HomeMy Public PortalAboutCommon Street 3 Week Look Ahead July 27, 2020ONYX - Three Week Look Ahead 7/27/20 through 8/14/20
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
D. Lazarro
Week Of
TASK
CREW
7/27/20
through
7/31 /20
A. Crew: Re -construct inslands at the round a bout. Then start installing p-100 granite
at the round about.
A. Onyx 4 Man Crew
8/3/20 through
8/7/20
A. Crew: Finish installing curb at round a bout then pour rumble strip at round a bout.
Finish loam and fill at the round a bout
A. Onyx 4 Man Crew
8/10/20
through
8/14/20
A. Crew: Finish work at the retention area and install lights, then pour panels that need
to be poured.
A. Onyx 4 Man Crew