HomeMy Public PortalAboutThree Week Look Ahead Common St. Watertown 3-9-20ONYX - Three Week Look Ahead 3/9/20 through 3/27/20
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
D. Dagle Electric
E. Garity Reclamation
Week Of
TASK
CREW
3/9/20 through
3/13/20
A. Crew: Mobilize site and install tree protection on Orchard St.
A. Onyx 4 Man Crew
3/16/20
through
3/20/20
A. Crew: Start lowering Casting on Orchard St./ Install conduit and speed indicator
foundation on Common St.
A. Onyx 4 Man Crew
Dagle Electric to install speed indicator at 206/207 Common St.
D. Dagle Electric
3/23/20
through
3/27/20
A.Crew: Work with Garity on Orchard St.
A. Onyx 4 Man Crew
E. Garity Reclamation crew to reclaim and grade Orchard St.
E. Garity Reclamation