Loading...
HomeMy Public PortalAboutChange Order No. 1 to Contract No. 50-2... Improvement for Training FacilityRFD Change Order #1 Smarrelli General Contractors Contract #50-2019 Document #1 Dated 5-22-2019 Due to soft sub grade on site of driveway addition excavation and #1 crushed concrete fill will be required. This need has been confirmed by the cities engineering department. le � J Additional cost up to: $ 15,000.00 RFD Change order #1 in an amount not to exceed: Signed Dealer Representative President Richmond Board of Works o rd of ks Member 0 Board 0 Works Member $151000.00 Date Date S-,36-19 Date 5, �p C Date SMARRELLI GENERAL CONTRACTOR, INC. 136S2 ND RICHMOND, IN 47374 Tel: 765-962-1378 Fax:765-962-3034 May 22, 2019 City of Richmond Fire training center 1740 South 81" street Richmond, IN 47374 Chief Purcell Request for Change order ##1 RE: Due to soft Sub grade on site for new driveway around concrete pad: Move existing stone previously installed Supply and install up to 200 tons of #1 sized crushed concrete for a new base Re -install 12inches of salvaged #2 crushed concrete Amount of #1 fill to be determined by truck loads, hours to install and billed actual cost plus 10% Total of Change order up to.ra.a...owa. Kong snmonae...=anKnow onMEOxman a $15YO00.00 Submitted By: Steve Shute, General Manager Date: I I '7 q � /