HomeMy Public PortalAboutCommon Street 3-Week Look Ahead September 16, 2019_1ONYX - Three Week Look Ahead 9-16-19 through 10-4-19
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
Week Of
TASK
CREW
9/16/19
through
9/20/19
A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common St.
A. Onyx 4 Man Crew
C. Continue pouring sidewalks
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
9/23/19
through
9/27119
A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common
St./ Install tree drains on Katherine St.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. Continue pouring sidewalks
C. F & C Concrete sidewalk Crew
9/30/19
through
10/4/19
A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common St.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. Continue pouring sidewalks
C. F & C Concrete sidewalk Crew