Change Order No.: 005
INDIANA Department of Transportation
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -37463 Letting Date:10/12/2017
District:GREENFIELD DISTRICT AE:Prather, Michael PE/S:Stanley, William
Change Order Information
Change Order No.: 005 EWA: Y or Force Acct: N
Date Generated: 11/19/2018 -
Date Approved: 00/00/0000
Reason Code: CHANGED COND, Constructability Related
Description: Rock Excavation
Original Contract Amount
$ 5,883,000.00
Current Change Order Amount
$ 2,550.00 Percent: 0.043 %
Total Previous Approved Changes
$ 0.00 Percent: 0.000 %
Total Change To -Date
$ 2,550.00 Percent: 0.043 %
Modified Contract Amount
$ 5,885,550.00
Time Extension Information
Date Initiated 06/25/2018 Date Completed 06/28/2018
Page: 'I
Status: Draft
Original Contract Time SS Completion Date 11/30/2018 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description: During excavation for storm structures, Milestone encountered rock that obstructed the
removal and placement of storm structures on June 25, 26, 27 and 28, 2018. Time Extension for the rock
excavation = 3 days. See Explananation Tab and attachment in Header Tab for further details. This Time Extension
is being created by the request of Milestone.
Current Time Extension SS Days 9 SP Days 0 SP Days Value $ 0.00
Previous Time Approved SS Days by AE: DCE: SCE: DDCM:
SS Days SP Days Value $
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 3
SS Date 00/00/0000 or SP Days 0
Contract No:R -37463
INDIANA Department of Transportation
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority
($ per Change Order)
(Days per Contract)
Verbal Approval Required?
Total Change To-Date>5%?
Scope/Design Recommendation
Required?
Change Order No.: 005
Page: 2
AE: x DCE: x SCE: * DDCM:
(-LE$250K-)(-LE$750K-)(--LE$2M--)(--GT$2M--)
( 50 SS days ) ( 100 SS days ) ( 200 SS Days) ( GT 200 SS days)
Y / N If Y, by Mike Prather Date Issued 10-23-18
Y / N If Y, Copy to Program Budget Manager
Y / N If Y, Referred to Project Manager(PM)
Date to PM
Approval Authority Concurs with PM? Y / N If Y, Concurrence by
If N,Resolution: Approved
Date Returned
Date
- Resolved by
LPA Signatures Required? Y / N If Y, Date to LPA 11-19-18
FHVVA Signatures Required? Y / N If Y, Date to FHWA
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Disapproved
Date
Date Returned
Date Returned
Field Engineer Bill Stanley - United Date 11-19-18
Comments: United recommends approval of Change Order 5
CWASL:: F? -37463
S C'L 1382310 . Biwa 102500003
Charge Order MY 0 0 5.
Charge Order DeSCAP00n: Rack Excavator..
HIA
Reason Code: CNGE-Di C-ONC).
C. L N PC,., ;.-I". FL M Rem code Unit ink Me Cc my
Suponmenmi Mazy
P 3.
L! -! . C " I a ,l 9 il
1"S 2,5-5- N,
Too Me 0 Qaqe Day 05 = i 2 5K
Conmo CwQx1r; We Title A junmem 0KA10#16,
No W DPS
Eanatcn Wn annsyn V Vam ov"M W-We 0 Z"m*Qc =A PX =W"VA En QTWV am Nummew 0 vorn Enmms
on Me 2& 25 27 xn 26 2W 8 One Ereason Or me OW WIMM = a cay 5je EgionvyCon Tat and anechmmon Hea cc Too 'or
!Wv demo WN Me We::si-rt is Li�ilg o-eu*.ed Jb-� �hc
Mor.. the SWAM sj;-,Cifirntions for this contract ryovides for such wcrk to ba perlorm:c, inn foliowing Change is recartIrric-Ided.
GW IN of snman chany Go. Enisnwzri
HI has tie Ocoee & us narge Usm See huazmlem 0 HSWU fa._ No WAS ACONUM MM CCZUERnnn KcIsm my Los
00!.Ii es"one -c, -,a,, s Tne unitpi ce 4 Wn MO 268 NOOT St:.. an S0.Q7..v=S took page 178 1 MYS P0 pay hem 0:
a�rJ st.zh I a"mmyrev 4 ad be pes!= M S 725 00 per am& lam S oant lve5 le!'S ihan C., eo,al I-- Nev.,
conown uamplAn caS Q j�WW 23 a GO 11 june 9i 209 5 3 dq" C, 15 , a,, IN"wo 5"MW&%mww e5mc & we RM
7 2 7 ramwW 3 x 5 x 1 7 St --z:!.r -, 307 re.-r.--val 7
3Cn
Change Order Explanation for Spacift L.MS KGM
........... - —11.1... ....... ................... -1- ...... , ............... 11.1111-1 ..........
. ;aeliis "was maye arm- I %Y me canwAa
--ar'n re ,..... ___ "iae "a
Mt cy"Scin!%, sn:s ac
Milestofie Contractors, L.P.
Oak
NWE 04er SnOn We S:Cnalures VOL no colons emn.1.0 tMAIr re hwmawgu spal-r.
Contract No:R -37463 INDIANA
Change Order No:005 Department of Transportation
.... ..,.>..... .,,,... ,.......... ...... ,,,,,
I APPROVED FOR LOCAL PUBLIC AGENCY
(SIGNATURE) (TITLE)
(SIGNATURE (TITLE)
.>.>,.,....>.«.,,>.,..«..,..,,>,.,,.,.,>......,..,.»,...,..,..,,>............. >....>...........
,,,,>..,,.....,,...,,,..,».
SUBMITTED FOR CONSIDERATION
pEIS Bill Stanley - United
Date:12/04/2018
Page: 4
iz•za—iF
(DATE)
la-/s�
(DATE)
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION
Approval Level Name of Approver Date Status
000TRA[TNO. R-37463'B
PROJECT DESCRIPTION
knvto/intersection /b»do«no(s)./
CHANGE ORDER REQUEST SUMMARY
DESCRIPTION
PROPOSED SOLUTION SUMMARY
Ootnber1Q,
DATE OFSUBMISSION 20i8
ENHANCEMENT, BIKE AND PEDESTR|A NFACILITIES, kNA//NE
COUNTY. ONE0A|NST.7mSTAND 1On'ST}NTHE CITY OF
R|CHMOND.|N
ROCK EXCAVATION
REMOVAL OF ROCK
NOTE: Upon mouestfrnmEngineer, enter detailed description unpage l
ONSET DATE OF CHANGE June 26, 2018 CHANGE ORDER TYPE 104-03 Extra Work
COST COST COSTINCREASE /(DECREASE: $ 2,S50.00
The cost adjustment shall include lump sum and estimated totaled unit -priced item costs. Attach a separate sheet of unit price items
including item description, unit ol measurement, estimated quantity and unit price.
CHECK APPROPRIATE BOXES PER APPROPRIATE BASIS OFCOST CHANGE:
[] I09.03A|tered Quantities [] 109.05(a)Agreed Price [] 109.05(b) Force Account [] 109.05.02 Delay Costs
PROPOSED COST CHANGE INCLUDES: 1ZLabor El Material Z Equipment 21 Lease Agreement [Z
Subcontractor
TIME ADJUSTMENT INCREASE/(DECREASE):
(work days) 3
CHECK APPROPRIATE BOXES PER APPROPRIATE BASIS OFTIME CHANGE:
O108.08(a)Excusable, Non-Compensable 0 108.08(@Excusable, [ompensable
NOTE: If[ompensob4e,attach details based onI89.D5.2(c)Allowable Delay Costs.
Additional information maybaentered bythe contractor.
CHANGE ORDER ORIGINATION: |ND0T/LPA ID Contractor
DOCUMENTS AFFECTED:
OCuntmctSpedfications(re[ducname/no.) Zo328'l]ZO(pO175)ZVzDStandards
[] Contract Plans (,ef. docoame/no.)
CHANGE ORDER REQUEST FORM
CONTRACT NO. R-37463-B
DATE RECEIVED REQUEST FOR SUBMITTAL DATE OF
ADDITIONAL DETAIL [Select Date] October 19, 2018
ADDITIONAL DETAIL
DETAILED DESCRIPTION / JUSTIFICATION:
(Include location(s), actions of contractor, owner, and other stakeholders, key events and related couse(s), discoveries,
discussions, meetings, and effect on the contract if no action is taken. Also include references to key documents attached
or available to support this change order request.)
DURING EXCAVATION, THE CONTRACTOR ENCOUNTERED ROCK THAT OBSTRUCTED THE REMOVAL AND
PLACEMENT OF STRUCTURES
PROPOSED SOLUTION — ADDITIONAL DETAILS:
(Include proposed scope of work, means & methods, materials, equipment, utility relocation required, subcontracted
scope and the effect on the contract schedule. Also include references to attached documents including, but not limited
to, sketches, calculations, photos, material information, and submittals and meeting minutes.)
EXCAVATION AND REMOVAL OF ROCK
Contractor:
Name: (print) SC'CITT A-HESTER
(signature)
Date: 10/iq/A
Project Engineer/Supervisor: (signature is to acknowledge receipt of the document and does not signify agreement of the change order)
Name: (print) 11 S4 Q rl
(signature)
Date: /o - 7—
NOTE: The Contractor and PENS should retain a signed copy of this document for record.
CHANGE ORDER REQUEST FOW.-I
CONTRACT NO. R-37463-E
ATTACHMENT: UNIT PRICE ITEMS DETAIL
Attach or paste a Unit price item detail.
ROCK EXCAVATION PER SPECIFICATION IS PAID AT S125.00 CY; THE TOTAL
CY OF ROCK EXCAVATION THRU o6/28/18 WAS 20.40/CY C S125.00/CY=S2,550.00
DATES AND CY BELOW:
06/25/18
5.60/CY
06/26/ 18
1.33/CY
06/27/ 18
11.40/CY
06/28/18
2.07/CY
TOTAL:
20.40/CY
203,?8
is included in the Schedule of Pay Items. Common excavation and unclassified
excavation will be paid for on the unit basis or contract quantities in accordance w-vith
203.27(a), wvithout any quantity limit. unless otherwise shown in the Schedule of Pay
Items. Combined quantities of borrow, common and unclassified excavation not
exceeding 15,000 cu yd will be paid for on the basis of contract quantities in
1290 accordance with 203.27(a) with no adjustment to plan shrinkage factor. Except as
noted above, borrow, as well as all other excavation, will be paid for on the basis of
measured quantities in accordance with 203.27(b), unless otherwise shown in the
Schedule of Pay Items. Linear grading will be paid for at the contract unit price per
linear foot.
If the class of excavation is linear grading, additional borrow and the excavation
of and disposal of unsuitable material not included as pay items will be paid for as
follows:
1300 If the total quantity exceeds 5,000 cu yd at a given location, it will be paid for at
S8.00 per cu yd. If the total quantity exceeds 1,000 cu yd, but does not exceed 5,000
cu yd at a given location, it will be paid for at $12.00 per cu yd. If the total quantity
does not exceed 1,000 cu yd at a given location, it will be paid for at $15.00 per cu
yd.
Linear grading includes only such grading within the construction limits. All
gt ading the Contractor is directed to perform outside the construction limits, except
for the Contractor's convenience, will be paid for in accordance with 104.03 or
109.03 unless such grading is shown on the plans or in the Contract Information
1310 book.
Existing concrete building foundations, concrete walls, concrete columns, or
concrete steps not visible and not shown on the plans within the limits of the planned
excavation will be paid for at 10 times the contract unit price per cubic yard for
common or unclassified excavation, whichever is set out as a pay item. Unless a
waste area is established within the contract limits, the minimum pay for this work
will be $80.00 per cu yd.
Excavation and disposal of unsuitable material will be paid for at the contract
1320 unit price for the class of excavation involved. If no such pay item is included in the
contract and embankment is included as a pay- item, the excavation and disposal will
be paid for at the contract unit price for embankment, unless otherwise directed.
If there is no pay item for rock excavation and such is encountered, it will be
paid for at $125.00 per cu yd for quantities less than or equal to 100 cu yd. For
quantities greater than 100 cu yd pay will be determined in accordance with 104.03.
If there is no pay item for common excavation and if such is encountered, it will
be paid for at the contract unit price per cubic yard for borrow.
1330
176
99950-801
Rock
Date Excavation
5.60
096/25/18
06/26/18
1.33
06/27/18
5.18
06/27/18
6.22
06/28/18
2.07
TOTALS:
20.40
30,i
;c
Milestone Contractors, L.P.
Job Name: R-37463-B BIKE PEDESTRIAN FACILITIES
®ally Report
Diary: Date - 06/25/2018 (Monday)
Normal Ground;
High 80-90;
Low above 60;
Partly Sunny / Cloudy
Started digging to install structure 1/303 hit rock at 2 foot deep .
Rock removal 151.20 c.f.! 5.60 c.y rented hoe ram from Mcaleslers
Busted rock oul set structure.
—Note Index Notes—
[SAFE10] 69 safe days
Time Card: Date - 06/25/2018 (Monday)
SAFE10
Cost Codes
56000-102 j
99950-801
Description
TYPE HA5 INL ',
ROCK EXCAVA i
Prod. Qty.
1 EA
5.6 LS x
Code
Name
Class
---
BUTTON,GEOR
George W Button
FOR
114
7
STOLLE,CHRI
Christopher Stolle
HSUP
1/3
7
BLEVINS,JAM
James E Blevins
OPR
1/3
7
Totals for Labor
Hours: 34
Totals for Equipment
Hours: 0
, - indicates a completed item.
'(R)' - indicates a rework quantity.
Job Code184003
Foreman - BUTTON,GEOR
Foreman - BUTTON,GEOR Revision - 1 Shift - -t
Broken Out: (24/10/0)
Broken Out: (0/0/0)
Printed on: 0711312018 10:52:32 Page 1
Totals
8/4
8/3
8/3
Milestone Contractors, L.P.
Job Name: R-37463-B BIKE PEDESTRIAN FACILITIES
Mealy Report
Diary: Date - 06/26/2018 (Tuesday)
Low above 60, High 70-80, Overcast, Heavy Rain, Ground Wet - Workable
Safe Day Number # 7 of 7
Excavated and place str. 11 104
had to use hammer to remove old structure that was poured in place
Excavated 5X6X1 rock to set bottom. t'� 1
Heavy rain came in before we could get pipe in. after rain placed pipe and sand bagged around them. to much water to pour concrete.
Job Code184003
Foreman - DULL,VERNON
Time Card:
Date - 06/26/2018 (Tuesday)
Revision. - 0
Shift - 1
Cost Codes
10120-13
10160-15
56000-89
/Foreman---DU�L,VERNON
99950-801 `
56000-102
Description
Prod:.Qty.
CURB CONCR
28 LF
REMOVE EXIS
1 EA
STORM 24" RC
11 LF
ROCK EXCAVA 1I
0 LS /
TYPE HA5 INL
0.5 EA
Code
Name
Class
----
Totals
27931
Vernon Scott Dull
HSUP
8/2
8/2
26651
Michael W Burt
OPR
1
1
31.5
1
2
8/0.5
28332
Diane K Reese
LAB
1
1
4/.5
2
8/0.5
-- - - - -
5755
----.._..- ..- -- --- -- - ------
R-Cat314EL CR Excav
- - -
._.._ .. ----- - - —..... -.........
1
1
-
2
1
3
8
Totals for Labor
Hours: 27
Broken Out:
(24/3/0)
Totals for Equipment
Hours: 8
Broken Out:
(8/0/0)
Cost Code Notes: Date - 06/26/2018 (Tuesday)
Code. Slot Notes
99950-801 4 1.33 CY
Inspector Note
x Date:
c' - indicates a completed item.
'(R)' - indicates a rework quantity.
Foreman - DULL,VERNON
Printed on: 06/29/2018 07.59:17 Page 1
Milestone Contractors, L.P.
Job Name: R-37463-B BIKE PEDESTRIAN FACILITIES
Daily Report
Diary: Date- 06127/2013 (Wednesday)
Normal Ground;
High 80-90;
Low 50-60;
Sunny
Started digging to install structure 11304 high voltage power duct run is in conflict with structure .
Moved to structure 4306 dug and installed structure.
3 feet of 24"plastic 3 feet of 12" plastic
Had 8 feet by 7 feet by 30" rock removal
5.1 t;
Moved to structure 11307 helped Mike Burk and Kali finish digging and set structure.
*"Note Index Notes -
[SAFE 10) 72 safe days
Time Card Date - 06127/2018 AN d d
SAFE10
Job Code184003
Foreman - BUTTON,GEOR
e nes ay)
Cost Codes
15200-27
56000-102
`99950-801
Foreman - BUTTON,GEOR Revision - 1
Shift - ?
/
Description
STRUCTURE B
TYPE FiA5 INL
ROCK EXCAVA
Prod. Qty.
2 CY
1 EA
5.18 LS
Code Name
Class
''-
—
_. _-'
Totals
BUTTON,GEOR George W Button
FOR
.I
2/4
5
8/4
STOLLE,CHRI ChristopherJ Stolle
- -- - --- - --- -
FISUP
--._._.. --
1
- -
2/3
5
8/3
BLEVIN ,JAM James E Blevins
OPR
- - ---- --- - - ----------- _..._..
1
_ --
2/3
- - - -- - - -- -
5
-------------- -. _.. _ . _.._ ...
8/3
Totals for Labor
Hours: 34
Broken Out:
(24/10/0)
Totals for Equipment
Flours: 0
Broken Out:
(0/0/0)
x---- --- -- -- - — --
--- --—
Date: ----------
--------- - ---- -- - --- ---
c' -indicates a completed item.
-- - ---------
-- _._---------
indicales a rework quantify.
Printed on:
07/13/2018
10:56:04
Page 1
Milestone Contractors, L.P.
Job Name: R-37463-B BIKE PEDESTRIAN FACILITIES Job Code 184003
Daaly Report
Diary: Date - 06/2712018 (Wednesday) Foreman - DULL,VERNON
Low above 60, High 80-90, Partly Sunny / Cloudy, Ground Wet - Workable
Safe Day Number # 8 of 8
6�
Finished str. 11 104 Used 3 cy of concrete from Andy's truck to pour collars and flow line.
Excavated and removed old str. and placed str. 307
Excavated 8X7X3' of rock6.22 Cy
Time Card: Date - 0612712018 (Wednesday)
Foreman - DULL,VERNON Revision - 0
Shift - 1
COsfCodes:'''
10120-13
10160-15
56000-93 56000-102
Description
CURBCONCR
REMOVE EXIS
7ROCKEXCAVA
STORM 18" PV TYPE HA5 INL
Prod:-Qty.
0 LF '
1 EA
0 LF 1.5 EA
Code Name'
Class
._
Totals
27931 Vernon Scott Dull
HSUP
4
8
26651 Michael W Burt
OPR
1
2
5/3
8/3
28332 Diane K Reese
LAB
1
2
5/3
8/3
5755 R-Cat 314EL CR Excav
1
2
5
8
Cost.Codes
Description
Prod: Qty.-
Code
27931
26651
28332
5755
99110-900 LOST TIME
SUPERINTEND Enter all non-ch
0 LS 0 LS..
Name
Class
Totals
Vernon Scott Dull
HSUP
E4
8
Michael W Burt
OPR
8/3
Diane K Reese
LAB
8/3
R-Cat 314EL CR Excav
8
x
c' - indicates a completed item.
'(R)' - indicates a rework quantity.
Date:
Printed on: 06/29/201 B 08:00:03
Page 1
Milestone Contractors, L.P.
Job Narne: R-37463-B BIKE PEDESTRIAN FACILITIES
Daily Report
Diary: Date - 06/28/2018 (Thursday)
Normal Ground:
High 80-90;
Low above 60;
Sunny
SAFE10
Poured 4yds of concrete at structure #306 and #307 2 yds each backfill with type 1 8s 10 cyds each (finiishing up 2 previous str installed)
Moved to structure #308 14' of curb and gutter.
8'x7'xV rock removal 2.07. cu yds
Will set structure tomorrow
56000-102 Class A Concrete = 4 cyds
—Note Index Notes—
[SAFE10] 73 safe days
rev
Job Code184003
Foreman - BUTTON,GEOR
Time Card: Date - 06128/2013 (Thursday)
- - - - -- •.•
Foreman - BUTTON,GEOR
Revision - 2 Shift - 1
Cost Codes
10120-13
�/s0s50-801
Description
CURB CONCR
ROCI< EXCAVA
Prod. Qty.
12 LF
2.07 LS X
Code
Name
Class
--
-
Totals
BUTTON,GEOR
George W Button
FOR
5/2
3
8/2
STOLLE,CHRI
Christopher J Stolle
HSUP
5/1
--- -- -----
3
8/1
BLEVINS,JAM
James E Blevins
OPR
5/1
3
8/1
BURT,MICHAE
Michael W Burt
OPR
5/1
3
8/1
REESE,DIANE
Diane K Reese
LAB
5/1
3
8/1
Totals for Labor
Hours: 46 Broken Out:
(40/610)
Totals for Equipment
Hours: 0 Broken Out:
(0/0/0)
Date:
'r.' - indicates a completed item.
'(R)' - indicates a rework quantity.
Printed on: 0711312018 11:03:28 Page 1