Loading...
HomeMy Public PortalAboutCommon Street 3-Week Look Ahead July 20 2020ONYX - Three Week Look Ahead 7/20/20 through 8/7/20 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew D. Lazarro Week Of TASK CREW 7/20/20 through 7/24/20 A. Crew: Finish Retention Area on Spring St. A. Onyx 4 Man Crew D. Pave Orcard St., Katherine Rd., and Columbia St. D. Lazarro 7/27/20 through 7/31 /20 A. Crew: Re construct inslands at the round a bout. Then start installing p-100 granite at the round about. A. Onyx 4 Man Crew 8/3/20 through 8/7/20 A. Crew: Finish installing curb at round a bout then pour rumble strip at round a bout. Finish loam and fill at the round a bout A. Onyx 4 Man Crew