HomeMy Public PortalAboutThree Week Look Ahead Common St. Watertown 4-20-20ONYX - Three Week Look Ahead 4/20120 through 5/8/20
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
D. Dagle Electric
E. Garity Reclamation
Week Of
TASK
CREW
4/20/20
through
4/24/20
A. Crew: Continue to Install curb and sidewalk on Orchard St. right side.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
4/27/20
through 5/1/20
A. Crew: Finish to Install curb and sidewalk on Orchard St. right side.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
5/4/20 through
5/8/20
A. Crew: Start to Install curb and sidewalk on Columbia St. one whole side.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew