HomeMy Public PortalAboutCommon Street 3-Week Look Ahead November 18, 2019ONYX - Three Week Look Ahead 11-18-19 through 12-6-19
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
Week Of
TASK
CREW
11/18/19
through
11/22/19
A., B. Crew: Continue with Curb/ Back or sidewalk curb and pour sidewalks @
Common St. and Orchard St.
A. Onyx 4 Man Crew
C. pour sidewalks @ Common St. and Orchard St. Right side
C. F & C Concrete sidewalk Crew
thhroughrough t
11/29/19
A. Crew: loam back of curb @ Common St. and Orchard St. Right Side/ Start installing
granite in round a bout.
A. Onyx 4 Man Crew
12/2/19
through
12/6/19
A.Crew: complete granite at round a bout/ start installing granite islands
A. Onyx 4 Man Crew