Loading...
HomeMy Public PortalAboutCommon Street 3-Week Look Ahead September 16, 2019_1ONYX - Three Week Look Ahead 9-16-19 through 10-4-19 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew Week Of TASK CREW 9/16/19 through 9/20/19 A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common St. A. Onyx 4 Man Crew C. Continue pouring sidewalks B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew 9/23/19 through 9/27119 A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common St./ Install tree drains on Katherine St. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. Continue pouring sidewalks C. F & C Concrete sidewalk Crew 9/30/19 through 10/4/19 A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common St. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. Continue pouring sidewalks C. F & C Concrete sidewalk Crew