HomeMy Public PortalAboutCommon Street 3-Week Look Ahead July 20 2020ONYX - Three Week Look Ahead 7/20/20 through 8/7/20
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
D. Lazarro
Week Of
TASK
CREW
7/20/20
through
7/24/20
A. Crew: Finish Retention Area on Spring St.
A. Onyx 4 Man Crew
D. Pave Orcard St., Katherine Rd., and Columbia St.
D. Lazarro
7/27/20
through
7/31 /20
A. Crew: Re construct inslands at the round a bout. Then start installing p-100 granite
at the round about.
A. Onyx 4 Man Crew
8/3/20 through
8/7/20
A. Crew: Finish installing curb at round a bout then pour rumble strip at round a bout.
Finish loam and fill at the round a bout
A. Onyx 4 Man Crew