HomeMy Public PortalAboutCommon Street 3-Week Look Ahead September 30, 2019ONYX - Three Week Look Ahead 9-30-19 through 10-18-19
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
Week Of
TASK
CREW
9/30/19
through
10/4/19
A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common
St./ Install tree drains on Katherine St.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
thhrouroughh
10/11/19
A., B. Crew: Continue with Curb and prep sidewalk opposite store side on Common
St./ Loam and sead along sidewalks from Katherine St to Common St.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. Continue pouring sidewalks
C. F & C Concrete sidewalk Crew
10/14/19
through
10/18/19
A., B. Crew: Start Curb and sidewalk work at the intersecting streets at the round
about.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. Continue pouring sidewalks
C. F & C Concrete sidewalk Crew