HomeMy Public PortalAboutCommon_Street_3-Week_Look_Ahead_August 19, 2019ONYX - Three Week Look Ahead 8-19-19 through 9-6-19 CREWS: A. Unyx 4 Man Grew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew Week Of TASK CREW 8/19/19 through 8/23/19 A. Crew: Pave round a bout, raise castings, then start curb from Columbia rd toward round a bout. A. Onyx 4 Man Crew 8/26/19 through 8/30/19 A., B. Crew: Continue with Curb and prep sidewalk A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. Start pouring sidewalks C. F & C Concrete sidewalk Crew 9/2/19 through 9/6/19 A., B. Crew: Continue with Curb and sidewalk A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. Continue pouring sidewalks C. F & C Concrete sidewalk Crew