HomeMy Public PortalAboutCommon Street 3-Week Look Ahead June 15 2020ONYX - Three Week Look Ahead 6/15/20 through 7/3/20
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
D. Lazarro
Week Of
TASK
CREW
6/15/20
through
6/19/20
A. Crew: Finish installing light bases and conduit./ Start Drainage at Spring St.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
6/22/20
through
6/26/20
A. Crew: Finish installing drainage at Spring St. Start curb and sidewalk on Spring St.
A. Onyx 4 Man Crew
D. Mill Robins, Columbia St, and Barnard St.
D. Lazarro
6/29/20
through 7/3/20
A. Crew: Finish installing drainage at Spring St. Start curb and sidewalk on Spring St.
A. Onyx 4 Man Crew
D. Pave Orcard St., Katherine Rd., and Columbia St.
D. Lazarro