Loading...
HomeMy Public PortalAboutThree Week Look Ahead Common St. Watertown 4-20-20ONYX - Three Week Look Ahead 4/20120 through 5/8/20 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew D. Dagle Electric E. Garity Reclamation Week Of TASK CREW 4/20/20 through 4/24/20 A. Crew: Continue to Install curb and sidewalk on Orchard St. right side. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew 4/27/20 through 5/1/20 A. Crew: Finish to Install curb and sidewalk on Orchard St. right side. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew 5/4/20 through 5/8/20 A. Crew: Start to Install curb and sidewalk on Columbia St. one whole side. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew