HomeMy Public PortalAboutCommon Street 3-Week Look Ahead November 18, 2019ONYX - Three Week Look Ahead 11-18-19 through 12-6-19 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew Week Of TASK CREW 11/18/19 through 11/22/19 A., B. Crew: Continue with Curb/ Back or sidewalk curb and pour sidewalks @ Common St. and Orchard St. A. Onyx 4 Man Crew C. pour sidewalks @ Common St. and Orchard St. Right side C. F & C Concrete sidewalk Crew thhroughrough t 11/29/19 A. Crew: loam back of curb @ Common St. and Orchard St. Right Side/ Start installing granite in round a bout. A. Onyx 4 Man Crew 12/2/19 through 12/6/19 A.Crew: complete granite at round a bout/ start installing granite islands A. Onyx 4 Man Crew