HomeMy Public PortalAboutCommon_Street_3-Week_Look_Ahead_August 19, 2019ONYX - Three Week Look Ahead 8-19-19 through 9-6-19
CREWS:
A. Unyx 4 Man Grew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
Week Of
TASK
CREW
8/19/19
through
8/23/19
A. Crew: Pave round a bout, raise castings, then start curb from Columbia rd toward
round a bout.
A. Onyx 4 Man Crew
8/26/19
through
8/30/19
A., B. Crew: Continue with Curb and prep sidewalk
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. Start pouring sidewalks
C. F & C Concrete sidewalk Crew
9/2/19 through
9/6/19
A., B. Crew: Continue with Curb and sidewalk
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. Continue pouring sidewalks
C. F & C Concrete sidewalk Crew