To: The Board of Public Works and Safety May 315L, 2018
From: Greg Stiens
Director of Public Works and Engineering
RE: Recommendation to approve Change Order #1 to Contract 106-2017
Round Barn Road Project — A 2016 Community
Crossings Project
ITEM Description Original Qty.
Revised Qty.
Unit
Unit Price
Price
14 Compacted Aggregate No 53 20
-0-
TONS
$26.00
($520.00)
16 HMA 4, 70, Surface 9.5mm 404
-0-
TONS
$97.00 ($39,188.00)
16 Revised HMA 3, 76 Surface 9.5mm -0-
404
TONS
$96.51
$38,990.04
EW Earth Work for Shoulders -0-
1
LS
$340.70
$340.70
EW Void ReducinR Asphalt Membrane -0-
1,865 _
LF
$2.49
$4,643.85
TOTAL CHANGE ORDER # 1........................................................................$4,266.59
Original Contract.......................................................$485,506.76
Change Order#1........................................................S4.266.59
New Contract Amount..........................................$489,773.35
A
ed by: Greg Stiens
ublic Works and Engineering
Approv by: The Board of Public Works and Safety
Vie inson — Presid t
Approved by: Milestone Contractors, LLC