Loading...
HomeMy Public PortalAboutCommon Street Three Week Look AheadONYX - Three Week Look Ahead 6/8/20 through 6/26/20 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew Week Of TASK CREW 6/8/20 through 6/12/20 A. Crew: Start to install Drainage structure, leaching basin, and trench drains. Remove and replace concrete in driveway @ 4 Middlesex Rd. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew 6/15/20 through 6/19/20 A. Crew: Finish installing light bases and conduit./ Start Drainage at Spring St. A. Onyx 4 Man Crew Mill Columbia Street and transitions 6/22/20 through 6/26/20 A. Crew: Finish installing drainage at Spring St. Start curb and sidewalk on Spring St. A. Onyx 4 Man Crew Pave Katherine Road, Orchard Street Ext. and Columbia Road