HomeMy Public PortalAboutHosmer_Safe_Routes_to_School_ProjectTOWN OF WATERTOWN
DEPARTMENT OF PUBLIC WORKS (P) 617-972-6420
124 ORCHARD STREET (F) 617-972-6402
WATERTOWN MA 02472
Gerald S. Mee Jr.
Superintendent
March 28, 2019
HOSMER SAFE ROUTES TO SCHOOL PROJECT
CURBING, SIDEWALK, AND DRIVEWAY AND INSTALLATION
BOYLSTON STREET, FROM FAIRFIELD ST. TO CHAUNCEY ST. INCLUDING
INTERSECTIONS
CHAUNCEY STREET
J. Tropeano, Inc. is scheduled to remobilize to complete the Hosmer Safe Routes to School project
on Monday, April 1, 2019 WEATHER PERMITTING. Typical work hours will be 7 AM to 4 PM. Work
will include:
• Repair of winter damage —damaged curb stones, sidewalk panels, etc.
• Installation of a catch basin on Chauncey Street near Hancock Street.
• Final loam and seeding, installation of landscaping, and private property repairs.
• Raising castings and final (top) course paving.
• Line painting.
• You will be notified by the Contractor 24 hours prior to any work that affects access to your
driveway. Driveways may remain closed up to three days to permit the concrete to cure. Please
have your car out of your driveway and work area by 7:00 AM on the date of the pour.
Pedestrians may use the newly poured sidewalks within 24-hours of the pour.
• The Watertown Police will be informed of the construction and its effects, including the need for
extended on -street parking due to driveway repairs.
Do to the nature of the work, residents should expect limited road and sidewalk closures, detours and
parking restrictions for this phase of the work. We thank you for your cooperation in this important
step of the reconstruction project.
Gerald S. Mee, Jr. Superintendent
K:ISTREET LETTER - RESIDENTSIFY191032819 Hosmer Work Recommence Notice. doc