HomeMy Public PortalAboutThree Week Look Ahead Common St. Watertown 5-13-19ONYX - Three Week Look Ahead 5-13-19 through 5-31-19
CREWS:
A. Onyx 4 Man Crew
B. Dagle Electric
Week Of
TASK
CREW
5/13/19
through
5/17/19
A. Crew: Continue working on drainage on Common St.
A. Onyx 4 Man Crew
B. Dagle to start installing Cabnet
B. Dagle Electric
5/20/19
through
5/24/19
A. Crew: Continue working on drainage on Common St./Install Hydrant at Orchard St.
A. Onyx 4 Man Crew
B. Dagle to install Mast arm at Common St. and Spring st.
B. Dagle Electric
5/27/19
through
5/31 /19
A. Crew: Finish drainage on common St./ Then finish water gate at the round a bout
A. Onyx 4 Man Crew