of two hundred and fifty dollars ($250.00). For every application for
subsequent recertification at 10 year intervals thereafter, there shall be paid to the Building,
Zoning and Planning Department, for the processing of each application, a fee of two hundred
and fifty dollars ($250.00).
Recording Fees: Established by the Clerk of the Court).
M. STRUCTURAL GLAZING SYSTEMS - RECERTIFICATION FEES
For the initial application for structural glazing recertification and each subsequent application
under Sections 2415.7 of the Florida Building Code and Section R4410.6.6 of the Florida
Residential Building Code there shall be paid to the Building, Zoning and Planning Department,
for the processing of each application, a fee of two hundred and fifty dollars ($250.00).
N. PERMIT SYSTEM FEES
For every building permit (building, electrical, public works, plumbing, mechanical, signs and
zoning) a fee of six dollars ($6.00) shall be assessed. These fees shall be used to purchase and
maintain the building permit system including software and upgrades.
O. FIRE INSPECTION FEE SCHEDULE
1. Any inspection related to the issuance of a building permit excluding the trade
permits ($100.00 electrical, mechanical, plumbing, and building) and minor permits
($50.00)
2. Annual Fire Life Safety Inspection:
a. Multiple Family - Restaurant and places of assembly $0.30 per
allowed occupant
b. Hotel
1. Restaurant and places of assembly $0.50 per allowed occupant
2. Retail and Office- see schedule in subparagraph (c) below
c. Retail and Office
30
1. Less than $5,000 sq. ft.
2. 5,001-10,000 sq. ft.
3. 10,001-15,000 sq. ft.
4. 15,001-20,000 sq. ft.
5. More than 20,000 sq. ft.
d. Private Clubs
e. Day care centers
31
s 20.00
$ 40.00
$ 60.00
$ 80.00
$100.00
$100.00
$ 50.00