HomeMy Public PortalAboutThree Week Look Ahead Common St. Watertown 4-6-20ONYX - Three Week Look Ahead 4/6/20 through 4/24/20 CREWS: A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew D. Dagle Electric E. Garity Reclamation Week Of TASK CREW 4/6/20 through 4/10/20 A. Crew: Install conduit for Speed Indicator at 205/207 Common St./ Pave Orchard St. Extention and Spring St./ Raise castings on Orchard St. and Spring St A. Onyx 4 Man Crew 4/13/20 through 4/17/20 A. Crew: Install curb and sidewalk on Orchard St. one whole side. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew Dagle Electric to install speed indicator at 206/207 Common St. C. F & C Concrete sidewalk Crew through through 4/24/20 A. Crew: Continue and Install curb and sidewalk on Orchard St. one whole side. A. Onyx 4 Man Crew B. F & C 5-7 Man Crew C. F & C Concrete sidewalk Crew