Change Order No.: 001
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -37463
Letting Date:10/12/2017
Distdct:GREENFIELD DISTRICT AE:Prather, Michael
PE/S:Stanley, William Status:Draft
Change Order Information Change Order No.: 001
EWA: N or Force Acct: N
Date Generated: 07/2312018 Date Approved: 00/00/0000
Reason Code: CHANGED COND, Constructability Related
Description: INDOT's Suspension of Work Directive Time Extension
Original Contract Amount $ 5,883,000.00
Current Change Order Amount $0.00
Percent: 0.000 %
Total Previous Approved Changes $0.00
Percent: 0.000 %
Total Change To -Date $0.00
Percent: 0,000 %
Modified Contract Amount $ 5,883,000.00
Time Extension Information
Date Initiated 07/23/2018 Date Completed -Q&00A)GW-
Original Contract Time SS Completion Date 11/30/2018 or SS Calendar/Work Days 0
SP Date 00/0010000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Previous I !me Approved SS Days by AE:_ DCE:_ SCE: DDCM:-
SS Days SP Days Value $
Revised Contract Time SS Completion Date 06/07/2019 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
M= = �,# 12
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE: V DCE: SCE: DDCM:.
($ per Change Order) LE $ 25OK-) LE $ 750K (-- LE $ 2 M (-- GT $ 2 M
(Days per Contract) 50 SS days ) 100 SS days ( 200 SS Days) ( GT 200 SS days)
I
Total Change To-Date>5%?
Scope/Design Recommendation
Required?
b Kkc PrekAher Date Issued
Date to PM Date Returned
Approval Authority Concurs with PM? Y / N If Y, Concurrence b Date
Resolved by Date
LPA Signatures Required? Y / N If Y, Date to LPA 8 - 9- / 8 Date Returned
FHWA Signatures Required? Y / N If Y, Date to FHA Date Returned
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer.p.,C�,?,/,5: Date
Comments:
Contract No:R -37463 INDIANA Date:08M!
Change Order No:001 Department of Transportation Page: 3
Contract: R -37463
Project: State: 138281 OOOLC3
Change Order Description: INDOT's Suspension of Work Directive Time Extension
Reason Code: CHANGED COND, Constructability Related
CLN PCN PLN Item Code Unit Unit Price co my, Comment Amount Change
Total Value for Change Order 001 0.00
Contract Completion Date Time Adjustment
Original Completion dt 11/30/2018 Adj comet dt 11130/2018 Adj No. of Days 51
Explanation: Work on the project was suspended from Thursday. April 19, 2018 thus Monday, June 11, 2018. Time Extension for the Suspension
of Work = 51 Days. See Explanation Tab and attachment in Header Tab for further details. This Time Extension is being created per the direction
of the AE, Mike Prather. Verbal approval was given to proceed with Issuing a Time Extension based on the original suspension of work directive
issued on April 19, 2018. Approval was given to proceed with processing of this CO at a progress meeting held on July 19, 2018, A copy of the
meeting minutes and those is attendance is attached for reference.
Whereas, the Standard Specifications for fts contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
Return to work was requested to begin on Monday June I I th 2018. The Suspension of Work was from Thursday April 19, 2018 to Monday, June
112018. It was agreed by INDOT City of Richmond and Milestone that 51 days be added to the contract. PM HT Pharn has been notified of the
change order. See Attachment in Header for further details. Additional documentation included with this CO Milestone formal request for days, a
copy of the work suspension letter Issued by Mike Prather and a return to work directive letter issued by Mike Prather. 51 calendar days
represents the total days of work suspension between April 19th. 2018 and June 1 1th, 2018. Divide the 51 calendar days by 5 work days per
week and then added the 10 weeks to April 1st, 9019 thus arriving at the new contract completion date of June 7th, 2019. CO #1 does not
include the (partial) costs incurred during the work suspension period; as previously discussed, the (total) costs will not be known until sometime
in 2019; CO #1 should be for adding time to the contract in order to establish the new contract completion date of June 7th, 2019.
Change Order Explanation for Specific Line Item
It Is the intent of the parties that this change order is full and complete compensation for the worka above.
Notification and consent to this change order is hereby acknowledged.
'-fill""'tcho,cowactors, Lp.
Contractor: � .� ! 6''- - Te,
Signed By:
Date: —2— — / 2
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract NOR -37463 INDIANA
Change Order No:001 Department of Transportation
.......... . ------- ........
APPROVED FOR LOCAL PUBLIC AGENCY
(SIGNATURE) (TITLE)
(S)"ATY ,5,E) 12,-, OL,t, (TITLE)
PETS
Date:08/02/2018
Page:, 4
(DATE)
� -P/ -IF
M..
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION
Approval Level Fume o; f . ApproverI I . D . ate S I tat I U I S ''
Contract No:R -37463 INDIANA
Change Order No:001 Department of Transportation
(SIGNATURE)
(SIGNATURE)
APPROVED FOR LOCAL PUBLIC AGENCY
(TITLE)
(TITLE)
&*kkkW:k*hkh***tr&*rt#Rkk*k*kWhYe44k4#�tr:k#+ktt*i.#*bh*R+t'R+R*^YRkk*k&1r#*hM*rt9+&R%^*Wnkkhirrt^kYWvkkkhk'fi'kk*#k#*%*A*Ak1r*k4*rtk *Yert*�rk:1'*Mk*#k**4#
SUBMITTED FOR CONSIDERATION
N&I
(DATE)
(DATE)
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION
Page:
Approval Level Flame of Approver Date Status
Project Engineer/Supervisor Stanley, William 11/08/2018 Approved
Area Engineer Prather, Michael 11/08/2018 Approved
District Construction Director Colonis, James 11/30/2018 Approved