Loading...
HomeMy Public PortalAboutCommon Street 3 Week Look Ahead July 27, 2020ONYX - Three Week Look Ahead 7/27/20 through 8/14/20 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew D. Lazarro Week Of TASK CREW 7/27/20 through 7/31 /20 A. Crew: Re -construct inslands at the round a bout. Then start installing p-100 granite at the round about. A. Onyx 4 Man Crew 8/3/20 through 8/7/20 A. Crew: Finish installing curb at round a bout then pour rumble strip at round a bout. Finish loam and fill at the round a bout A. Onyx 4 Man Crew 8/10/20 through 8/14/20 A. Crew: Finish work at the retention area and install lights, then pour panels that need to be poured. A. Onyx 4 Man Crew