CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
D. Dagle Electric
E. Garity Reclamation
Week Of
TASK
CREW
4/6/20 through
4/10/20
A. Crew: Install conduit for Speed Indicator at 205/207 Common St./ Pave Orchard St.
Extention and Spring St./ Raise castings on Orchard St. and Spring St
A. Onyx 4 Man Crew
4/13/20
through
4/17/20
A. Crew: Install curb and sidewalk on Orchard St. one whole side.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
Dagle Electric to install speed indicator at 206/207 Common St.
C. F & C Concrete sidewalk Crew
through
through
4/24/20
A. Crew: Continue and Install curb and sidewalk on Orchard St. one whole side.
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew