HomeMy Public PortalAboutChange Order No. 1 to Contract No. 111-2015 -Metro - American Environmental Corp.- Phase 1 RemediationCHANGE ORDER
Former Carpenter Bus Facility
No. 1
Owner: City of Richmond, Indiana
Contractor: American Envrionmental Corporation
Project Manager: Chris White, Senior Project Manager
Project Representative: Weaver Boos Consultants - Steven Stanford
Description of Change: Removal of free product and impacted groundwater via a
vacuum truck prior to activating the system recovery wells in these areas.
Reason for Change: Remove free product from WB-8 and impacted groundwater
from RW-3, RW-4, and RW-5.
Change in Contract Price
Original Contract Price:
$ 325,167.00
Net Increase (Decrease) from previous Change
Orders:
Contract Price Prior to this Change Order:
$ 325,167.00
Net Increase (Decrease) of this Change Order:
$ 4,381.00
Contract Price with the Approved Change Orders:
$ 329,548.00
Approvals:
Change in Contract Times:
Original Contract Times:
Substantial Completion
N/A
Final Completion
N/A
Net Change from Previous Change Orders:
Substantial Completion
N/A
Final Completion
N/A
Contract Times Prior to this Change Order:
Substantial Completion
N/A
Final Completion
N/A
Net Increase (Decrease) of this Change Order:
Substantial Completion
N/A
Final Completion
N/A
Contract Times with All Approved Change Orders:
Substantial Completion NA
days
Final Completion NA
days
Contractor:�—
American Environmental Corporation
Project Engineer: lag�
Kim Jyrc�a,
Owner: `?4'
!ZA4.
chmond, Indiana
Design Engineer: -,� S usnl S�ASrVF�kS
Weaver Boos Con C91s
0
Date
Date
Date
8� `2v/gyp
Date
Stanford, Steven
From: White, Chris <cwhite®aecindy.com>
Sent: Friday, August 19, 2016 2:02 PM
To: Stanford, Steven
Cc: Greg Stiens; Aho, Scott
Subject: RE: June Carpenter Bus operations - Groundwater Profile
No problem, I wasn't exactly sure of what to send. A breakdown of costs is presented below.
Description
Rate
Total
Vacuum Truck & Labor
$138
8 Hrs
$1,100
Water Disposal (per gallon)
$0.44
5,000 gallons
$2,200
American (Labor)/Staff
$91.50
10 Hrs
$915
Mileage
$0.57
160 miles
$91
Sample Gloves
$0.33
15 pair
$5
Oil/Water Interface Probe
$55
1 Day
$55
Decon Material
$15
Each
$15
Total
$4,381
Chris White
Senior Project Geologist
American Environmental Corporation
8500 Georgetown Road
Indianapolis, Indiana 46268
(317) 871-4090 ext. 210
cwhite@aecindy.com
-----Original Message -----
From: Stanford, Steven [mailto:sstanford@wcgrp.com)
Sent: Friday, August 19, 20161:47 PM
To: White, Chris <cwhite@aecindy.com>
Cc: Greg Stiens <gstiens@richmondindiana.gov>
Subject: RE: June Carpenter Bus operations - Groundwater Profile
Dear Chris,
This looks okay, however, I think we're going to need an itemized cost estimate to support the value of the proposed
change order.
Steven Stanford
I