Loading...
HomeMy Public PortalAboutCommon Street 3-Week Look Ahead June 10, 201911[ lrr ... • • - • • •' f • • • A. Onyx 4 Man Crew B. Dagle Electric Week Of TASK CREW A. Crew: Continue working on installing electric conduit on Common St. heading A. Onyx 4 Man Crew 6/10/19 toward the round about through 6/14/19 6/17/19 A. Crew: Finish installing electric conduit then start drainage at the round about A. Onyx 4 Man Crew through 6/21/19 6/24/19 A. Crew: continue drainage at the round about A. Onyx 4 Man Crew through 6/28/19