HomeMy Public PortalAboutCommon Street 3-Week Look Ahead June 10, 201911[
lrr
... • • - • • •' f • • •
A. Onyx 4 Man Crew
B. Dagle Electric
Week Of TASK CREW
A. Crew: Continue working on installing electric conduit on Common St. heading A. Onyx 4 Man Crew
6/10/19 toward the round about
through
6/14/19
6/17/19 A. Crew: Finish installing electric conduit then start drainage at the round about
A. Onyx 4 Man Crew
through
6/21/19
6/24/19 A. Crew: continue drainage at the round about A. Onyx 4 Man Crew
through
6/28/19