HomeMy Public PortalAboutCommon Street 3-Week Look Ahead June 15 2020ONYX - Three Week Look Ahead 6/15/20 through 7/3/20 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew D. Lazarro Week Of TASK CREW 6/15/20 through 6/19/20 A. Crew: Finish installing light bases and conduit./ Start Drainage at Spring St. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew 6/22/20 through 6/26/20 A. Crew: Finish installing drainage at Spring St. Start curb and sidewalk on Spring St. A. Onyx 4 Man Crew D. Mill Robins, Columbia St, and Barnard St. D. Lazarro 6/29/20 through 7/3/20 A. Crew: Finish installing drainage at Spring St. Start curb and sidewalk on Spring St. A. Onyx 4 Man Crew D. Pave Orcard St., Katherine Rd., and Columbia St. D. Lazarro