NOTICE OF CONSTRUCTION
BOYLSTON STREET
GAS MAIN INSTALLATION
July 7, 2017
Dear Boylston Street Abutter:
The Watertown Department of Public Works announces that National Grid will be starting
construction to install a new plastic gas main along Boylston Street from Fairfield Street to
#203-205 Chauncey Street in order to replace an aged gas main.
You are receiving this notice since you are an immediate abutter to the project area. The
project will include construction activities such as excavation and backfilling, paving, services
renewals, restoration of disturbed surface areas, traffic control, and site clean up.
Contractors will be performing the work on behalf of National Grid. Feeney Brothers
Excavation Corporation of Boston, MA will be responsible for excavation, backfilling and
restoration.
Work is proposed to begin on Wednesday, July 12, 2017 and is anticipated to be complete in
two months. Final cleanup and paving restoration activities will be necessary.
Work hours will generally be between 7:00 am and 4:00 pm Monday through Friday, with the
potential for Saturday work. There may be dust and/or noise generated by the work and minor
traffic / detour inconveniences. Existing gas services will be disrupted when new installations /
connections to the new gas main must be made.
Should you have any questions concerning the project, please contact National Grid at
781-907-3804. If the Watertown Department of Public Works can be of any assistance, please
feel free to contact the DPW at 617-972-6420.
We appreciate your cooperation and patience throughout the duration of this project.
Gerald S. Mee, Jr.
Superintendent of Public Works
K:INational Grid Roadway IetterslBoylston St WAT Abutter Letter Start 7122017. doc