HomeMy Public PortalAboutCommon_Street_3Week_LookAhead_04292019ONYX - Three Week Look Ahead 4-29-19 through 5-17-19
CREWS:
A. Onyx 4 Man Crew
B. Dagle Electric
Week Of
TASK
CREW
4/29/19
through 5/3/19
A. Crew: Continue on water services on Common St.
A. Onyx 4 Man Crew
5/6/19 through
5/10/19
A. Crew: Continue working on water service tie overs on Common St. then start water
gate work at the round about.
A. Onyx 4 Man Crew
5/13/19
through
through
A. Crew: Start on the drainage on Common St. where we left off from last year
A. Onyx 4 Man Crew
Dagle to be on site to run wire, install control panel, install mast arm, and install ped
lig hti ng(Tentitively)
113. Dagle Electric