HomeMy Public PortalAboutChange Order No. 2 to Contract No. 111-2015 - Metro - American Environmental Corp.- Phase 1 RemediationCHANGE ORDER
Former Carpenter Bus Facility
March 9, 2017
No.
Owner: City of Richmond, Indiana
Contractor: American Envrionmental Corporation
Project Manager: Chris White, Senior Project Manager
Project Representative: Weaver Boos Consultants - Steven Stanford
Description of Change: Labor & equipment to manifold monitoring well WB-8 to
the remediation system.
Reason for Change: Remove free product and impacted water from WB-8
via the remediation system
Change in Contract Price
Original Contract Price:
$ 325,167.00
Net Increase (Decrease) from previous Change
Orders:
$ 4,381.00
Contract Price Prior to this Change Order:
$ 329,548.00
Net Increase (Decrease) of this Change Order:
$ 1,700.00
Contract Price with the Approved Change Orders:
$ 331,248.00
Change in Contract Times:
Original Contract Times:
Substantial Completion
N/A
Final Completion
N/A
Net Change from Previous Change Orders:
Substantial Completion
N/A
Final Completion
N/A
Contract Times Prior to this Change Order:
Substantial Completion
N/A
Final Completion
N/A
Net Increase (Decrease) of this Change Order:
Substantial Completion
N/A
Final Completion
N/A
Contract Times with All Approved Change Orders:
Substantial Completion NA
days
Final Completion NA
days
Approvals: a�,»Y�bymmMft
Chris White
Contractor:
American Environmental Corporation
Owner: VU41
City of Richmond, Indiana
Steven Digitally signed by Steven Stanford
Design Engineer: DN:cn=Steven Stanford, o=Weaver
tonat—M 151op, LLC,
eltant', =Environmental Pract
ice Group,temail=sstanford@wcgrp.com, c=USanor
Date: 2017.03.1011:46:10 -0S'00'
March 9, 2017
Date
�-lGrlrl
Date
Date
Carpenter Bus Parts list to hookup RW-4 to WB-8
1.2- traffic barricades type-1 Grainger # 13P879 =
$205.00
2.2-2" #40 pvc tees = $ 4.00
3.2" #40 pvc pipe = $16.00
4.2" X 1" fernco adapter =$ 12.00
5.1-2" female adapter = $1.50
6.1" #40 pvc pipe = $8.50
7.1- !" # 40 pvc ball valve=$ 5.00
8. 1- 2" X 20' flexible hose Grainger # 1ZMW6=$126.50
9. Round trip mileage $90.00
10. Staff person (includes drive time) 8 hrs. X $
91.50 = $732.00
11. Field technician (includes drive time) 8 hrs. X
62.75= $ 502.00
Total= $1702.50
Greg Stiens
From:
Michael, Tracey <TMichael@ifa.IN.gov>
Sent:
Wednesday, March 08, 2017 11:14 AM
To:
'Stanford, Steven'
Cc:
gstiens@richmondindiana.gov; Esbenshade, Travis; Elifritz, Bonny
Subject:
Change Order #2
Steven,
Your request for change order #2 in the amount of $1700 for the system modification is approved.
Thanks,
'I'raccy Michael, LPG #2396
Project Manager
Indiana Brownf cIds Program
100 Nortli Senate Avenue, Room 1275
Indianapolis, Indiwia 46204
Office (317) 232-4402
Fxx (317) 234-1338
tmichael@ifa.in.p,ov
From: Stanford, Steven [mailto:sstanford@wcgrp.com]
Sent: Wednesday, March 08, 2017 8:06 AM
To: Michael, Tracey <TMichael@ifa.IN.gov>
Cc: gstiens@richmondindiana.gov; Esbenshade, Travis <tesbenshade@wcgrp.com>
Subject: RE: carpenter bus cost estimate
**** This is an EXTERNAL email. Exercise caution. DO NOT open attachments or click links from
unknown senders or unexpected email. ****
Tracey:
The attached Progress Report No. 4 explains that it is our opinion that the remediation can be hastened if we
temporarily incorporate monitoring well WB-8 into the dual -phase extraction system. Previously this has just been an
idea. We asked American to provide a cost estimate for implementing the recommendation as cost-effectively as
possible, which is an above -ground connection between the RW-4 and WB-8 wellheads at a cost of approximately
$1,700. The wellheads are about 10 ft apart. The connection and hose will obstruct two of the parking stalls at the SW
corner of the front office.
I am in the office today if you might like to discuss.
Thanks!
Steven M. Stanford, LPG
Environmental Practice Group, South Bend Operations Manager
`Weaver Consultants Group
7121 Grape Road
Granger, IN 46530
0: 574-271-3447 F: 574-271-3343 1 M: 219-808-3608
www.wcgrp.com sstanford@wcprp.com
IMPORTANT NOTICE: The information contained in this email message (including any attachments) may be confidential, privileged or both, and is intended exclusively for
the addressee(s) intended by the sender. If it appears you have received this email message in error, please notify the sender immediately and then delete; any other use of this
email message is prohibited. Thank you.
From: Michael, Tracey [mailto:TMichael@ifa.IN.gov]
Sent: Tuesday, March 07, 2017 12:09 PM
To: Stanford, Steven
Subject: RE: carpenter bus cost estimate
Steve, I must have not been included in the conversation regarding the system modification. Could you enlighten me a
little more on the how, what, where?
Thanks,
Tracey
From: Stanford, Steven [mailto:sstanford@wcgrp.com]
Sent: Wednesday, March 01, 2017 9:27 AM
To: gstiens@richmondindiana.gov_; Michael, Tracey <TMichael@ifa.IN.Rov>
Cc: White, Chris (cwhite@aecindy.com) <cwhite@aecindy.com>; Kimberly A. Jurczak P.E. (kiurczak@aecindv.com)
<kjurczak@aecindy.com>; Jacob Smith (smith@aecindy.com) <smith@aecindy.com>; Esbenshade, Travis
<tesbenshade@wcgrp.com>
Subject: FW: carpenter bus cost estimate
Importance: High
**** This is an EXTERNAL email. Exercise caution. DO NOT open attachments or click links from
unknown senders or unexpected email. ****
Dear Greg and Tracey:
Weaver Consultants Group believes that modification of the remediation system as described herein will increase its
effectiveness and hasten the removal of petroleum from the shallow aquifer layer(s). We therefore strongly
recommend that a change order be prepared based on this estimate and accepted for implementation. Please let us
know if you agree and we will contact the property owner and occupant to see if the temporary loss of two parking stalls
is an impediment.
Sincerely,
Steven M. Stanford, LPG
Environmental Practice Group, South Bend Operations Manager
"Weaver Consultants Group
7121 Grape Road
Granger, IN 46530
0: 574-271-3447 F: 574-271-3343 1 M: 219-808-3608
www.wcgro.com sstanford@wcgro.com
IMPORTANT NOTICE: The information contained in this email message (including any attachments) maybe confidential, privileged or both, and is intended exclusively for
the addressee(s) intended by the sender. If it appears you have received this email message in error, please notify the sender immediately and then delete; any other use of this
email message is prohibited. Thank you.
From: Aho, Scott [mailto:saho(&aecindy.com]
Sent: Tuesday, February 28, 2017 2:24 PM
To: Stanford, Steven
Cc: White, Chris; Jurczak, Kim; Smith, Jacob
Subject: carpenter bus cost estimate
Steve,
Please see attached estimate to hook up RW-4 to WB-8. Estimate allows for 2 people to construct a wellhead with a 1"
straw extending down into WB-8 from RW-4 with appropriate connections. Main connection will be with a 2" flexible
hose. The wellhead presently on RW-4 will have to be modified or rebuilt to allow connection to WB-8. Barricades will
be to block off the 2 parking spaces adjacent wells. Time allotted will allow for adjustments to the system and well heads
to optimize performance from WB-8. Don't hesitate to call should you have questions. Thank you
erican
nvironmental
American Environmental Corporation
8500 Georgetown Road
Indianapolis, IN 46268
Scott Aho
Certified Wastewater Operator(class B)
Senior Technician
317-871-4090 x244
cell 317-339-1432
saho@aecindy.com