CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
Week Of
TASK
CREW
10/14/19
through
10/18/19
A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common
from Katherine St. to Round a boutand down Church St.
A. Onyx 4 Man Crew
C. Continue pouring sidewalks
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
throughh
through
10/25/19
A., B. Crew: Start Curb and sidewalk work at the intersecting streets at the round
about.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. Continue pouring sidewalks
C. F & C Concrete sidewalk Crew
10/28/19
through
11/1/19
A., B. Crew: complete additional water work/including irrigation line @ Orchard St. and
Common St/ Start curb and sidewalk Orchard and Common St.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew