No. 14-1— Date of Adoption MAY 15, 2014
AUTHORIZING A PROFESSIONAL SERVICES CONTRACT
FOR ENGINEERING SERVICES WITH T &M ASSOCIATES -
STORMWATER PUNIP STATION & EQUALIZATION BASIN
NOE STREET AREA DRAINAGE LNIPRO VENIENTS
FINAL DESIGN PHASE SERVICES
WHEREAS, the Borough of Carteret is in need of specialized engineering services in
connection with the Noe Street Area Drainage Improvements Final Design Phase Services for
the Stormwater Pump Station & Equalization Basin; and
WHEREAS, the Borough's Consulting Engineers, T &M Associates, possess the requisite
and expertise to provide said services; and
KREAS, T &M Associates has submitted a proposal to provide said engineering services at
cost not to exceed $104,400.00; and
the Mayor and Council have reviewed said proposal; and
the Chief Financial Officer has certified that fiords are or will be available for said
THEREFORE, BE IT RESOLVED by the Mayor and Council of the Borough
, County of Middlesex, State of New Jersey, as follows:
I. That the proposal from T &M Associates for engineering services related to
the Noe Street Area Drainage Improvements Final Design Phase Services for
the Stormwater Pump Station & Equalization Basin in a total amount of
$104,400.00 billable in accordance with T &M's existing contract with the
Borough is hereby approved;
2. That aimexed hereto is a copy of said proposal;
t
3. That this action is approved as an award of a professional services contract
pursuant to N.J.S.A. 40A:11- 5(1)(a) in accordance with the Borough's Fair
and Open Process as authorized by law.
Adopted this 15" day of May, 2014
and certified as a true copy of the
original on May 16, 2014.
KATHLEEN M. BARNEY, MMC
Municipal Clerk
RECORD OF COUNCIL VOTE
COUNCILMAN
1'GS
NO
NV
A.B.
COUNCILMAN
NV
A.B.
BELLINO
KRUPI
DIAZ
X
NAPLES
IYESNO
DIMASCIO
X
sITARZ
X - Indicate Vote AB - Absent NV - Not Voting XOR - todicates Vote
to Overrule Vela
Adopted at a meeting of the
Kftinicipal Council
� 15 2014
1373 Broad Street, Suite 306, Clifton, New Jersey 07013
(973) 614 -0005 ' fax (973) 614 -0025 * www.tandanassociates.com
CART -02211
Mayor Daniel J. Reiman
Borough of Carteret
Municipal Building
61 Cooke Avenue
Carteret, NJ 07008
Re: Stormwater Pump Station & Equalization Basin
Noe Street Area Drainage Improvements
Final Design Phase Services
Dear Mayor Reiman:
January 21, 2014
i rm
ASSOCIATES
T &M Associates is pleased to present this scope of services and fee estimate for final design and permit
related services for the Noe Street Area Stormwater Pump Station and Equalization Basin improvement
project.
Prefect Narrative
The proposed improvements consist of the construction of a new 8000 gpm Stormwater Pump Station
and Equalization Basin along Noe Street, on Bieck 177, Lots 2, 3, 4, and 5.01. It is currently envisioned
that the new pump station will be similar in size and design to the Borough's existing Beverly Street
Stormwater Pump Station. A new outfall pipe from the pump station is also proposed. The outfall pipe
will discharge to Noe's Creek crossing under Industrial Road and Includes a tide gate. The outfall pipe
routes will be evaluated and it is anticipated the route with the least environmental impact and
construction costs will be chosen. Potential utility conflicts will also be evaluated via test pits as
required.
In addition to the main pump station and basin, the project will also include drainage and road
improvements in the vicinity of Noe Street to ensure that stormwater runoff will effectively flow to the
new pump station. Portions of the existing drainage collection system will require replacement and
modification to divert runoff from the low point areas on Harris and Noe Streets and the ends of Lowell
and Emerson Streets as well as, Pershing Avenue to the new basin and pump station. The new pipes will
be larger, re -sized to convey the runoff from the 25 -year storm and diverted to discharge into the
proposed basin. Based on our preliminary review, as much as, 65% of the Lower Noe Street Area
Drainage Basin Collection System will be Improved. See Figure 1.
ENERGY & UTILITIES , ENVIRONMENTAL SERVICES - PUBLIC WORKS
REAL ESTATE DEVELOPIMEN - i • TRANSPORTATION • WATER RESOURCES
Regional Offices in NEW JERSEY, PENNSYLVANIA and 01 -110
ASSOCIATES
CART -02211 January 21, 2014
Page 2 of 8
Le: Mayor Daniel J.Relmon
Borough of Carteret
Re: Stormwater Pump Station & Equalization Basin
Noe Street Area Drainage Improvements
Final Design Phase Services
Figure 1
The Stormwater equalization basin will serve as a "wet well' for the pump station and store runoff
during high tide events while the new pumps discharge the stormwater out of the area. During low tide
the outfall pipe from the pump station and basin will function as a gravity discharge system.
The proposed project improvements will also include rehabilitation of the affected roadways. The roads
will be fully reconstructed as necessary and include full width milling and resurfacing. We have also
assumed curbs and sidewalks will be replaced along the portion of the streets where new pipes will be
Installed.
TM
ASSOCIATES
CART -01211 January 21, 2014
Page 3 of 8
Le: Mayor Daniel J. Reiman
Borough of Carteret
Re: Storm water Pump Station & Equalization Basin
Noe Street Area Drainage Improvements
Final Design Phase Services
Scope of Services
TASK 1: Permit & Approvals
In order to authorize regulated activities in environmentally sensitive areas, such as Noe's Creek, T &M
will prepare and submit the following permit applications:
• Waterfront Development Application
• General Freshwater Wetlands GP 11 / Coastal Wetland Permit
• USACOE Nationwide Permit for Discharges
• Individual Flood Hazard Area Permit Application
• Soil Erosion and Sediment Control Permit
The application package(s) will be submitted to the N1DEP's land Use Regulation Program and the
Freehold Soil Conservation District. T &M will review applicable basemaps to delineate the limits of
freshwater wetlands and State open waters throughout the project area. Upon completing the
delineation, T &M will calculate the total wetland impacts associated with the final design. T &M will
make every effort to minimize wetland impacts while still meeting the goals of the project. Specifically,
Impacts will be kept to a minimum in order to avoid an Individual Freshwater Wetland Permit and
mitigation.
If the N1DEP specifies that a mitigation plan is required to offset wetland impacts, a separate scope of
services and fee estimate will be prepared and submitted to the Borough for review and approval. After
completing the wetland delineation and design plans, T &M will prepare and submit the Permit
Applications. Please note that all permit fees will be paid for directly by the Borough. This scope of work
does not anticipate any T &E species investigation, Cultural Resources investigation or Intertidal /subtidal
shallows mitigation.
TASK 2: Final Construction Plans and Specifications
Under this Task T &M will prepare final construction plans for the drainage improvements for the
project. The final plans will be submitted to the Freehold Soil Conservation District and be used for
public bidding. During the final design phase, we will perform the following:
• Prepare final pump station structure and building layout.
Re; Stormwater Pump Station & Equalization Basin
Noe Street Area Drainage Improvements
Final Design Phase Services
• Prepare final Site Plans for the pump station and equalization basin including layout drawings
Including driveway, fencing, grading, and other site amenities.
• Prepare a final plan of the outfall pipe /force main and, tide gate location.
• Determine the limit of disturbance for the project and any regulation impacts, if any.
• Provide all SESC countermeasures.
• Provide final construction cost estimates.
The plans will indicate the wetland and State open water limits and floodplain limits as determined using
Federal Emergency Management Agency ("FEMA ") information and NJDEP Methods 2 through 4. The
following plans are anticipated:
• Cover/Title Sheet
• Legend and General Notes
• Existing Conditions Plan
• Grading, Drainage and Soil Erosion and Sediment Control Plans
• Stormwater Pump Station General Plan and Elevation
• NJDEP Environmental Permit Plan
• Outfall Profile Plan
• Construction Details
• Soil Erosion and Sediment Control Notes.
• Soil Erosion and Sediment Control Details.
Upon authorization T &M will continue to advance the project to Final Construction Documents and
upon approval of all permit agencies, will finalize same. This task will be on -going from preliminary
design and throughout the permit review process. The following items are anticipated under the final
design phase of this task.
• Perform final design stormwater, mechanical, electrical and structural calculations.
• Prepare final pump station layout plans including mechanical, electrical and structural details.
• Prepare one -line diagram and specialty schematics, such as wiring for ventilation controls or
pump controls
• Develop building plans showing interior and exterior lighting, receptacles, auxiliary devices such
as electric heaters and fans. These plans will include locations of power and control equipment
as well as fire alarms, security devices and communications equipment. Partial equipment
elevations will be provided where appropriate.
• Prepare control panel and sensor drawings, panel schedules, fixture and equipment schedules
and electrical details.
Re: Stormwater Pump Statlon & Equalization Basin
Noe Street Area Drainage improvements
Final Design Phase Services
• Coordinate with electrical, structural, and architectural departments regarding power and
controls for the pump station, structural design for the pump station wet well, and building
design.
• Finalize pump station and equalization site plan and site grading including access driveway,
grading, and fencing.
• Prepare plan and profile of proposed outfaii pipe alignment. This task will Include a jack and
bore crossing of Industrial Road and design and preparation of plans and details for an outlet
structure and potential tide gate.
• Prepare technical construction specifications for all aspects of the project.
• Prepare quantity takeoffs.
• Prepare final construction cost estimate.
• Prepare Bid Package using the Borough's preferred front end sections suitable for public bid.
TASK 3: Bidding and Recommendation of Award
T &M will aid the Borough In the bidding process and contractor selection as follows:
• We will coordinate placing the advertisement in local newspapers for bids.
• Prepare twenty (20) sets of contract documents Including bid proposal and specifications for
advertisement. Plans will be made available out of our Clifton office.
• Answer prospective Bidder questions and prepare revisions and Addenda to the bid documents
if necessary during the bid process.
• Attend the bid opening at the Borough of Carteret municipal building.
• Prepare a bid summary identifying the lowest, responsive bidder.
• Consult with the Borough Attorney during the bid review and make a recommendation of
award.
TASK 4: Project Management
Under this task T &M will implement our in -house Project Management guidelines and QA /QC initiatives
to coordinate with all engineering disciplines Involved in the project and to coordinate and inform the
Borough of the project milestones and deadlines to keep the project on schedule and on budget.
Re: Stormwater Pump Station & Equalization Basin
Noe Street Area Drainage Improvements
Final Design Phase Services
txceotions
The following items are specifically excluded from our final design phase services for the subject scope
of services and fee estimate.
• All permit fees will be the responsibility of the Borough.
• Police for traffic control needed during survey and /or other field activities will be provided by
the Borough at no cost.
• Investigations, testing, lab work, research, sampling or any other services related to soil and /or
groundwater contamination.
• Survey services related to easements, property acquisition and property boundary
determinations.
• Construction Inspection services.
• Tasks not specifically listed in Items 1 through 4 above.
Fee Schedule
T &M will provide the above described scope of services for an estimated fee not to exceed $104,400.
The cost of services for construction administration and inspection services are not included in the
above estimate and will be provided in a separate scope letter prior to the construction phase, Tasks
shall be billed in accordance with the Schedule of Hourly Billing Rates and Schedule of Miscellaneous
Charges in our current municipal contract.
Proiect Fees
TASK 1: Permit Application Follow -Up $ 2,500
TASK 2: Final Plans and Specifications $ 89,900
TASK 3: Bidding And Recommendation of Award $ 4,000
TASK 4: Project Management $ 8,000
Total $104,400
Project Schedule
T &M Associates will begin work on final project design upon written authorization to proceed. We
anticipate completion of the final project plans for public bidding within 75-days. T &M Associates will
work closely with the Borough so that the project Is completed expeditiously and on schedule. Upon
authorization of the final design services, T &M will work closely with NJDEP to expedite the final permit
review process. The NJDEP review period is anticipated to be a minimum of 120 -days from notice of
administratively complete project permit documents.
Re: 5tormwater Pump Station & Equalization Basin
Noe Street Area Drainage Improvements
Final Design Phase Services
We appreciate this opportunity to submit this scope of services for professional services in connection
with the Noe Street Area Stormwater Pump Station.
We will await your authorization to proceed. in the interim, if you have any questions or require
additional Information, please call.
DJN:sp
Cc: John DuPont, Director of Engineering
Kathy Barney, Clerk
Patrick DeBlasio, CFO
H: \Cart\02211 \Correspondence \Draft Proposal -ASiM - 1.20.14 -Final Des ign.doc
J
'+' � o,, �.6J.'�•13.1 -V.41 L1 .4.�� `w✓W.L .lLA -�� '
MIDDLESEX COUNTY
TEL (732) 5413600
FAX (132) 641 -6925
OFFICE OF
YATgLBEN M. BA13MBY, RMC /CMC 61 COOKE AVB:NUE
MUNICIia1 CLERK CARTERET, NEW JERSEY 07008
7 � 9
T0: Patrick DeBlasio,
Treasurer
Borough,. Carteret
REQUEST FOR CERTIFICATION OF AVAILABLE FUNDS:
For: /
I
G
Name of Account: #/9—/d/
AMOUNT TO BE ENCUMBERED:
KATHLEEN M. DARNEY,
Municipal Clark
CERTIFICATION OF,AVAILABILITY OF FUNDS
I, Treasurer of the Borough of Carteret, do hereby certify that
there are sufficient funds available in the current budget to
enable the Municipal Council to authorize the entering into
Contract between the Borough of Carteret and :'
pa-
The funds available for this contract are in the Budget,
account of:
_a�_iy- io3 -�aa
in the amount o£:
By this caiiification, I have hereby encumbered the above named
account for the amount of the contract pending Council, action.
_at
Pat ck DeBlaaio,
• Treasurer
DATE:
AFFIDAVIT OF PUBLICATION
The following is a true copy of an Ordinance or Resolution of
the Borough of Carteret that has appeared in the Star Ledger,
a newspaper which is printed in Newark, New Jersey and
published in Essex County, of general circulation in said ,
2014county and state. One (1) time(s) once in each issue as
follows:
July 22, 2014
}
Notary PuMN&K,f jMersey
NOTARY PUBLIC OF NEW JERSEY
MY COMMISSION EXPIRES MAY 2
Kathleen M. Barney, M
Municipal Clerk
Sworn and Subscribed before
Me this 2211day of
'.
BOROUGH OF CARTERET '
20 COOKE AVENUE `' }
ji) Pkb tL�p t)
CARTERET, NEW JERSEY 07008
THIS AGREEMENT: made this 15 of May 2014
By and between: T &M Associates
1373 Broad St., Suite 306
Clifton, NJ 08859
And the Borough of Carteret a municipal Corporation having its Principal Office at the
Borough Hall, 61 Cooke Avenue, Carteret, New Jersey 07008
As per Resolution Number 14 -101.
THE CONTRACTOR does hereby agree to perform the following: PROFESSIONAL SERVICE
SPECIALIZED ENGINEERING SERVICES IN CONNECTION WITH THE NOE ST. AREA DRAINAGE
IMPROVEMENTS FINAL DESIGN PHASE SERVICES FOR THE STORMWATER PUMP STATION &
EQUALIZATION BASIN.
NOT TO EXCEED $104,400.00.
According to the terms set forth in the Resolution.
THE BOROUGH does hereby agree to pay the Contractor the sum set forth in the Resolution.
IN WITNESS WHEREOF, the parties hereto have hereunder set their hands and seals or caused these
presents to be signed by their proper corporate offices and their corporate seals to be hereto
affixes, the day and year written above.
WITNESSED BY:
For the Co orationnr
BY:
TITLE:
BOROUGH OF CARTERET
BY:
Daniel J. Reim
Mayor
Kathleen M. Barney
Municipal Clerk