HomeMy Public PortalAboutChange Order No. 18 to Contract No. 148...82810 - Bike Pedestrian facilitiesContract No:R -37463
Change Order No.: 018
INDIANA Department of Transportation Page: I
Construction Change order and Time Extension Summary
Contract Information Contract No.: R -37463
Letting Date:10/12/2017
District: GREEN FIELD DISTRICT AE:Prather, Michael
PEIS:Stanley, William Status:Draft
Change order Information Change Order No.: 018
EWA: Y or Force Acct: N
Date Generated: 04/30/2019 Date Approved: 00/00/0000
Reason Code: CHANGED COND, Constructability Related
Description: Replace Power Feed to Existing Signal Controller
Original Contract Amount $ 5,883,000.00
Current Change Order Amount $ 1,95'1.77
Percent: 0.033 %
Total Previous Approved Changes $-301119.55
Percent:--0.512 %
Total Change To -Date $-28,167.78
Percent: -0.479 %
Modified Contract Amount - $ 5,854,832.22
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00
Previous Time Approved SS Days by AE: DCE: SCE: DDCM:
SS Days SP Days Value $
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:R -37463
INDIANA Department of Transportation
Construction Change order and Time Extension Summary
Review and Approval Information
Required Approval Authority
($ per Change order)
(Days per Contract)
Verbal Approval Required?
Total Change To-Date>5%?
Scope/Design Recommendation
Required? ,
Change Order No.: 018
Page: 2
AE: M.Prather DCE: SCE: * DDCM:
(-LE$250K-)(-LE$750K-)(--LE$2M--)(--GT$2M--)
( 50 SS days) (100 SS days) (200 SS Days) (GT 200 SS days)
Y / N If Y, by G. Steins Date Issued 10/29/18
Y / N If Y ;Copy to Program Budget Manager
Y / N If Y, Referred to Project Manager(PM)
Date to PM Date Returned
Approval Authority Concurs with PM? Y 1 N If Y, Concurrence by
If N,Resolution: Approved
Resolved by
LPA Signatures Required? Y1 N If Y, Date to LPA 4/30/19
FHWA Signatures Required? Y 1 N If Y, Date to FHWA
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer Date
Comments:
Date
Disapproved
Date
Date Returned
Date Returned
Contract NoKR -7463 INDIANA Date:04/3012019
Change. -Order No:016 Department o Transportation Page-: 3
moist'"x9�.»"'e"+QY!°y�r*`,�`X'�p°F'sx-.�'°.j;�C •.e".:°;at:r;am ar'uSf�w,.ssyg<w.:s^�v?.+;Y.Y.t>c7�:?nesixa+:?N.oam.:+:"'¢�'a�-'w:'�iW!t-^. +st^v�;na�+sc�r .�"y"'. ==g.�,.,h.;.....-.,.W2csc�..a.. ..aa ax:xeaevxwrw+�vca:-wawrsssx�sw„..,"a,..nHm*
Contract: R '37463
i t'o 6t. 138210 w State.Y1 38281 0\./1��r C
Change :Order N�br: .018
Change O rd6e De'scrip#ion: Repiade' Power Peed to E.�istind Signl Controller
reason Code: CHANGED' oND', Owstructabiiity.Related
�CLN PG�I PLN item fade �lnit Unit la�riceDt� Q#�. C�mr�ent Amvun� �Gf�ange
.0185 1882810 0185 .80MZ9 60 LS- 1195.1.770 1.000 :C Amounf,$= i,951.77
.tteM -Descripftion: ELECTRICAL WOkK
Supplementaf Des!:00onI: Remove and. Replace.
Supplemental Ddscr1'pt11dn2:- EX' Ii ing-Sig6al- Pow6r- Feed
Total Value -for.-Change Order 018 = - "
whereas, the Standard SpecificMiQns for this Gd-Oftaci provides four. such work%to be.peffvrined, the-folloWtng change is recomimended,
'General. or Standard 0hange Drder.Explanation
`["hit change-oMer c'M bbnsates MiiWnne and-James.H Qrew for Work:bompleted -to-install •a riew- power feed to. the existing signal-(oc;ated -at 3rad-
and lain. There- was. -an,existing handhole that will now baWthin the Maih Street and 3rd Street intersectlan which contained the.power-feed
frorn RPL which powers the.existing trafFic signal at the intersection.. RPL.does pot Want to work-iri the existing tnanhate W ause.their.did not
install it4nd the existing c€7ndition is a patchwork syrsten that.has -been cobbled'tagether-over the_ybars. The-aervice has been hitseveral times
.and spliced together Gills NWth-INE)OT reviewed thiswith Milestone'and.with Mike Prather- afteir a-proores!§ nisieting-,on.
'October-17, 2018; The CIty. requested RPL.ta proviide�.:at prlco-.for-setting-'a� new ha�ndhole'and'running oeav po%ver,:t6 tie sigri�l cabinet; This' vv rk
would eliminate the exlsiing servlde .and provide,a new power feed to the -existing controller cabinet -,Greg Steins requested thts work be
performed -as part'.of the -project sine the area is already under construction. A -breakdown of.costsassociated with this work has been'included
with this -change order �s:.supporting'd4�r�rnentation.. The. �rork was completed do Qctober '2J, -201-8.
Dhange.Order Explanaiton. 'for Spa ciftc Line Item
*yk�f,Tr�k�r!#�1r,Y,��k+k****�*#*arfer!**it�ir�rf��t+t�#'�**+�'�' k*iri#t#�t�*frl�.t�*k�#fts:�k����k �rieacit it,►yY� *{��?�#,k�*atit+t*1�1�► �k#itdr�4-+�r�4yRki��k��#it-A,t�t+�*�k# �k#�
Ifis theintent ofthe parties thakhis change -order is full and complete compensatfon_for the work desc i -above.
Notifica.tiorvand cohsent.toAhis change order is hereby acknoWlddged:
e we -Contractors;. LwPm - .
Ontradtar'.. Signed -By:
'NOTE:'Other'required :State acld FHWA: sigriatUr" s `,wilt 'b'e dbt�ined electronicatly through t4d S1tWa`nager`sgUe' M.
Contract No:R -37463 INDIANA Date:04/30/2019
Change Order No:018 Department of Transportation Page: 4
APPROVED FOR LOCAL PUBLIC AGENCY
C
L'OOF URE) (TITLE) (DATE)
(SIG URE) (TITLE) (DATE)
-fF
,on SUBMITTED FOR CONSIDERATION
Ae .0001��
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORTATION
Approval Level Name of Approver Date Status
CHANGE ORDER REQUEST FORM
CONTRACT NO. R-37463-B " DATE OF SUBMISSION April 15, 2019 '
PROJECT DESCRIPTION ENHANCEMENT, BIDE AND PEDESTRIAN FACILITIES, WAYNE
COUNTY, ON E MAIN ST, 7TH ST AND 1OTH-ST IN THE CITY OF
(route / intersection % bridge no(s).) R10 HMON D, IN
CHANGE ORDER REQUEST SUMMARY INSTALL NEW POWER FEED TO THE CONTROLLER CABINET AT 3Ro{
DESCRIPTION AND MAIN
PROPOSED SOLUTION SUMMARY JAMES H DREW, SUBCONTRACTOR TO INSTALL POWER FEED TO
CONTROLLER CABINET
NOTE: Upon request from Engineer, enter detailed description on page 2.
ONSET DATE OF CHANGE [Select Date] CHANGE ORDER TYPE 104.03 Extra Work
PROPOSED COST AND TIME ADJUSTMENT
: COST INCREASE DECREASE
COST j (DECREASE): $ 1,951.77
The cost adjustment shall include lump .sum and estimated totaled unit -priced item costs. Attach a separate sheet of unit price items
including item description, unit of measurement, estimated quantity and unit price.
CHECK APPROPRIATE BOXES PER APPROPRIATE BASIS OF COST CHANGE:
❑ 109.03 Altered Quantities ® 109.05{a} Agreed Price ❑ 109.05(b) Force Account ❑ 109.05.02 Delay Costs
PROPOSED COST CHANGE INCLUDES: ❑ Labor ❑ Material ❑ Equipment ❑ Lease Agreement 0 Subcontractor
TIME ADJUSTMENT INCREASE j DECREASE): (workdays) 0
CHECK APPROPRIATE BOXES PER APPROPRIATE BASIS OF TIME CHANGE:
❑ 108.08(a) Excusable, I4on-Compensable Z 108.08{b} Excusable, Compensable
NOTE: If Compensable, attach details based on 109.05.2(a) Allowable Delay Costs.
SUPPLEMENTAL INFORMATION -
Additional information ma-y be entered by the contractor.
CHANGE ORDER ORIGINATION: ❑ INDOT / LPA N Contractor
DOCUMENTS AFFECTED:
❑ Contract Specifications (ref. doc name/no.) N/A
❑ Contract Plans (ref. doc name/no.) N/A
CHANGE ORDER AFFECTS DBE PARTICIPATION: ❑yes l no cif yes, attach details) i
i
E
Ver. 10.23.17
CHANGE ORDER REQUEST FORM
CONTRACT NO, R-37463-B
UPON WRITTEN REQUEST FROM THE ENGINEER, PROVIDE ADDITIONAL DETAIL
DATE RECEIVED REQUEST FOR SUBMITTAL DATE OF E
ADDITIONAL DETAIL. 5elect Dated ADDITIONAL DETAIL [select Date]
DETAILED DESCRIPTION / JUSTIFICATION:
(Include loCQtion(s), actions of contractor, owner, and other stakeholders, key events and related cause(s), discoveries,
discussions, meetings, and effect on the contract if no action is taken. Also Include references to key documents attached
or available to support this change order request.)
s OWNER REQUESTED INSTALLATION OF ANEW POWER FEED TO THE CONTROLLER CABINET AT 3R° AND
MAIN — JAMES H DREW CORPORATION, SUBCONTRACTOR,
PERFORMED THE WORK.
PROPOSED SOLUTION -- ADDITIONAL DETAILS: -
(include proposed scope of work, means & methods, materials, equipment, utility relocation required, subcontracted
scope and the effect on the contract schedule. Also include references to attached documents including, but not limited
to, sketches, calculations, photos, material information, and submittals and meeting minutes.)
MILESTONE HAD SUBCONTRACTOR, JAMES H DREW CORPORATION, PERFORM THE INSTALLATION OF A
NEW PONDER FEED TO THE CONTROLLER CABINET.
SIGNATURES
Contractor:
Name: (print) OTT T R
It/ I
(signature) � Date:
04/151/9
Project Engineer/Supervisor: (signature is to acknowledge receipt of the document and does not signify agreement of the change order)
Name: (print) Christopher J Miller
Digitally signed by Chris Miller
(signature) DN: cn--Chris Miller, o, ou, Date:
%..6 hi I I a 1 V41 11 %. I emai x ns.mi er@uc n y.com, Fas
Date: 201 Q 01 :Q1:06-04'00,
NOTE. The Contractor and PE/5 should retain a signed copy a t�rs Xacument for record.
4/3 D/l9
2
CHANCE ORDER REQUEST FORM
CONTRACT NO. R-37463-B
ATTACHMENT: UNIT PRIDE ITEMS DETAIL
Attach or paste a unit price item detail.
.DAMES H DREW PERFORMED THE WORK THAT WAS COMPLETED 04/08/19
WE REQUEST CHANGE ORDER FOR THE WORK:
INSTALL POWER TO CONTROLLER CABINET 3RD & MAIN
I LUMP SUM @ $11981.77 = $71951 w77
pi). 3
Ivi
ikq
Milestone Contractors, L.P.
=
Extra Work Pricina Summa
Project No:
184003
Date Requested:
TO Date Submitted: 4/12/2019
1NDOT R-37463-B BIKElPED ENHANCE
Description of Work:
JAMES H DREW - INSTALL. A NEW POWER FEED TO THE CONTROLLER CABINET AT 3RD & MAIN
Reason for Extra Work:
1NDOT REQUESTED
Has Work Already Been Completed? YES When: 29-Oct-18 THROUGH 8-Apr-19
MCLP Project No.
184003 Cost Activity Code: 184003
item:
Quantity. 1 Chits LS
Labor:
Cost =
$0.00 Markup X
20% S - Total
$ -
Equipment:
Cost =
$0.00 Markup %
12% S - Total
$ -
Materials:
Cost =
$0.00 Markup %
12% 5 - Total
$ -
SubcoRtract.
Cost =
$ 1,769.38 Markup %
10% S 176.94
Markup %
7% S - Total
$ 1,946.32
Trucking:
Cost =
$ - Markup / _
12% S -
$ -
$ 1,769.38 S 176.94 5 1.946.32
Insurance & Bond Cost = $ 4.87 Markup,% 12% S 0.58 Total 5 5.45
Total 5 1,951.77
Unit Price 1 LS $ 1,951.77
Extra Days Requested 0.0
184003 R-37463-B inst Power to Cont Cabinet Page 1
ICI FORCE ACCOUNT/EXTRA WORK
JAMES H. DREW CORPORATION
Submitted By
DREW JOB NO. 518569
PROJECT NO.
DATE October- 29, 2018
CONTRACT R-37463
Description
Change Order Cost
Install 2 fiberglass handholes. Not responsible for pulling wire. Conduit to be installed per Each
contract. Quantity (2)
$ 884.89
LARaR 10CP_04 (a.) WP:F= { FNnimr..-
�ELECTRICIAN-
�0�0�000���
!COMBINATION LABORER
FICA
7.65% X LINE (1)
FRINGES
ELECTRICIANS
0. HRS X 22.49 =
LABORERS
0 HRS X 15.16 =
OPERATORS
8 HRS X 18.41 =
TEAMSTERS
a HRS X 15.74
0 HRS X - _
WORKMEN'S COMPENSATION
BODILY INJURY INSURANCE
PROPERTY DAMAGE INSURANCE
STATE UNEMPLOYMENT
FEDERAL UMPLOYMENT
TRAVEL ALLOWANCE OR SUBSISTENCE (NOTE #3)
TOTAL LINES 1, 2,314,5,617,8,&9
20% X LINE (10)
GRAND TOTAL LABOR LINES (10) + (11)
I U I AL LAbUK
TOTAL FRINGES
2.84% X LINE (1)
4.50% X LINE (1)
0.85% X LINE (1)
8.92% X LINE (1)
0.90% X LINE (1)
526.08 (1)
40.25 (2)
273.20 (3)
14.94
(4)
23.67
(5)
4.47
(6)
46.93
(7)
4.73
(8)
(9)
934.27
(10)
186.85
( 1 1)
$ 1,121.13
(12)
INSURANCE, TAXES 109.04 (b) 0
INSURANCE (13) PAGE
TAXES (14)
TOTAL LINES (13) + (14)
10%XLINE (15)
GRAND TOTAL FOR INSURANCE, TAXES: LINE (15) + (16)
MATERIALS 109.04. (c)
MATERIALS WEEK ENDING See Page 4 of 4
(ATTACH COPIES OF INVOICES)
TOTAL MATERIALS
12% X LINE (18)
GRAND TOTAL FOR MATERIALS: LINE (18) + (19)
EQUIPMENT 109.04 (d)
400.00 (18)
48�.00� (19)
448.00 (20)
CONTRACTOR OWNED
S
M
T
w
T
F
S
TOTAL
RATE
TOTAL
1
DIGGER DERRICK TRUCK
Q
87.56
'
2
BUCKET TRUCK
0-
51.05
-
3
SERVICE TRUCK -1 TON
8
8
22.35
178.80
TRENCHER,PLOW,HOE
4
COMBO
Q
28.96
-
TRUCK CRANE (13 TON)
5
W/DIGGER
0
123.95
AIR COMPRESSOR W TOOLS-
s
185 HP
o
13.Ss
-
7
TRAILER 10 TON
0
4.24
-
8
POLE TRAILER - 8 TON
0
3•91
'
9
BACKHOE 580 EXTEND -A -HOE
0139.25
'
10
DUMP TRUCK
0
28.99
-
17
CONCRETE SAW, 65 HP
0
31.07
'
12
LOOP TRUCK
0
22.35
-
13
BORING MACHINE
0
89.74
-
14
LDOP SEALANT HOT MELTER
0
30.69
-
TOTAL CONTRACTOR OWNED EQUIPMENT
178.80
(21)
RENTED EQUIPMENT (ATTACH DAILY COPIES OF INVOICES)
-
(22)
FUEL, LUBRICANTS AND TRANSPORTATION COSTS
(23)
TOTAL LINES (21) + (22) + (23)
178.80
(24)
12% X LINE (24)
21.46
(25)
GRAND TOTAL EQUIPMENT LINES (24) + (25)
200.26
(25)
0
Equipment Rental 109.04 (d) PAGE 3 OF 4
Equipment Rental Week Ending
Item
Description
Qty
Unit
Rate
Extension
2
_
3
_
4
_
5
_
6
-
Subcontracts 109.04 (d) Rental Total -
Item
Subcontractor
Amount
1
2
3
4
5
6
7
TOTAL SUBCONTRACT WEEK ENDING - (27)
TOTAL SUBCONTRACT TO DATE - (28)
10% X LINE (28) $3,000 OR LESS - (29)
7% X LINE (28) OVER $3,000 FALSE (30)
GRAND TOTAL SUBCONTRACT LINES (28) + (29) + (30) - (31)
TOTAL LINES (12) (17) (20) (26) & (31) $ 1,769.38 (32)
% OF BOND RATE BASED UPON LINE (32) - (33)
10% X LINE (33) - (34}
TOTAL EXTRA WORK LINE (32) + (33) + (34) 1,769.38 (35)
0
MATERIALS 109.04 (c) PAGE 4 OF 4
Materials
Item
description
Qty
Unit
Unit Price
Extension
1
FlbeMlass Hand Hale
2
EACH
200.00
400.00
2
3
-
4
-
5
6
-
7
-
8
-
9
`
10
-
12
-
13
14
r
16
-
17
`
18
19
-
20
-
MATERIAL TOTAL
400.00