HomeMy Public PortalAboutCommon Street 3-Week Look Ahead September 30, 2019ONYX - Three Week Look Ahead 9-30-19 through 10-18-19 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew Week Of TASK CREW 9/30/19 through 10/4/19 A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common St./ Install tree drains on Katherine St. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew thhrouroughh 10/11/19 A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common St./ Loam and sead along sidewalks from Katherine St to Common St. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. Continue pouring sidewalks C. F & C Concrete sidewalk Crew 10/14/19 through 10/18/19 A., B. Crew: Start Curb and sidewalk work at the intersecting streets at the round about. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. Continue pouring sidewalks C. F & C Concrete sidewalk Crew