HomeMy Public PortalAboutChange Order No. 1 to Contract No. 148-2014 - INDOT Coordination Agreement (R-37463) 1382810 - Bike Pedestrian facilitiesContract No:R -37463 Change Order No.: 001 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -37463 Letting Date:10/12/2017 Distdct:GREENFIELD DISTRICT AE:Prather, Michael PE/S:Stanley, William Status:Draft Change Order Information Change Order No.: 001 EWA: N or Force Acct: N Date Generated: 07/2312018 Date Approved: 00/00/0000 Reason Code: CHANGED COND, Constructability Related Description: INDOT's Suspension of Work Directive Time Extension Original Contract Amount $ 5,883,000.00 Current Change Order Amount $0.00 Percent: 0.000 % Total Previous Approved Changes $0.00 Percent: 0.000 % Total Change To -Date $0.00 Percent: 0,000 % Modified Contract Amount $ 5,883,000.00 Time Extension Information Date Initiated 07/23/2018 Date Completed -Q&00A)GW­- Original Contract Time SS Completion Date 11/30/2018 or SS Calendar/Work Days 0 SP Date 00/0010000 or SP Days (SS = Standard Specification, SP = Special Provision) Previous I !me Approved SS Days by AE:_ DCE:_ SCE: DDCM:- SS Days SP Days Value $ Revised Contract Time SS Completion Date 06/07/2019 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 M= = �,# 12 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE: V DCE: SCE: DDCM:. ($ per Change Order) LE $ 25OK-) LE $ 750K (-- LE $ 2 M (-- GT $ 2 M (Days per Contract) 50 SS days ) 100 SS days ( 200 SS Days) ( GT 200 SS days) I Total Change To-Date>5%? Scope/Design Recommendation Required? b Kkc PrekAher Date Issued Date to PM Date Returned Approval Authority Concurs with PM? Y / N If Y, Concurrence b Date Resolved by Date LPA Signatures Required? Y / N If Y, Date to LPA 8 - 9- / 8 Date Returned FHWA Signatures Required? Y / N If Y, Date to FHA Date Returned * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer.p.,C�,?,/,5: Date Comments: Contract No:R -37463 INDIANA Date:08M! Change Order No:001 Department of Transportation Page: 3 Contract: R -37463 Project: State: 138281 OOOLC3 Change Order Description: INDOT's Suspension of Work Directive Time Extension Reason Code: CHANGED COND, Constructability Related CLN PCN PLN Item Code Unit Unit Price co my, Comment Amount Change Total Value for Change Order 001 0.00 Contract Completion Date Time Adjustment Original Completion dt 11/30/2018 Adj comet dt 11130/2018 Adj No. of Days 51 Explanation: Work on the project was suspended from Thursday. April 19, 2018 thus Monday, June 11, 2018. Time Extension for the Suspension of Work = 51 Days. See Explanation Tab and attachment in Header Tab for further details. This Time Extension is being created per the direction of the AE, Mike Prather. Verbal approval was given to proceed with Issuing a Time Extension based on the original suspension of work directive issued on April 19, 2018. Approval was given to proceed with processing of this CO at a progress meeting held on July 19, 2018, A copy of the meeting minutes and those is attendance is attached for reference. Whereas, the Standard Specifications for fts contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation Return to work was requested to begin on Monday June I I th 2018. The Suspension of Work was from Thursday April 19, 2018 to Monday, June 112018. It was agreed by INDOT City of Richmond and Milestone that 51 days be added to the contract. PM HT Pharn has been notified of the change order. See Attachment in Header for further details. Additional documentation included with this CO Milestone formal request for days, a copy of the work suspension letter Issued by Mike Prather and a return to work directive letter issued by Mike Prather. 51 calendar days represents the total days of work suspension between April 19th. 2018 and June 1 1th, 2018. Divide the 51 calendar days by 5 work days per week and then added the 10 weeks to April 1st, 9019 thus arriving at the new contract completion date of June 7th, 2019. CO #1 does not include the (partial) costs incurred during the work suspension period; as previously discussed, the (total) costs will not be known until sometime in 2019; CO #1 should be for adding time to the contract in order to establish the new contract completion date of June 7th, 2019. Change Order Explanation for Specific Line Item It Is the intent of the parties that this change order is full and complete compensation for the worka above. Notification and consent to this change order is hereby acknowledged. '-fill""'tcho,cowactors, Lp. Contractor: � .� ! 6''- - Te, Signed By: Date: —2— — / 2 NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Contract NOR -37463 INDIANA Change Order No:001 Department of Transportation .......... . ------- ........ APPROVED FOR LOCAL PUBLIC AGENCY (SIGNATURE) (TITLE) (S)"ATY ,5,E) 12,-, OL­,t, (TITLE) PETS Date:08/02/2018 Page:, 4 (DATE) � -P/ -IF M.. APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION Approval Level Fume o; f . ApproverI I . D . ate S I tat I U I S '' Contract No:R -37463 INDIANA Change Order No:001 Department of Transportation (SIGNATURE) (SIGNATURE) APPROVED FOR LOCAL PUBLIC AGENCY (TITLE) (TITLE) &*kkkW:k*hkh***tr&*rt#Rkk*k*kWhYe44k4#�tr:k#+ktt*i.#*bh*R+t'R+R*^YRkk*k&1r#*hM*rt9+&R%^*Wnkkhirrt^kYWvkkkhk'fi'kk*#k#*%*A*Ak1r*k4*rtk *Yert*�rk:1'*Mk*#k**4# SUBMITTED FOR CONSIDERATION N&I (DATE) (DATE) APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION Page: Approval Level Flame of Approver Date Status Project Engineer/Supervisor Stanley, William 11/08/2018 Approved Area Engineer Prather, Michael 11/08/2018 Approved District Construction Director Colonis, James 11/30/2018 Approved