HomeMy Public PortalAboutThree Week Look Ahead Common St. Watertown 5-13-19ONYX - Three Week Look Ahead 5-13-19 through 5-31-19 CREWS: A. Onyx 4 Man Crew B. Dagle Electric Week Of TASK CREW 5/13/19 through 5/17/19 A. Crew: Continue working on drainage on Common St. A. Onyx 4 Man Crew B. Dagle to start installing Cabnet B. Dagle Electric 5/20/19 through 5/24/19 A. Crew: Continue working on drainage on Common St./Install Hydrant at Orchard St. A. Onyx 4 Man Crew B. Dagle to install Mast arm at Common St. and Spring st. B. Dagle Electric 5/27/19 through 5/31 /19 A. Crew: Finish drainage on common St./ Then finish water gate at the round a bout A. Onyx 4 Man Crew