HomeMy Public PortalAbout2021.03.01 LHTACT2 Quarterly Progress Report Local Highway Technical Todd Smith
Chairman
Assistance Council
3330 Grace Street Robert(BJ)Berlin
Boise, Idaho 83703 Vice Chairman
Phone 208.344.0565 Neal Gier
Fax 208.344.0789 116
Secretary rrreasurer
Jeff R.Miles. P.E.
www.lhtac.org �10 Administrator
Since 1994
February 19, 2021 RECEIVED
MAR 01 2021
City of McCall
Attention: Robert Giles
216 E. Park St.
McCall, ID 83638
RE: LHTAC Quarterly Progress Report
Dear Mayor Giles:
The Local Highway Technical Assistance Council (LHTAC) provides an important linkage between Local Highway
Jurisdictions (LHJs) and the Idaho Transportation Department in the utilization of Federal-aid highway funds available to
the LHJs in Idaho. This letter includes the status listing of current and upcoming LHTAC projects for District 3.
LHTAC is committed to helping sponsors through the Federal-aid process and developing a successful project. We hope
you find this information informative. If you have any questions or need any additional information please contact our
staff at 1-800-259-6841 or 208-344-0565.
Sincerely,
Jeff R. Miles, P.E.
Administrator
Local Highway Technical Assistance Council
Council Members
Association of Idaho Cities Idaho Association of Highway Districts Idaho Association of Counties Ex-Officio Members
Mayor Mac Pooler Commissioner Neal Gier Commissioner Phil Lampert Kelley Packer,Executive Director
City of Kellogg Buhl Highway District Benewah County Association of Idaho Cities
Mayor Robert(Bl)Berlin Commissioner Terry Werner Commissioner Mark Rekow Nick Veldhouse,Executive Director
City of Roberts Post Falls Highway District Gem County Idaho Association of Highway Districts
Mayor Bruce Hossfeld Commissioner Gilbert Hofineister Commissioner Todd Smith Seth Grigg,Executive Director
City of Paul Power County Highway District Madison County Idaho Association of Counties
JA
1
Pro'ects in Desi _n/DevelopMgnt_(Up a.ted,Quarterly�
Middleton & Ustick Roundabout, Sponsor: City of Caldwell Key # 13487
Description: This project will improve a four-way stop at the Middleton Road and Ustick Road Intersection by building a
roundabout to help traffic flow and congestion.
Status: This project is in Final Design.
Project Manager: Wayne Herbel
Construction Year: 2025
S. Johns Street Improvements, Sponsor: City of Emmett Key # 13493/22948
Description: This project is located in the City of Emmett on S. Johns Avenue between 4th Street and 12th Street and will
consist of reconstruction of S. Johns Avenue of the roadway asphalt, base materials, sidewalk, curb/gutter, and storm
water improvements. The project includes construction of mini-roundabouts at the intersections of S. Johns Ave. with 4th
Street and S. Johns Avenue and 12th Street.
Status: The Plans, Specifications, & Estimate package has been submitted by the Consultant. The project is ready to be
advertised when funding is available. Construction is scheduled for FY2021.
Project Manager: Wayne Herbel
Construction Year: 2021
Old Hwy 30/Plymouth St Bridge Replacement, Sponsor: Canyon HD Key # 13494
Description: This project will construct a new bridge at a new location. The existing bridge will be left in place to serve
pedestrians and bicyclists and provide connectivity for the City of Caldwell's Greenbelt pathway. The project includes two
canal crossings and approximately 2200 feet of new approach roadway construction.
Status: This project is currently developing Preliminary Design Plans and working on the Environmental Document.
Project Manager: Wayne Herbel
Construction Year: 2023
N 10th Ave ITS & Overlay, Sponsor: City of Caldwell Key # 13905
Description: This project will overlay a one-half mile section of 10th Avenue in Downtown Caldwell from the Railroad
Overpass to 1-84 to replace surface in poor condition. Install intelligent transportation system (ITS) components to connect
signals and bring pedestrian facilities to current standards.
Status: This project is currently in Preliminary Design. The consultant is working on the Environmental document.
Project Manager: Wayne Herbel
Construction Year: 2026
Peckham Road Rehabilitation, Sponsor: Golden Gate HD Key # 13964
Description: The project intends to improve 3.75 miles of Peckham Road between US-95 and Notus Rd. It includes curb,
gutter and sidewalk in select locations within the city limits of Wilder and Greenleaf.
Status: The Final Design Review for this project is complete. The Consultant is working on revisions to prepare the Plans
Specifications & Estimates submittal. ROW acquisition is complete. This project is being coordinated with KN 2210,
Peckham Rd Intersections, a Freight project, for efficiency.
Project Manager: Wayne Herbel
Construction Year: 2022
Desert Canyon Trail BikePed, Sponsor: City of Mountain Home Key # 18827
Description: This project will construct sidewalks, bicycle lockers, shelters, benches, drinking fountains, lighting, and
information boards on the Desert Canyon Trail in Mountain Home.
Status: The Project is waiting on an updated Plan, Specifications and Estimate (PS&E) submittal to be re-advertised
during FY2021.
Project Manager: Kevin Kuther
Construction Year: 2019
2 �
Cove Rd Bridge, Washington Co, Sponsor: Washington County Key # 19129
Description: This project is for work to replace the 3-span steel truss bridge on Cove Road over the Weiser River with a
2-span steel girder bridge, and raise the approach grades.
Status: This project is currently developing Preliminary Design Plans and working on the Environmental Document.
Awaiting Memorandum of Agreement for the bridge mitigation. Currently work is being done to complete the
Environmental Document.
Project Manager: Scott Wood
Construction Year: 2025
Old Hwy 30; Goodson to Oasis, Sponsor: Canyon HD Key # 19951
Description: The project will rehabilitate approximately 3.4 miles of Old Highway 30, a major rural collector serving
northern Canyon County, as well as southern Payette and Gem Counties. This is the final phase of rehabilitating Old
Highway 30 from the vicinity of Caldwell to Payette County.
Status: The project is currently waiting on Final Permits and Plans. Specification. and Estimate (PS&E) submittal to
obligate funds.
Project Manager: Dan Coonce
Construction Year: 2026
Sand Hollow Rd; Oasis to BI Canyon, Sponsor: Payette County Key # 20019
Description: This is phase 2 of the improvements on Sand Hollow Road. This phase is 4.7 miles (from Black Canyon
Road to Oasis Road). The project includes rehabilitating asphalt pavement (pavement repair and overlay) and upgrading
guardrail at existing structures.
Status: The Final Plans, Specifications, & Estimate package has been received and waiting for construction funding.
Project Manager: Muhammad Zubery
Construction Year: 2026
Ola Hwy; Powerline Rd to 2nd Fork Rd, Sponsor: Gem County Key # 20100
Description: The Ola Highway Improvement project is located near the unincorporated Community of Ola in Gem County
and is anticipated to overlay two miles of existing pavement and pave three miles of existing gravel road to keep paved
roads good and also to pave a road which exceeds the ADT for a gravel type surface.
Status: Concept report and materials phase reports have been approved. Preliminary design review completed.
Environmental document preparation continued.
Project Manager: Muhammad Zubery
Construction Year: 2026
Mission Street; Southern City Limits to Deinhard Lane, Sponsor: City of McCall Key # 20146
Description: The Mission Street Rehabilitation project is located in the City of McCall in Valley County and is anticipated
to include the removal of the existing asphalt surface, widening of the road section, verifying the structural integrity of the
base and sub-base, new asphalt pavement, striping, utility relocations and the installation of storm water conveyance and
treatment systems to improve the condition of the roadway. It is also anticipated to include the design of a multi-use
pathway adjacent to the roadway.
Status: The project is in Preliminary Design. The consultant is preparing the Environmental document.
Project Manager: Wayne Herbel
Construction Year: 2026
Old Hwy 30; Old Oregon Trail Rd To E 54th S St, Sponsor: Mountain Home HD Key # 20182
Description: The Old HWY 30; Old Oregon Trail Road to E 54th Street project will pulverize the existing surface to
construct a 1 foot CRABS layer and a new asphalt overlay. Additionally, guardrail along the southbound lane, will be
replaced to improve safety for all roadway users near the intersection with Old HWY 30.
Status: The project is currently waiting to obligate funds
Project Manager: Dan Coonce
Construction Year: 2024
31
Eastside Drive Bridge, Sponsor: Valley County Key # 20230
Description: This project will reconstruct the deteriorated bridge and extend the length to push the abutments beyond the
channel limits in order to minimize potential for future scouring. The bridge length would extend to approximately 120',
meaning that the new abutments would extend 16' beyond the exiting abutments.
Status: Preliminary design, hydraulic design, and environmental evaluation are underway. The geotechnical foundation
report has been approved.
Project Manager: Scott Wood
Construction Year: 2025
E Lake Fk Rd; E Lake Fk Cr Br To Sh55, Sponsor: Valley County Key # 20242
Description: This is a rehabilitation project of 0.55 mile long on East Lake Fork Road between Lake Fork Creek Bridge
and intersection with SH 55. This project is expected to widen the roadway and lessen the vertical grade near the SH-55
intersection to bring it into compliance with current standards. Additional improvements will include replacing deteriorated
culverts at an irrigation canal crossing, acquiring right-of-way, and mitigating impacts to wetlands adjacent to the roadway.
Status: This project is in the Idaho Transportation Investment Program and currently scheduled under Preliminary
Development. It is waiting for design funding currently which is programmed for FY2021.
Project Manager: Wayne Herbel
Construction Year: 2026
Bike/Ped Br Over Boise River, Sponsor: City of Eagle Key # 20841
Description: This project will design and construct a bicycle and pedestrian bridge over the north channel of the Boise
River adjacent to the SH-55 (Eagle Rd.) Bridge. The bicycle and pedestrian bridge will provide a critical link between the
Boise River Greenbelt, planned pathways, and a rapidly growing residential and commercial core area in the City of
Eagle.
Status: The project is in process of Final Design and environmental documentation.
Project Manager: Amanda LaMott
Construction Year: 2023
Simco Rd Rehabilitation, Sponsor: Mountain Home HD Key # 21981
Description: This project will rehabilitate a 5 mile stretch of Simco Road. This is a rural asphalt surface and a major
collector in Elmore Co.
Status: Initial survey and geotechnical investigation have been completed. Concept report and materials reports
completed.
Project Manager: Muhammad Zubery
Construction Year: 2026
Greenhurst Rd; Sunnnybrook to Canyon St, Sponsor: City of Nampa Key # 21999
Description: This project will provide safety improvements on Greenhurst Rd. from Sunnybrook Rd. to Canyon St. in the
City of Nampa. The project will install a traffic control signal with pedestrian crossing facilities, a pedestrian-activated
flashing beacon crossing light, street lighting, and a raised median to reduce or eliminate fatal and serious injury accidents
for roadway users.
Status: This project is currently advertised and construction is anticipated summer 2021.
Project Manager: Amanda LaMott
Construction Year: 2021
Midway Rd; Karcher to Caldwell Blvd, Sponsor: Canyon HD Key # 22016
Description: This project will Rehabilitate pavement and construct shared-use shoulders on Midway Road between SH-
55(Karcher Road) and 1-84B(Caldwell Boulevard) in Canyon County.
Status: The Concept/Charter has been approved and awaiting additional funds to issue the next phase of contract.
Project Manager: Dan Coonce
Construction Year: 2026
1
4 � •
Cherry Ln; Franklin Blvd to 11th Ave N, Sponsor: City of Nampa Key # 22017
Description: This project will rebuild Cherry Lane from 11th Ave North to Franklin Boulevard.
Status: The consultant selection process has been initiated.
Project Manager: Dan Coonce
Construction Year: 2026
Montana Ave; Ped Impry & Widening, Sponsor: City of Caldwell Key # 22018
Description: This project will construct sidewalk from Syringa Middle School to Spruce Street on the West Side of
Montana Avenue in the City of Caldwell. The project includes pedestrian crossing and rectangular rapid flashing beacon
crossing at the Alder Street and Spruce Street intersections across Montana Avenue.
Status: The consultant selection process has been initiated.
Project Manager: Amanda LaMott
Construction Year: 2026
Peckham Rd Intersections, Sponsor: Golden Gate HD Key # 22101
Description: This project will reconstruct three intersection on Peckham Road at Travis Road, Allendale Road Van Slyke
Road. Each interseciton is substandard for truck turning movements. The reconstruction will provide large turning radii to
eliminate truck off-tracking and reduce edge breakup. The intersection improvements will also allow trucks to maintain
their own travel lane while making turns.
Status: The Consultant is preparing the environmental document.
Project Manager: Wayne Herbel
Construction Year: 2022
Franklin Blvd & Karcher Rd Int, Sponsor: City of Nampa Key # 22102
Description: This project will construct a dual lane offset roundabout at Franklin Blvd. and Karcher Rd. in the City of
Nampa. The project includes right-of-way, curb and gutter, sidewalk, lighting, pedestrian ramps and lane widening.
Status: The project is currently working on the Concept Report.
Project Manager: Dan Coonce
Construction Year: 2022
Int 3rd Ave N & W Industrial Rd, Sponsor: City of Nampa Key # 22103
Description: This project will install a new signalized intersection approximately one quarter mile south of the existing
Franklin Blvd. and Industrial Rd. intersection in the City of Nampa.
Status: The project is currently working on the Concept Report.
Project Manager: Dan Coonce
Construction Year: 2022
Int Holly St & NW Nazarene U Rdway, Sponsor: City of Nampa Key # 22132
Description: This project will reconfigure the four-lane Holly St. roadway section(Rossevelt Ave. to Colorado Ave.) to a
three-lane section and add bicycle lanes to improve vehicle, bicycle and pedestrian transportation safety issues along the
Holly St. corridor adjacent to Northwest Nazarene University in the City of Nampa.
Status: The project is in the consultant selection process.
Project Manager: Dan Coonce
Construction Year: 2026
Ditto Cr & Reservoir Rd, Sponsor: Mountain Home HD Key # 22405
Description: This project will be improving sections of the rural roadways by redesigning the alignments horizontal and
vertical curves to current geometric standards and will add a paved surface to the roadway improving skid resistance.
Status: The project is in process of Final Design and Environmental Documentation.
Project Manager: Brian Wright
Construction Year: 2022
r
5 � = �
Recreational Roads Signing, Sponsor: Valley County Key # 22406
Description: The scope of the Recreational Roads Signing & Delineation Safety Improvements project, located in Valley
County, will be accomplished by providing extra signage to help drivers safely navigate and increase driver awareness of
corners at various locations along recreational roads within Valley County.
Status: Funds to start Project Development will be obligated in the upcoming year. The State and Local Agreement for
this Group Safety Project is being prepared.
Project Manager: Brian Wright
Construction Year: 2021
S. 4th Ave, Indian Creek Bridge, Sponsor: City of Caldwell Key # 22593
Description: This project will replace the S. 4th Avenue bridge (ITD Bridge Key 27590) over Indian Creek in Caldwell.
This bridge replacement is part of a Completive Highway Bridge Program grant and is bundled with eight bridges in
southern Idaho. The new bridge will a single span and constructed with prestressed voided slabs.
Status: Preliminary design and environmental evaluation are underway.
Project Manager: Scott Wood
Construction Year: 2021
North Fork Boulder Creek Bridge, Sponsor: Owyhee County Key # 22594
Description: This project will replace the bridge over the North Fork Boulder Creek on Flint Creek Road (ITD Bridge Key
28270) in Owyhee County. This bridge replacement is part of a Completive Highway Bridge Program grant and is bundled
with eight bridges in southern Idaho. The new bridge will be a single span prefabricated steel girder bridge with GRS-IBS
abutments.
Status: Preliminary design and environmental evaluation are underway.
Project Manager: Scott Wood
Construction Year: 2021
Homedale Rd Curve Improvement, Sponsor: Canyon HD Key # 22878
Description: This project will improve safety for roadway users by widening a bridge, widening shoulders, installing white
thermoplastic rumble strips and flatten side slopes. This will remove obstructions to errant vehicles, increase the recovery
area on pavement, provides drivers visual guidance with an alert of lane departure and improves recovery area with a
reduction in overturning potential.
Status: The project is in the consultant selection process.
Project Manager: Dan Coonce
Construction Year: 2024
Pine-Featherville Rd Rehab, Sponsor: Mountain Home HD Key # 22889
Description: This project will rehabilitate Pine-Featherville Road by using a RABS (Recycled Asphalt Base Stabilization)
or CRAB (Cement Recycled Asphalt Base) process in conjunction with a new layer of plant mix asphalt.
Status: This project is in the Idaho Transportation Investment Program (ITIP)and is currently waiting for Project
Development funds in FY2022.
Project Manager: Dan Coonce
Construction Year: 2026
FY22 Stoddard Pathway, Sponsor: City of Nampa Key # 22944
Description: The Stoddard pathway(Sherman Avenue to 2nd Street South) project is an extension of the pathway adding
approximately 0.3 miles to the paved trail.
Status: In the process of getting the State and Local Agreement signed by the City of Nampa.
Project Manager: Amanda LaMott
Construction Year: 2022
r
6 �
1st St Pedestrian Safety, Sponsor: City of McCall Key # 22950
Description: The 1st Street Pedestrian Safety Project will construct 1Oft. wide sidewalk, curb and gutter along the east
and west sides of 1 st Street within the City of McCall's downtown core between E Lake Street SH55 south to Park Street.
Status: This project is in the Idaho Transportation Investment Program (ITIP) and is currently waiting for Project
Development funds in FY2022.
Project Manager: Amanda LaMott
Construction Year: 2023
Main St Sidewalk & Beacon, Sponsor: City of Cascade Key # 22953
Description: This project will construct a 10' sidewalk downtown on SH55, Pine Street to Lake Cascade Parkway.
Status: This project is in the Idaho Transportation Investment Program (ITIP) and is currently waiting for Project
Development funds in FY2022.
Project Manager: Dan Coonce
Construction Year: 2023
rojects Und ..onstruction/Beginning Soon (Updated Quarterly)
S Cemetery Rd; SH 44 to Willow CR, Sponsor: City of Middleton Key # 12048
Description: This project will construct a new 0.284 mile roadway segment south of SH-44 and a bridge over Willow Creek
in Middleton.
Status: This project is currently in construction and about 5% complete. The anticipated completion date is in June, 2021.
Project Manager: Garrick Nelson
Construction Year: 2021
W 9th St: Pioneer-W Indianhead Rd, Sponsor: City of Weiser Key # 12049
Description: This project will develop plans and specifications for the intersection alignment, pavement maintenance or
pavement rehabilitation services. It will replace a functionally obsolete one-lane bridge. The project may include minor
widening and right-of-way acquisition.
Status: The project is in construction and about 10% complete. The anticipated completion date is in May 2021.
Project Manager: Megan Kautz
Construction Year: 2019
Indian Cr Path Ext; Taffy to Peppermint, Sponsor: City of Nampa Key # 20141
Description: This project will construct approximately 633 feet of 8-foot-wide, multi-use, asphalt trail for Indian Creek
Pathway. The project will also provide for safety and ADA improvements to the crosswalk where Indian Creek Pathway
crosses South Kings Road, including Rapid Flashing Beacons (RFB), street lighting, ADA pedestrian ramps,
sidewalk/stormwater system repair, thermoplastic striping and signage.
Status: This project has been awarded and construction is anticipated to be complete fall 2021.
Project Manager: Amanda LaMott
Construction Year: 2019
Int N Middleton Rd & Cornell St, Sponsor: City of Middleton Key # 20430
Description: The N Middleton Road &Cornell Street Roundabout project is located in the City of Middleton in Canyon
County and will improve this intersection with the conversion of the intersection to a mini-roundabout to reduce/eliminate
serious injury crashes and fatalities.
Status: This project has been awarded and construction is anticipated to begin in June 2021.
Project Manager: Kevin Kuther
Construction Year: 2021
Intersection Lone Star and Middleton Road Improvement, Sponsor: City of Nampa Key # 20613
Description: The Lone Star Road & Middleton Road Intersection Improvement project is located in the City of Nampa in
Canyon County will improve commuter and pedestrian/bike safety and will improve traffic flow with the installation of a traffic
signal and sidewalk to reduce/eliminate serious injury crashes and fatalities.
Status: The project is currently in construction and about 15% complete. The anticipated completion date is Summer 2021.
Project Manager: Amanda LaMott
Construction Year: 2020
Stoddard Path Ext PH 1, Sponsor: City of Nampa Key # 22050
Description: The Stoddard City Pathway (Iowa to Amity) project is an extension of the existing Stoddard Pathway located
in Nampa, Canyon County. The current Stoddard Pathway is approximately 2-miles and connects neighborhoods to parks
and schools in southeast Nampa. This extension would add approximately '/2- mile to the paved trail starting at Iowa Avenue
and ending at Amity Avenue.
Status: This project has been awarded and construction is anticipated to begin in February 2021 with a Summer 2021
completion.
Project Manager: Amanda LaMott
Construction Year: 2020
Stoddard Path Ext, PH 2, Sponsor: City of Nampa Key # 22070
Description: The purpose of this project is to extend the Stoddard Pathway from Amity Avenue to Sherman Avenue. The
Stoddard City Pathway (Amity to Sherman) extension will provide a safe route to Sherman Elementary, which is one of
Nampa's highest needs school. Students and pathway users will be able to utilize an existing crosswalk with a Rapid
Flashing Beacon at the Amity Avenue crossing. The project will also tie into the proposed Stoddard City Pathway (Iowa to
Amity), creating approximately 2 and '/a miles of continuous trail.
Status: This project has been awarded and construction is anticipated to begin in February 2021 with a Summer 2021
completion.
Project Manager: Amanda LaMott
Construction Year: 2020
Grimes City Pathway, Sponsor: City of Nampa Key # 22076
Description: This project is on the Grimes Pathway between Birch Ln. and Karcher Rd and between Franklin Rd. and 11th
Ave. It is located in Nampa. Canyon County. The southern section of the project begins on Karcher Rd. and extends
northeast between McDonagh Park and the railroad. The northern section of the project begins by connecting to the existing
Grimes Pathway in Sunset Oaks Park and extends north to Birch Ln
Status: Construction is expected to be completed by Fall 2021.
Project Manager: Amanda LaMott
Construction Year: 2020