HomeMy Public PortalAboutCommon Street 3-Week Look Ahead October 14, 2019ONYX - Three Week Look Ahead 10-14-19 through 11-1-19 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew Week Of TASK CREW 10/14/19 through 10/18/19 A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common from Katherine St. to Round a boutand down Church St. A. Onyx 4 Man Crew C. Continue pouring sidewalks B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew throughh through 10/25/19 A., B. Crew: Start Curb and sidewalk work at the intersecting streets at the round about. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. Continue pouring sidewalks C. F & C Concrete sidewalk Crew 10/28/19 through 11/1/19 A., B. Crew: complete additional water work/including irrigation line @ Orchard St. and Common St/ Start curb and sidewalk Orchard and Common St. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew