HomeMy Public PortalAbout100_072_Elkins - Invoice #4 6-30-14 Invoice No.
ELKINS
C O N S T R L C T O R S . I N C .
INVOICE
Customer
Name City of Tybee Island Date 6/30/2014
Job# 311311
Address 403 Butler Avenue PM Andy Hardaker
City Tybee Island State GA ZIP 31328 Net 30 days
Attention: Diane Schleicher J
Description Total
This invoice (direct costs only with no markups)is for design changes including
structural modifications for revised steel at the sally port and changes to footing
elevations(includes forming footers for elevation change and maintain schedule).
1 Revised steel at sally port(see Apex quote) $4,490
2 CMU for lowered foundations (see Bibler quote) $1,959
Elevation change for concrete foundations, including formed footers to maintain
3 schedule due to weather(see Pro Slab quote) $17,380
Builders Risk $0
P&P Bond $0
General Liability $0
Fee $0
Please Remit Payment to:
Elkins Constructors, Inc.
P.O. Box 2396
Jacksonville, FL 32203
(904)353-6500 Net Due this Invoice 23,829.00
Apex Fabrication , Inc.
710 Griffin Court
Macclenny, Florida 32063 Apex
change order no.
Change Order Request 4001E-2
To: Elkins Constructors. Inc. Date: February 26,2014
Apex Project No. : 4001 E
Project: Tybee Island Public Safety Bldg.
Added Structural Steel on Approval
Attn. : Mr. Noah Anderen-Davis at Garage Low Roof Framing
Proposed Change(s) to the Subcontract:
1 Add, Furnish& Erect,Prime Painted Structural Steel added on approval of the Garage Roof Low Framing
E4 Apex shop drawing consisting of: Beams W14 x 22(2 ea),Plus,TS 3 x 3 x 1/4 Jambs(4 ea)and fasteners
at roll up doors.
Amount of this Change Order Request: $4,490.00
Previous Change Order Request(s):
Original Subcontract Amount:
Total Adjusted Subcontract Amount:
Note : Ai;disputes must be submitted in writinc within 10 days cf this change
No work wilt be done on this chance until this chance order cr your ccmesoondinc change order s signed and returned to Apex Fabrication.inc.
Apex Fabrication, Inc. Elkins Constructors, Inc.
By: Ed Bogardus By:
Title: Project Manager Title:
Date: February 26,2014 Date:
Customer Copy
44 I
v
SUBCONTRACTOR REQUEST FOR CHANGE/WORK ORDER
DATE: 2/21/14 CONTRACTOR: Elkins Constructors
REQUESTED BY: Court Boyd 'PROJECT: Tybee island Public Safety Building
{REQUEST#: 001 (REV) PROJECT MANAGER: Richard Byrd
CHANGE DESCRIPTION:1
Added Ctv1U for the lowering of the footings on the west and south side of the building
f I
Quantit+ Description E uio Labor Material TOTAL
I 148 Pcs cf Gra r Block CMU •rout filled solid { $1.16 $4.40 $5.47 $1.632.44
$0.00
50.00
_ $0.00
$0.00
-- $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
- I 50.00
SUBTOTAL: $1,632.44
SUBCONTRACTORS BOND COST: $0.00
SUBTOTAL: $1.632.44
PROFIT AND OVERHEAD: S326.49
TOTAL: $1,958.93
ADDITIONAL DAYS REQUIRED:
By execution of th,s document you are agreeing that the contractor wilt pay for the work at the prices set forth herein regardless of
whether contractor is paid by the owner for such work. To the extent that the terms contained herein may conflict with the terms
the coginal agreement between Contractor and Subcontractor.the terms herein shall prevail.
BIBLER MASONRY CON-TRACTORS, INC.: CONTRACTOR'S REPRESENTATIVE:
- t
rc !1 22;1
y DATE DATE
5100 Old Eklns Pointe x Suite 100 * Roswell, Georgia 30076
770-667-1633 fax 770-667-1624
PRO SLAB, INC. DATE NUMBER
90 SAM'S POINT RD. 2127/2014 02/27-COR1
BEAUFORT, SC 29907
CHANGE ORDER REQUEST
CUSTOMER
Accepted:
Elkins Constructors Inc.
701 W. Adams Street Phone: 904-353-6500
Jacksonville, Florida 32204
Fax: 904-387-1303 Date: -- -
E-mail: johnm @elkinsconstru...
PROJECT: Tybee Island Public Safety Building
DESCRIPTION TOTAL =
CHANGE ORDER REQUEST#1: 2,180.00
RE: Elevation Changes Returned With Rebar Shop Drawir.cs:
Excavate Footings(39 CYDS): -$780
Backfill&Compact Stemwalls(29 CYDS): S 580
Rebar Cost Increase(CMC CO#1): $ 535
Added Amount S 1,895 T 15%=$2,180
TOTAL = $2,180.00
PRO SLAB, INC. DATE NUMBER
90 SAM'S POINT RD. 4/1/2014 12/03-COR3
BEAUFORT, SC 29907 CHANGE ORDER REQUEST
CUSTOMER
Accepted:
Elkins Constructors Inc.
701 W. Adams Street Phone: 904-353-6500
Jacksonville, Florida 32204 Date:
Fax: 904-387-1303
E-mail: johnm@elkinsconstru...
PROJECT: Tybee island Public Safety Building
DESCRIPTION TOTAL =
CHANGE ORDER REQUEST#3: 15,200.00
RE: Formed Footing Requested by General Contractor.
Per Agreed to Contract Amount of$ 15,200
Attachment#1, Page 2 of 3.
TOTAL = $15,200.00