HomeMy Public PortalAboutThree Week Look Ahead Common St. WatertownONYX - Three Week Look Ahead 6/29120 through 7/17/20
CREWS:
A. Onyx 4 Man Crew
B. F & C 5-7 Man Crew
C. F & C Concrete sidewalk Crew
D. Lazarro
Week Of
TASK
CREW
6/29/20
through 7/3/20
A. Crew: Continue installing drainage at Spring St. Continue curb and sidewalk on
Spring St.
A. Onyx 4 Man Crew
D. Lazarro
7/6/20 through
7/10/20
A. Crew: Continue installing drainage at Spring St. Continue curb and sidewalk on
Spring St.
A. Onyx 4 Man Crew
D. Pave Orcard St., Katherine Rd., and Columbia St.
D. Lazarro
ththroughrough
7/17/20
A. Crew: Finish installing drainage,curb and sidewalk on Spring St. Start Retention
area on Spring St.
A. Onyx 4 Man Crew