Loading...
HomeMy Public PortalAboutFinancial Report - Measure AA Oversight- FY19Me a s u r e A A B o n d O v e r s i g h t C o m m i t t e e Measure AA Bond Annual Accountability Report ————————————————————————————————————————————————————————— JULY 1, 2018 – JUNE 30, 2019 Ana María Ruiz, General Manager Stefan Jaskulak, Chief Financial Officer iMeasure AA Bond Annual Accountability Report FY2018-19 Table of Contents INTRODUCTION———————————————————————————————————————————————————————— Letter from the General Manager ii———————————————————————————————————————————————————————— Letter from the Chief Financial Officer iv ———————————————————————————————————————————————————————— Mission Statement v———————————————————————————————————————————————————————— Measure AA Portfolio Map vi———————————————————————————————————————————————————————— REPORT———————————————————————————————————————————————————————— Executive Summary 1—————————————————————————————————————————————————————— Portfolio Allocation to Expenditure Roll Up 2—————————————————————————————————————————————————————— Portfolio Expenditures to Allocations 2—————————————————————————————————————————————————————— Land Acquisition MAA Expenditures 4———————————————————————————————————————————————————————— Priority Portfolio Actions by Region (from MAA Expenditure Plan) 7 ———————————————————————————————————————————————————————— Portfolio Expenditures (Numerically by Portfolio Number) 14———————————————————————————————————————————————————————— Financial Report by Project 76———————————————————————————————————————————————————————— ATTACHMENTS———————————————————————————————————————————————————————— Exhibit A: Expenditure Plan 84———————————————————————————————————————————————————————— Exhibit B: Tax Rate Statement 91———————————————————————————————————————————————————————— Measure AA Bond Program: Schedule of Program Expenditures 92———————————————————————————————————————————————————————— PHOTO CREDITS Top: Picchetti Ranch Open Space Preserve by Scott Johnson Lower Left: Bear Creek Redwoods Open Space Preserve by Alisha Laborico Lower Middle: Russian Ridge Open Space Preserve by David Henry Lower Right: Ravenswood Open Space Preserve by Midpen Staff ii Measure AA Bond Annual Accountability Report FY2018-19 Message from the General Manager to the Bond Oversight Committee June 2019 marks five years since local voters voiced their support for protecting, restoring and connecting with open space by passing the Measure AA general obligation bond. Over this timespan, the Midpeninsula Regional Open Space District has invested more than $58 million in fulfilling the community’s vision for the future of open space in our region. Highlights of our five-year accomplishments across the top 25 Measure AA priorities include: ———————————————————————————————————————————————————————— Preserving an additional 1,947 acres of public open space.———————————————————————————————————————————————————————— Reintroducing conservation grazing to 315 acres to control invasive weeds, reduce fuels, maintain open grasslands, and support local sustainable agriculture.———————————————————————————————————————————————————————— Opening the Mount Umunhum summit and award-winning Mt. Umunhum Trail at Sierra Azul Open Space Preserve.———————————————————————————————————————————————————————— Opening Lower La Honda Creek Open Space Preserve with a new parking area and 6 miles of trails.———————————————————————————————————————————————————————— Opening Mindego Hill with 360-degree panoramic views at Russian Ridge Open Space Preserve.———————————————————————————————————————————————————————— Nearing construction of a 0.6-mile trail gap to complete 80 miles of continuous Bay Trail at Ravenswood Open Space Preserve. ———————————————————————————————————————————————————————— This report details the progress to date across our balanced mission. Achievements for fiscal year 2018-19 (July 1, 2018-June 30, 2019) include:———————————————————————————————————————————————————————— Opening the first phase of public access at Bear Creek Redwoods Open Space Preserve and continuing invasive species removal.———————————————————————————————————————————————————————— Protecting an additional 190 acres of redwood forest in the Upper San Gregorio Creek watershed.———————————————————————————————————————————————————————— Adding nearly 2 acres to El Sereno Open Space Preserve to enhance trail connections.———————————————————————————————————————————————————————— Completing bayfront habitat restoration through partnerships at Ravenswood Open Space Preserve.———————————————————————————————————————————————————————— Developing a plan to evaluate forest restoration and management priorities for watershed protection in La Honda Creek Open Space Preserve.———————————————————————————————————————————————————————— Restoring natural flow to areas of Hendrys Creek in Sierra Azul Open Space Preserve.———————————————————————————————————————————————————————— Completing the Oljon Trail and restoring an old steep trail alignment to natural habitat at El Corte de Madera Creek Open Space Preserve.———————————————————————————————————————————————————————— Completing the second phase of restorative ecology plantings at the Mt. Um summit.———————————————————————————————————————————————————————— Completing the Purisima Uplands property transfer to facilitate a future Purisima-to-the-Sea regional trail corridor.———————————————————————————————————————————————————————— Advancing plans for the Highway 17 wildlife and trail crossings.———————————————————————————————————————————————————————— Building two new pedestrian bridges along the Stevens Creek Nature Trail at Monte Bello Open Space Preserve.———————————————————————————————————————————————————————— Forming a new Public Access Working Group for the La Honda Creek Parking and Trailhead Access Feasibility Study and completing rare plant survey and wetlands identification for loop trail planning.———————————————————————————————————————————————————————— Continuing to support the Saratoga-to-the-Sea regional trail connection in partnership with the City of Saratoga.———————————————————————————————————————————————————————— These projects would not be possible without community support to provide the funding necessary to protect these natural resources, restore damaged habitat and watersheds, and connect the public access to these treasured landscapes. We are eager to share this progress and thank the Bond Oversight Committee for your service on behalf of the public in verifying these MAA expenditures to create the transparency necessary for continued confidence in our work. Sincerely, Ana María Ruiz General Manager iiiMeasure AA Bond Annual Accountability Report FY2018-19 Rancho San Antonio Open Space Preserve by Zhao Han iv Measure AA Bond Annual Accountability Report FY2018-19 Bond Oversight Committee: Midpen is pleased to present our fourth Measure AA Bond Annual Accountability Report. MAA, approved by voters in 2014, is a $300 million bond measure to accelerate land acquisition, environmental restoration and public access within the District. We present this report to you to fulfill two key tenets of this legislation— transparency and accountability—by highlighting MAA project progress and providing an overview of bond expenditures for FY2018-19. As committee members, your role is defined and authorized by Midpen board policy, adopted on August 12, 2015, which states: ———————————————————————————————————————————————————————— The Committee has the following three responsibilities for each of the years the Measure AA general obligation tax is collected, or revenues expended: —————————————————————————————————————————————————————— Review Plan expenditures on an annual basis to verify conformity with the Expenditure Plan —————————————————————————————————————————————————————— Review the District’s Annual Audit and Annual Accountability report and present the Committee’s findings to the Board at a public meeting —————————————————————————————————————————————————————— Review any proposed amendments to the Expenditure Plan —————————————————————————————————————————————————————— The Committee Chair shall report the Committee’s findings at a public meeting of the Board of Directors. The Committee shall not have authority to recommend, advise, or direct any such matters that may fall under its responsibility to review. The Committee is not advisory to the Board of Directors and has no power to determine how General Fund monies are spent. The Board of Directors retains its authority to make such decisions and determinations. ———————————————————————————————————————————————————————— As of the end of this reporting period, Midpen has spent a life-to-date total of $58.4 million in MAA bond funds. Midpen spent a total of $10.2 million on MAA projects in FY2018-19, with $48.2 million spent in previous reporting periods. Through leveraging $3.3 million in grants and partnership funding, along with an additional $2.7 million in interest income from the bond proceeds, available MAA bond funding has increased to $306 million total. MAA projects are grouped into 25 portfolios. Projects are completed or underway in 20 of the 25 portfolios, with progress in the current reporting year spanning 18 portfolios. Additional efforts in support of the MAA portfolios are also noted in Portfolio Expenditures. Looking ahead, Midpen continues to invest in projects across the 25 MAA portfolios. The adopted Budget and Action Plan for fiscal year 2019-20 includes projects in 15 MAA portfolios. We thank you for your time and service to our community, including the inspection of this accountability report, which supports the health of the environment we all share. Sincerely, Stefan Jaskulak Chief Financial Officer Message from the Chief Financial Officer to the Bond Oversight Committee Bear Creek Redwoods Open Space Preserve by Alisha Laborico MISSION The mission of the Midpeninsula Regional Open Space District is to acquire and preserve a regional greenbelt of open space land in perpetuity, protect and restore the natural environment, and provide opportunities for ecologically sensitive public enjoyment and education. COASTSIDE MISSION To acquire and preserve in perpetuity open space land and agricultural land of regional significance, protect and restore the natural environment, preserve rural character, encourage viable agricultural use of land resources, and provide opportunities for ecologically sensitive public enjoyment and education. vMeasure AA Bond Annual Accountability Report FY2018-19 vi Measure AA Bond Annual Accountability Report FY2018-19 Midpeninsula Regional Open Space District Measure AA Portfolio Map MAA01 Open Miramontes Ridge MAA02 New Bayfront Trails MAA03 Purisima-to-the-Sea Trail MAA04 Walking, Hiking and Biking Trails at El Corte de Madera Creek MAA05 Upper La Honda Creek Preserve MAA06 New Trails at Windy Hill MAA07 Driscoll Ranch Area at La Honda Creek MAA08 Upper San Gregorio Creek Watershed MAA09 New Trails at Russian Ridge MAA10 Alpine Road at Coal Creek MAA11 Welcome Center at Rancho San Antonio MAA12 Complete Middle Stevens Creek Trail MAA13 Expand Grazing at Cloverdale Coastal Ranch MAA14 New Trails throughout the Redwoods MAA15 Redwood Forest Protection MAA16 New Access Facilities at Long Ridge MAA17 Upper Stevens Creek Trail MAA18 Saratoga to Sea Trail MAA19 El Sereno Trails to Dogs and Complete Trail MAA20 Safe Wildlife Corridors Across Highway 17 MAA21 Bear Creek Redwoods MAA22 Cathedral Oaks at Sierra Azul MAA23 Mount Umunhum at Sierra Azul MAA24 Rancho de Guadalupe at Sierra Azul MAA25 Open Loma Prieta Area at Sierra Azul 1Measure AA Bond Annual Accountability Report FY2018-19 Executive Summary We are pleased to present Midpen’s fourth Measure AA Bond Annual Accountability Report. This report reflects MAA expenditures from July 1, 2018 to June 30, 2019. The structure of this document is guided by MAA ballot language, specifically Priority Portfolio Actions by Region, beginning on page 7. The MAA expenditure plan with 25 priority actions and project portfolios were the culmination of the vision planning effort that began in 2002. The public portion of this visioning process spanned 18 months and defines Midpen’s strategic direction for the next 40 years. In total, the vision plan yielded a list of 54 priority actions. The top 25 priority actions were subsequently incorporated into a ballot initiative. In 2014, voters approved Measure AA, a $300 million general obligation bond, designed to fund these top 25 priority actions as described in the MAA expenditure plan. This MAA accountability report is arranged in parallel with that expenditure plan to facilitate review. Projects are grouped into 25 key project portfolios organized by geographic area within District boundaries. No changes in portfolio allocations are proposed for this reporting period. In the future, should a shift in portfolio allocations be needed, the MAA Bond Oversight Committee will be advised. Bond Oversight Committee Connection with Budget and Action Plan In keeping with its role of reviewing retrospective expenditures, this committee is not charged with reviewing the budget or other prospective information, unless it is provided as part of an explanation of a proposed portfolio allocation adjustment. There is, of course, a synergy between the budgeted and actual expenditures, and the following information is provided as context for, and insight into, Midpen’s management of MAA spending. Each year Midpen embarks upon a priority-setting and budgeting process with the board, allowing for at least a six-month planning process. The Budget and Action Plan is approved prior to the start of the fiscal year. Within the budget, there is a Measure AA Projects Budget Overview, which provides a prospective view into the next year’s planned spending. Bond Issuance, Size and Look-Back Period In June 2014, voters approved MAA, a $300 million general obligation bond fund to protect natural open space lands, open preserves or areas of preserves to public access, construct public access improvements, such as new trails and staging areas, and restore and enhance open space land, including forests, streams, watersheds and coastal ranch areas. In August 2015, Midpen issued its first tranche of $45 million in general obligation bonds to cover three years of planned project expenses, as well as the legally permitted look-back period of 60 days prior to the board’s certification of election results. In February 2018, Midpen issued its second tranche of $50 million in general obligation bonds to cover project expenses planned for approximately the next three years. 2 Measure AA Bond Annual Accountability Report FY2018-19 Portfolio Allocations and Expenditures The rollup below shows how much of the total MAA expenditure plan allocation has been used on a life-to-date basis. The following chart shows the portfolio allocations approved in the expenditure plan and the life-to-date expenditures in each portfolio through June 30, 2019. For details, please reference the financial report on page 76, which contains actual expenditure numbers and remaining allocations. Portfolio Expenditures to Allocations (in millions) MAA01 MAA02 MAA03 MAA04 MAA05 MAA06 MAA07 MAA08 MAA09 MAA10 MAA11 MAA12 MAA13 MAA14 MAA15 MAA16 MAA17 MAA18 MAA19 MAA20 MAA21 MAA22 MAA23 MAA24 MAA25 $0.0 $2.5 $5.0 $7.5 $10.0 $12.5 $15.0 $17.5 $20.0 $22.5 $25.0 $27.5 $30.0 Total Life-to-Date Through 6/30/19 Expenditure Plan Remaining Total Life -To-Date Through 6/30/19 19.48% Expenditure Plan Remaining 80.52% Portfolio Allocation to Expenditure Roll Up MAA15 Portfolio Allocation is $50.73M 3Measure AA Bond Annual Accountability Report FY2018-19 Spending Trends As of June 30, 2019, $58.4 million has been expended from MAA Funds. The primary spending for the period July 1, 2018-June 30, 2019 was in engineering and construction associated with opening the western part of Bear Creek Redwoods Preserve (MAA21) to the public. These activities included completing a new parking lot, installing a new vault-toilet restroom, completing an accessible pathway around Upper Lake, installing a new bridge, and opening 6 miles of new and improved trails. Another focus area was completing the remaining site improvements at the Cooley Landing Park next to Ravenswood Preserve (MAA02), in partnership with the City of East Palo Alto, which include new motion- activated roadway lighting, a free-standing restroom, an outdoor classroom area, a path around the education center to complete a loop trail, secondary unpaved trails, and a new entry sign. Also in this reporting period, we demolished dilapidated structures in the Twin Creeks area of Sierra Azul Preserve (MAA23) to restore riparian habitat and protect water quality, constructed a new section of the Oljon Trail in El Corte de Madera Creek Preserve (MAA04), and prepared construction documents for the Ravenswood Bay Trail project. Midpen actively seeks land acquisition opportunities for conservation and preservation. We added 240 acres to Purisima Creek Redwoods Preserve (MAA03), 190 acres to La Honda Creek Preserve (MAA05) with the purchase of the Woodruff Redwoods property, and 1.87 acres to El Sereno Preserve (MAA19), including a portion of the Acquinos Trail. In addition to direct spending on MAA projects, Midpen has prioritized key initiatives in support of MAA portfolios, including land acquisition negotiations, usage surveys, operational infrastructure improvements, environmental assessments, geotechnical studies and habitat restorations. Although the Bond Oversight Committee review is primarily focused on actual MAA expenditures, additional accomplishments not funded by MAA but that support these projects have been included to help provide a sense of the work required to move them forward, which sometimes involves partnership collaborations. These accomplishments are described in detail in the portfolio expenditure summary starting on page 14. Midpen’s annual audited financial statements can be found at openspace.org/financials. Bear Creek Redwoods Open Space Preserve by Mike Kahn/Midpen 4 Measure AA Bond Annual Accountability Report FY2018-19 Of the $10.3 million expended in this reporting period, $2.2 million was related to land acquisition and related expenses, which represents 21.6% of all spending for the period. The tables below contain a breakdown of land acquisition costs by portfolio for the current fiscal year and life-to-date. Portfolios with Land Acquisition Expenses Cost Project* Type of Activity MAA02 $108,273 SFPUC Easement at Ravenswood Trail Easement property right MAA03 $546,476 Riggs Property Purchase and Site Cleanup/ Remediation, Chamberlain/Lundell Trust (Lobitos Creek), Giusti Property Rights Transfer Includes lot line adjustment, Guisti Uplands, and Lobitos Creek land conservation purchase MAA05 $1,756,093 Toepfer and Ashworth Property Purchases Land conservation purchases MAA07 $9,008,773 Apple Orchard and Event Center property and Cunha Property Purchases Land conservation purchases MAA08 $2,153,910 Woodruff Redwoods Property Purchase Land conservation purchase MAA15 $3,018,550 POST/Alpine Ranch Easement, Conley Property Purchase Easement property right and land conservation purchases MAA17 $754,552 Lysons Property Purchase Property Expense equals Purchase Price minus grant income of $740,000 MAA19 $479,527 Gupta/Kahn Property Purchase, Dunham- Bohlman Easement, Haight-Perry Property Purchase Easement property right and land conservation purchases MAA22 $540,587 Freudenberg Land Purchase, Hendrys Creek Land conservation purchase, land conservation easement to Santa Clara Valley Water District who funded full amount of $1,500,000 for Hendrys Creek parcel MAA23 $3,314,084 Meyer Property Purchase, Twin Creeks Land Purchase Land conservation purchases MAA24 $1,591,996 Barth, Petersen, Navid/Gagher, Kahn Land conservation purchases MAA25 $410,150 Burton Property Purchase Land conservation purchase Total Land Acquisition MAA Expenditures $23,682,971 * Pre-acquisition project expenditures were transferred from MAA funding to the general fund for MAA01 Zion Property and MAA24 Morales Property. Acquisition of these properties are not expected to materialize soon. Land Acquisition MAA Expenditures (May 11, 2014 - June 30, 2019) Portfolios with Land Acquisition Expenses Cost Project Type of Activity MAA03 $11,558 Giusti Property Rights Transfer Property rights transfer MAA08 $2,153,910 Woodruff Redwoods Property Purchase Land conservation purchase MAA19 $52,977 Haight-Perry Property Purchase Land conservation purchase FY2018-19 Total $2,218,445 Land Acquisition MAA Expenditures (July 1, 2018 - June 30, 2019) 5Measure AA Bond Annual Accountability Report FY2018-19 Anticipated Future Trends The Bond Oversight Committee primarily reviews retrospective expenses. The following section provides a high-level glimpse of anticipated expenditures based on the approved fiscal year Budget and Action Plan and operational workload. This is provided for contextual purposes and to demonstrate the managed progress Midpen is making toward MAA projects. Next year’s report, covering FY2019-20, will include the sixth year of MAA funding. Based on the approved FY2019-20 budget, planned life-to-date spending is estimated to exceed $65 million, or approximately 22% of the $300 million bonding capacity authorized under Measure AA. The capital program for FY2019-20 continues progress on many phased projects, with a concentrated effort on expanding public access at Bear Creeks Redwoods Preserve (MAA21) and upper La Honda Creek Preserve (MAA05), Ravenswood Preserve (MAA02) trail connections, and Mindego Ranch pond restoration at Russian Ridge Preserve (MAA09). Finally, portfolio allocations include estimated land acquisition costs. Because purchases are primarily opportunity driven, estimates are not tied to a specific time frame, as we do not know when properties and/or rights will be available for purchase. The real property department actively pursues targeted opportunities for land purchases, as well as the purchase of property rights and easements, so purchase expenses may be realized as future opportunities become available. Rancho San Antonio Open Space Preserve by Melinda Hom 6 Measure AA Bond Annual Accountability Report FY2018-19 El Corte de Madera Creek Open Space Preserve by Liv Ames 7Measure AA Bond Annual Accountability Report FY2018-19 Priority Portfolio Actions by Region (From the Measure AA Expenditure Plan) South Bay Foothills (Los Gatos, Monte Sereno, Saratoga, and Santa Cruz Mountains) PORTFOLIO 18 South Bay Foothills—Saratoga-to-the-Sea Trail and Wildlife Corridor———————————————————————————————————————————————————————— Protect wildlife corridor along Highway 9———————————————————————————————————————————————————————— Connect trail to Saratoga-to-the-Sea Trail and Skyline-to-the-Sea Trail———————————————————————————————————————————————————————— Portfolio Allocation: $1,365,000———————————————————————————————————————————————————————— PORTFOLIO 19 El Sereno—Dog Trails and Connections———————————————————————————————————————————————————————— Provide infrastructure to open trails to dogs———————————————————————————————————————————————————————— Develop connections to Skyline, Sanborn County Park and Lexington Reservoir———————————————————————————————————————————————————————— Portfolio Allocation: $2,254,000———————————————————————————————————————————————————————— PORTFOLIO 20 South Bay Foothills—Wildlife Passage and Ridge Trail Improvements———————————————————————————————————————————————————————— Establish safe corridors for mountain lions across Highway 17———————————————————————————————————————————————————————— Establish Bay Area Ridge Trail crossing———————————————————————————————————————————————————————— Portfolio Allocation: $13,966,000———————————————————————————————————————————————————————— PORTFOLIO 21 Bear Creek Redwoods—Public Recreation and Interpretive Projects———————————————————————————————————————————————————————— Open for hiking, equestrian activities———————————————————————————————————————————————————————— Provide parking areas, trails; upgrade stables———————————————————————————————————————————————————————— Restore and protect habitats for various species———————————————————————————————————————————————————————— Repair roads and trails to reduce sediment———————————————————————————————————————————————————————— Rehabilitate Alma College site———————————————————————————————————————————————————————— Portfolio Allocation: $17,478,000———————————————————————————————————————————————————————— Sierra Azul Open Space Preserve by Chris Terry PORTFOLIO 22 Sierra Azul—Cathedral Oaks Public Access and Conservation Projects———————————————————————————————————————————————————————— Develop multiuse trail and plan future trails as land is available———————————————————————————————————————————————————————— Develop parking———————————————————————————————————————————————————————— Restore plant communities and soils———————————————————————————————————————————————————————— Install trailside amenities———————————————————————————————————————————————————————— Preserve additional open space and complete wildlife corridor in upper Los Gatos Creek watershed———————————————————————————————————————————————————————— Portfolio Allocation: $6,714,000———————————————————————————————————————————————————————— PORTFOLIO 23 Sierra Azul—Mount Umunhum Public Access and Interpretive Projects———————————————————————————————————————————————————————— Open Mount Umunhum for multiuse public access to summit via road and trail———————————————————————————————————————————————————————— Open Bay Area Ridge Trail and nearby trail connections———————————————————————————————————————————————————————— Preserve additional open space and complete wildlife corridor———————————————————————————————————————————————————————— Portfolio Allocation: $27,972,000———————————————————————————————————————————————————————— PORTFOLIO 24 Sierra Azul—Rancho de Guadalupe Family Recreation———————————————————————————————————————————————————————— Open Rancho de Guadalupe to public access———————————————————————————————————————————————————————— Develop accessible multiuse trails with amenities such as parking and family recreation———————————————————————————————————————————————————————— Restore habitat for rare species———————————————————————————————————————————————————————— Protect cultural and natural resources———————————————————————————————————————————————————————— Portfolio Allocation: $10,078,000———————————————————————————————————————————————————————— PORTFOLIO 25 Sierra Azul—Loma Prieta Area Public Access, Regional Trails and Habitat Projects———————————————————————————————————————————————————————— Provide public access and recreation, including small campground———————————————————————————————————————————————————————— Develop, improve and connect regional multiuse trails to Forest of Nisene Marks State Park, protected land to east, and Mount Umunhum———————————————————————————————————————————————————————— Protect steelhead habitat, rare plants and grasslands, and restore knob cone pine stands———————————————————————————————————————————————————————— Portfolio Allocation: $7,986,000———————————————————————————————————————————————————————— 8 Measure AA Bond Annual Accountability Report FY2018-19 9Measure AA Bond Annual Accountability Report FY2018-19 Peninsula Foothills and Bay (Cupertino, Los Altos, Los Altos Hills, Sunnyvale, Mountain View, Palo Alto, East Palo Alto, Menlo Park, Atherton, Redwood City, San Carlos, Woodside, Portola Valley, and Skyline) PORTFOLIO 2 Regional—Bayfront Habitat Protection and Public Access Partnerships———————————————————————————————————————————————————————— Partner to complete gaps in Bay Trail and develop city-to-bay trails———————————————————————————————————————————————————————— Support wetland restoration and associated interpretive facilities———————————————————————————————————————————————————————— Preserve additional bayfront open space———————————————————————————————————————————————————————— Portfolio Allocation: $5,052,000———————————————————————————————————————————————————————— PORTFOLIO 4 El Corte de Madera Creek—Bike Trail and Water Quality Projects———————————————————————————————————————————————————————— Develop single-use biking/hiking trails, complete Ridge Trail gaps and develop trail system leading to parking area———————————————————————————————————————————————————————— Restore damaged trails to improve water quality———————————————————————————————————————————————————————— Preserve additional open space as available———————————————————————————————————————————————————————— Portfolio Allocation: $8,376,000———————————————————————————————————————————————————————— PORTFOLIO 5 La Honda Creek—Upper Area Recreation, Habitat Restoration, and Conservation Grazing Projects———————————————————————————————————————————————————————— Open upper half of the preserve to public; provide biking/hiking/equestrian trails, dog access and staging areas———————————————————————————————————————————————————————— Provide loop and connector trails———————————————————————————————————————————————————————— Restore habitat for rare species———————————————————————————————————————————————————————— Improve fencing, corrals and water systems to reintroduce conservation grazing———————————————————————————————————————————————————————— Portfolio Allocation: $11,733,000———————————————————————————————————————————————————————— Ravenswood Open Space Preserve by Madhur Kulkarni PORTFOLIO 6 Windy Hill—Trail Improvements, Preservation, and Hawthorns Area Historic Partnership———————————————————————————————————————————————————————— Improve trails; complete pond facilities———————————————————————————————————————————————————————— Increase multiuse trails; study possible improvements to increase dog use———————————————————————————————————————————————————————— Open Hawthorns Area; develop trails connecting to Portola Valley and Palo Alto trails———————————————————————————————————————————————————————— Partner to protect, restore and interpret historic buildings———————————————————————————————————————————————————————— Improve habitat conditions in Los Trancos Creek———————————————————————————————————————————————————————— Preserve additional scenic open space as available———————————————————————————————————————————————————————— Portfolio Allocation: $12,740,000———————————————————————————————————————————————————————— PORTFOLIO 8 La Honda Creek and Russian Ridge—Preservation of Upper San Gregorio Watershed and Ridge Trail Completion———————————————————————————————————————————————————————— Preserve Upper San Gregorio watershed; restore endangered species habitats———————————————————————————————————————————————————————— Support opportunities to provide additional water for fisheries———————————————————————————————————————————————————————— Complete Bay Area Ridge Trail multiuse connections and gaps———————————————————————————————————————————————————————— Provide additional public use facilities———————————————————————————————————————————————————————— Portfolio Allocation: $15,347,000———————————————————————————————————————————————————————— PORTFOLIO 9 Russian Ridge—Public Recreation, Grazing, and Wildlife Protection Projects———————————————————————————————————————————————————————— Open currently closed areas of preserve———————————————————————————————————————————————————————— Construct and extend trails———————————————————————————————————————————————————————— Improve fencing, corrals and water systems to reintroduce conservation grazing———————————————————————————————————————————————————————— Improve habitat for sensitive species; implement pond enhancement projects for garter snakes and red-legged frogs———————————————————————————————————————————————————————— Portfolio Allocation: $5,560,000———————————————————————————————————————————————————————— PORTFOLIO 10 Coal Creek—Reopen Alpine Road for Trail Use———————————————————————————————————————————————————————— Reopen Alpine Road as trail connection between Portola Valley and Skyline Boulevard———————————————————————————————————————————————————————— Reroute trails to reduce erosion and improve visitor experience———————————————————————————————————————————————————————— Portfolio Allocation: $8,017,000———————————————————————————————————————————————————————— PORTFOLIO 11 Rancho San Antonio—Interpretive Improvements, Refurbishing, and Transit Solutions———————————————————————————————————————————————————————— Add welcome center———————————————————————————————————————————————————————— Refurbish and add interpretive exhibits to Deer Hollow Farm———————————————————————————————————————————————————————— Support of transit improvement options such as bike trails, bike share station, bus service or additional parking———————————————————————————————————————————————————————— Portfolio Allocation: $10,811,000———————————————————————————————————————————————————————— 10 Measure AA Bond Annual Accountability Report FY2018-19 11Measure AA Bond Annual Accountability Report FY2018-19 PORTFOLIO 12 Peninsula and South Bay Cities—Partner to Complete Middle Stevens Creek Trail———————————————————————————————————————————————————————— Support work by cities to develop the middle section of the Stevens Creek Trail and enhance neighborhood connections———————————————————————————————————————————————————————— Support work by partners to complete stream corridor restoration and steelhead habitat enhancement below dam———————————————————————————————————————————————————————— Develop and install interpretive signage———————————————————————————————————————————————————————— Portfolio Allocation: $1,038,000———————————————————————————————————————————————————————— PORTFOLIO 16 Long Ridge—Trail, Conservation, and Habitat Restoration Projects (Saratoga)———————————————————————————————————————————————————————— Improve roadside parking and provide restrooms———————————————————————————————————————————————————————— Develop new trail connections to Eagle Rock and Devils Canyon———————————————————————————————————————————————————————— Repair trails for year-round, multiuse access———————————————————————————————————————————————————————— Protect watersheds for steelhead———————————————————————————————————————————————————————— Preserve additional open space as available———————————————————————————————————————————————————————— Implement pond and habitat enhancement restoration projects to benefit rare species———————————————————————————————————————————————————————— Portfolio Allocation: $5,140,000———————————————————————————————————————————————————————— PORTFOLIO 17 Regional—Complete Upper Stevens Creek Trail———————————————————————————————————————————————————————— Complete multiuse connection between the Bay Trail and Bay Area Ridge Trail above the reservoir through Picchetti Ranch Open Space Preserve and Lower/Upper Stevens Creek County Parks———————————————————————————————————————————————————————— Improve preserve trails and neighborhood connections———————————————————————————————————————————————————————— Preserve additional open space as available———————————————————————————————————————————————————————— Portfolio Allocation: $7,760,000———————————————————————————————————————————————————————— Russian Ridge Open Space Preserve by Charles Tu PORTFOLIO 1 Miramontes Ridge—Gateway to the Coast Public Access, Stream Restoration and Agriculture Enhancement———————————————————————————————————————————————————————— Preserve scenic open space land as available, and establish wildlife corridor———————————————————————————————————————————————————————— Restore fish and red-legged frog habitats in Madonna Creek watershed———————————————————————————————————————————————————————— Partner to enhance water availability for agriculture and fish———————————————————————————————————————————————————————— Develop trail loop system, including Ridge Trail and neighborhood access points———————————————————————————————————————————————————————— Develop staging area; repair bridges———————————————————————————————————————————————————————— Portfolio Allocation: $27,774,000———————————————————————————————————————————————————————— PORTFOLIO 3 Purisima Creek Redwoods—Purisima-to-the-Sea Trail, Watershed Protection and Conservation Grazing———————————————————————————————————————————————————————— Complete and open multiuse Purisima-to-the-Sea Trail connection between Ridge Trail and Coastal Trail, and new parking areas———————————————————————————————————————————————————————— Preserve additional open space as available———————————————————————————————————————————————————————— Remove fish barriers and restore Lobitos Creek———————————————————————————————————————————————————————— Restore ponds for endangered species———————————————————————————————————————————————————————— Portfolio Allocation: $7,608,000———————————————————————————————————————————————————————— PORTFOLIO 7 La Honda Creek—Driscoll Ranch Public Access, Endangered Wildlife Protection and Conservation Grazing———————————————————————————————————————————————————————— Open Driscoll Ranch area; provide biking/hiking/equestrian trails, limited dog access, parking areas and interpretive displays———————————————————————————————————————————————————————— Develop loop and connector trails———————————————————————————————————————————————————————— Restore habitat for endangered species———————————————————————————————————————————————————————— Restore La Honda Creek; remove fish migration barriers———————————————————————————————————————————————————————— Portfolio Allocation: $14,825,000———————————————————————————————————————————————————————— 12 Measure AA Bond Annual Accountability Report FY2018-19 Coast (Half Moon Bay, San Gregorio, Pescadero, and La Honda) Purisima Creek Redwoods Open Space Preserve by Anda Corlan 13Measure AA Bond Annual Accountability Report FY2018-19 PORTFOLIO 13 Cloverdale Ranch—Wildlife Protection, Grazing and Trail Connections———————————————————————————————————————————————————————— Improve fencing, corrals and water systems to increase conservation grazing and sustain large contiguous grasslands———————————————————————————————————————————————————————— Restore habitat for endangered species———————————————————————————————————————————————————————— Provide trail connections to nearby state parks———————————————————————————————————————————————————————— Portfolio Allocation: $15,712,000———————————————————————————————————————————————————————— PORTFOLIO 14 Regional—Trail Connections and Campgrounds———————————————————————————————————————————————————————— Develop trails between Butano State Park, Pescadero County Park and Russian Ridge, and between Skyline Ridge and Portola Redwoods and Big Basin state parks———————————————————————————————————————————————————————— Partner with county and state parks to improve existing campgrounds———————————————————————————————————————————————————————— Portfolio Allocation: $3,966,000———————————————————————————————————————————————————————— PORTFOLIO 15 Regional—Redwood Protection and Salmon Fishery Conservation———————————————————————————————————————————————————————— Preserve additional open space as available———————————————————————————————————————————————————————— Protect and enhance redwood stands, mountain scenery, various habitats and steelhead———————————————————————————————————————————————————————— Portfolio Allocation: $50,728,000———————————————————————————————————————————————————————— La Honda Creek Open Space Preserve by Frances Freyburg 14 Measure AA Bond Annual Accountability Report FY2018-19 Portfolio Expenditures Numerically by Portfolio Number Russian Ridge Open Space Preserve by Brian Washburn 15Measure AA Bond Annual Accountability Report FY2018-19 Preface The Portfolio Expenditures section includes a description of each of the top 25 MAA portfolios and its allocation, which was included in the MAA ballot language, under the expenditure plan. This bond funding allocation may be shifted if needed following the board of director’s approval, however, for this reporting period, no deviation from the original expenditure plan is proposed. Portfolio expenditures listed in the description represent all project costs that have been deemed eligible for MAA reimbursement from inception through June 30, 2019. Portfolios that have no incurred expenditures are included in this report to keep continuity from year to year. Additional contextual information is included in notable accomplishments, project challenges and potential next steps, as well as the tables and charts associated with each portfolio. Although the Bond Oversight Committee review is primarily focused on actual MAA expenditures, additional accomplishments not funded by MAA but that support these projects have been included to help provide a sense of the work required to move them forward, which sometimes involves partnership collaborations. The tables and charts restate information gleaned from Midpen’s accounting system and provide another graphical way to view the expenditures. Finally, where available, we have included photographs of the preserves in which the projects occur. Portfolio Progress Indicators The following indicators show the progress to date on each element of the portfolio description:———————————————————————————————————————————————————————— Not started, or little progress to report———————————————————————————————————————————————————————— Started and approximately 25% complete———————————————————————————————————————————————————————— Approximately 50% complete———————————————————————————————————————————————————————— Approximately 75% complete———————————————————————————————————————————————————————— Complete———————————————————————————————————————————————————————— Portfolio 1 Miramontes Ridge Gateway to the Coast Public Access, Stream Restoration and Agriculture Enhancement DESCRIPTION———————————————————————————————————————————————————————— Preserve scenic open space land as available, and establish wildlife corridor ———————————————————————————————————————————————————————— Restore fish and red-legged frog habitats in Madonna Creek watershed ———————————————————————————————————————————————————————— Partner to enhance water availability for agriculture and fish ———————————————————————————————————————————————————————— Develop trail loop system, including Ridge Trail and neighborhood access points ———————————————————————————————————————————————————————— Develop staging area; repair bridges ———————————————————————————————————————————————————————— Portfolio Allocation: $27,774,000 Portfolio Expenditures Through 6/30/2019: $0 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS In Support of MAA01 Fiscal Year 2018-19———————————————————————————————————————————————————————— Completed botanical study and hydrological study of pond area.———————————————————————————————————————————————————————— Began hazardous materials testing of a former ranch dump/debris site.———————————————————————————————————————————————————————— Worked with the City of Half Moon Bay and the Peninsula Open Space Trust to develop a nonbinding letter of intent to memorialize the agreement to collaborate and partner on future public trail access.———————————————————————————————————————————————————————— Continued to work with San Mateo County to resolve zoning and Coastal Plan inconsistencies to facilitate land acquisition.———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Evaluated road/trail access and connections. ———————————————————————————————————————————————————————— Assessed regional trail link to Wavecrest and Coastal Trail with the Peninsula Open Space Trust.———————————————————————————————————————————————————————— Met with City of Half Moon Bay to discuss shared public parking, Highway 1 crossing at south end of Main Street and trail/bike path along Higgins Road. ———————————————————————————————————————————————————————— Completed California red-legged frog surveys and habitat characterization at Madonna Creek Ranch. ———————————————————————————————————————————————————————— Pursued negotiations and due diligence investigation regarding proposed transfer of 650 acres of POST’s Johnston Ranch Uplands to public ownership.———————————————————————————————————————————————————————— Participated in the development of a lot line adjustment application for seven parcels, and submitted the application to the County of San Mateo in June 2018. ———————————————————————————————————————————————————————— 16 Measure AA Bond Annual Accountability Report FY2018-19 Miramontes Ridge Open Space Preserve by Midpen Staff 17Measure AA Bond Annual Accountability Report FY2018-19 PROJECT CHALLENGES ———————————————————————————————————————————————————————— Acquisitions on the Coast require a willing seller.———————————————————————————————————————————————————————— Easy access to Johnston Ranch Uplands south of Higgins Canyon Road will require acquisition of permissive rights through City of Half Moon Bay property. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS———————————————————————————————————————————————————————— Continue pursuing a potential new property purchase.———————————————————————————————————————————————————————— Continue discussions with City of Half Moon Bay and POST.———————————————————————————————————————————————————————— Develop dump removal and site remediation plan.———————————————————————————————————————————————————————— Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $27,774,000 01-003—Zions Property Purchase*$52,915 ($52,915)$0 Grand Total $27,774,000 $52,915 ($52,915)$0 $27,774,000 0.00% * Project expenditures were transferred from MAA funding to the general fund since acquisition of this property is not expected to materialize in the near future. Portfolio 1: Miramontes Ridge—Gateway to the Coast Public Access, Stream Restoration and Agriculture Enhancement 0.00% OF FUNDS USED Total Life-to-Date Through 6/30/19 $0 Expenditure Plan Remaining $27,774,000 Portfolio 2 Regional Bayfront Habitat Protection and Public Access Partnerships DESCRIPTION———————————————————————————————————————————————————————— Partner to complete gaps in Bay Trail and develop city-to-bay trails ———————————————————————————————————————————————————————— Support wetland restoration and associated interpretive facilities ———————————————————————————————————————————————————————— Preserve additional bayfront open space ———————————————————————————————————————————————————————— Portfolio Allocation: $5,052,000 Portfolio Expenditures Through 6/30/2019: $1,386,063 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA02-001 Cooley Landing Interpretive Facilities Design and Implementation Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Funded the completion of design drawings, permitting, and construction of public access improvements at Cooley Landing Park, consistent with the Cooley Landing Vision Plan.———————————————————————————————————————————————————————— Completed third and final year of plant restoration work in partnership with Grassroots Ecology. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Provided technical assistance to City of East Palo Alto staff in final design and bidding for public access site improvements at Cooley Landing Park. ———————————————————————————————————————————————————————— Obtained board approval for $1.25M in MAA funding for remaining project elements at Cooley Landing Park. Amended partnership agreement to include MAA funding and coordinated reimbursement of eligible city expenses. ———————————————————————————————————————————————————————— MAA02-002 Ravenswood Bay Trail Design and Implementation Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed construction documents. ———————————————————————————————————————————————————————— Recorded trail easement from Caltrans.———————————————————————————————————————————————————————— Received approval of a memorandum of understanding with City of East Palo Alto from the city council addressing a) patrol and emergency response, b) site security and c) future community trail access. ———————————————————————————————————————————————————————— Received two grants: $300,000 from Facebook and $1,055,328 from the California Natural Resources Agency- Urban Greening Program. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Negotiated proposed exchange agreement and public trail easement with the City and County of San Francisco and City of East Palo Alto. ———————————————————————————————————————————————————————— Concluded negotiations with the City and County of San Francisco, which resulted in the city’s board of supervisors approving a 0.6-mile Ravenswood Bay Trail easement over San Francisco Public Utilities Commission lands. This agreement will close a gap within a segment of the SF Bay Trail that connects 80 miles of continuous trail within the 500-mile route along the shoreline of the nine Bay Area counties. ———————————————————————————————————————————————————————— 18 Measure AA Bond Annual Accountability Report FY2018-19 Cooley Landing by Midpen Staff 19Measure AA Bond Annual Accountability Report FY2018-19 ———————————————————————————————————————————————————————— Completed geotechnical investigations and developed 65% plan set for construction of the 0.6-mile Ravenswood Bay Trail connection. Submitted a joint aquatic resource permit application. ———————————————————————————————————————————————————————— PROJECT CHALLENGES MAA02-001 Cooley Landing Interpretive Facilities Design and Implementation ———————————————————————————————————————————————————————— Interagency coordination between Midpen and City of East Palo Alto. ———————————————————————————————————————————————————————— Current city project team lacks familiarity with project history; more Midpen involvement is necessary.———————————————————————————————————————————————————————— MAA02-002 Ravenswood Bay Trail Design and Implementation ———————————————————————————————————————————————————————— Requires extensive, multiple agency coordination and permits, including coordination between cities, Association of Bay Area Governments, SFPUC and other governmental and regulatory entities. ———————————————————————————————————————————————————————— Limited construction season due to sensitive species (Sept. through Jan.) may extend or delay construction. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS MAA02-001 Cooley Landing Interpretive Facilities Design and Implementation ———————————————————————————————————————————————————————— Comply with land use covenant for operations and maintenance of soil cap related to 2014 site remediation work. ———————————————————————————————————————————————————————— Formalize separate agreements/easements (Midpen, City of East Palo Alto, Regional Water Quality Control Board, Menlo Fire) to meet operations and maintenance requirements.———————————————————————————————————————————————————————— MAA02-002 Ravenswood Bay Trail Design and Implementation ———————————————————————————————————————————————————————— Secure final licenses and permits to implement project. ———————————————————————————————————————————————————————— Complete construction of new trail. ———————————————————————————————————————————————————————— Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $5,052,000 02-001—Cooley Landing Interpretive Facilities Design and Implementation $200,686 $973,076 $1,173,762 02-002—Ravenswood Bay Trail Design and Implementation $518,977 $353,932 $872,909 Subtotal $5,052,000 $719,663 $1,327,008 $2,046,671 $3,005,329 40.51% 02-002—Ravenswood Bay Trail Design and Implementation Grant Income ($229,621)($430,987)($660,608) Grand Total $5,052,000 $490,042 $896,021 $1,386,063 $3,665,937 27.44% Portfolio 2: Regional—Bayfront Habitat Protection and Public Access Partnerships 27.44% OF FUNDS USED Total Life-to-Date Through 6/30/19 $1,386,063 Expenditure Plan Remaining $3,665,937 Portfolio 3 Purisima Creek Redwoods Purisima-to-the-Sea Trail, Watershed Protection and Conservation Grazing DESCRIPTION———————————————————————————————————————————————————————— Complete and open multiuse Purisima-to-the-Sea Trail connection between Ridge Trail and Coastal Trail, and new parking areas ———————————————————————————————————————————————————————— Preserve additional open space as available ———————————————————————————————————————————————————————— Remove fish barriers and restore Lobitos Creek ———————————————————————————————————————————————————————— Restore ponds for endangered species ———————————————————————————————————————————————————————— Portfolio Allocation: $7,608,000 Portfolio Expenditures Through 6/30/2019: $1,270,676 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA03-001 Purisima Uplands Lot Line Adjustment and Property Transfer Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Received board approval to finalize lot line adjustment documents with the County of San Mateo and transfer of the 240-acre Purisima Uplands property to Midpen, which completes the assemblage of public lands for the future Purisima-to-the-Sea Trail. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Purchased the 40.2-acre Riggs property, helping to protect the Lobitos Creek watershed and spawning habitat for coho salmon and steelhead.———————————————————————————————————————————————————————— Received two redwood parcel gifts totaling 0.5 acres as additions to Purisima Creek Redwoods Preserve. ———————————————————————————————————————————————————————— Received a gift of two separate parcels totaling 0.34 acres within the Redwood Estates paper subdivision as an addition to Purisima Creek Redwoods Preserve for the purposes of watershed, open space and redwood forest preservation. ———————————————————————————————————————————————————————— MAA03-002 Purisima Uplands Site Cleanup and Soil Remediation Assessment Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed phase I environmental site assessment for a remnant structure on the property (hunting cabin).———————————————————————————————————————————————————————— Prepared right of entry for Midpen use of farm roads for site cleanup and restoration of oil facilities, and hunting cabin assessment.———————————————————————————————————————————————————————— 20 Measure AA Bond Annual Accountability Report FY2018-19 Purisima Creek Redwoods Open Space Preserve by Vivian Lou Prior Years———————————————————————————————————————————————————————— Completed Purisima Uplands lead and asbestos abatement for the cabin to inform future demolition work.———————————————————————————————————————————————————————— Completed corral demolition, water system installation and fence installation for Bluebrush Ranch at Purisima Creek Redwoods Preserve. ———————————————————————————————————————————————————————— Completed phase II oil tank and facilities assessment, including site cleanup and restoration cost estimates to address site safety issues as part of the property land transfer.———————————————————————————————————————————————————————— Completed road erosion assessment for farm roads on Purisima Uplands property and private farm roads providing access to the property to inform condition of property assets (roads) and need for future repairs.———————————————————————————————————————————————————————— MAA03-003 Purisima Creek Fence Construction Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed installation of fencing along riparian areas to keep cattle out of Purisima Creek. ———————————————————————————————————————————————————————— MAA03-004 Harkins Bridge Replacement Prior Years———————————————————————————————————————————————————————— Completed the Harkins Bridge installation project. Project secures long-term vehicle and pedestrian access. ———————————————————————————————————————————————————————— MAA03-005 Purisima Uplands Parking Area and Trail Connections Prior Years———————————————————————————————————————————————————————— Purchased a 45-acre riparian conservation and public access easement over private property along Lobitos Creek for protection of significant scenic, open space, riparian and natural wildlife habitat values. The easement also contains provisions for a possible future public trail through the area. ———————————————————————————————————————————————————————— In Support of MAA03 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed design and construction of double vault restroom to replace existing single vault. Obtained County of San Mateo building permit. Project improves public facilities at Purisima Creek Redwoods Preserve. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Collaborated with the United States Geological Survey to install fog collection experimental stations at Purisima Creek Redwoods Preserve to conduct research on the viability of fog water harvesting to support agricultural uses and/or improve water availability for wildlife.———————————————————————————————————————————————————————— Completed mowing projects at October Farm to control brush encroachment and at Bluebrush Canyon to control invasive species and reduce wildfire fuels. ———————————————————————————————————————————————————————— Attended real property department site tour with POST and property owner to discuss parking and access opportunities related to the Purisima-to-the-Sea Trail.———————————————————————————————————————————————————————— 21Measure AA Bond Annual Accountability Report FY2018-19 PROJECT CHALLENGES Purisima-to-the-Sea ———————————————————————————————————————————————————————— Completing transfer agreement with owner, resolving conservation easement inconsistencies with POST, and County of San Mateo process for completing a lot line adjustment. ———————————————————————————————————————————————————————— Parking Area and Trail Connection ———————————————————————————————————————————————————————— Ongoing discussions and negotiations with property owners. ———————————————————————————————————————————————————————— Uncertainty as to where to locate a parking area for Purisima-to-the-Sea Trail. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS———————————————————————————————————————————————————————— Record conservation easement amendment with POST over the Purisima Uplands property. ———————————————————————————————————————————————————————— 22 Measure AA Bond Annual Accountability Report FY2018-19 Purisima Creek Redwoods Open Space Preserve by Stephen McNally 23Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $7,608,000 03-001—Purisima Uplands Lot Line Adjustment and Property Transfer $409,711 $11,558 $421,269 03-002—Purisima Uplands Site Cleanup and Soil Remediation Assessment $69,155 $21,704 $90,859 03-003—Purisima Creek Fence Construction $85,501 $85,501 03-004—Harkins Bridge Replacement $475,374 $41,543 $516,917 03-005—Purisima Uplands Parking Area and Trail Connections $156,130 $156,130 Grand Total $7,608,000 $1,110,370 $160,306 $1,270,676 $6,337,324 16.70% Portfolio 3: Purisima Creek Redwoods—Purisima-to-the-Sea Trail, Watershed Protection and Conservation Grazing 16.70% OF FUNDS USED Total Life-to-Date Through 6/30/19 $1,270,676 Expenditure Plan Remaining $6,337,324 Portfolio 4 El Corte de Madera Creek Bike Trail and Water Quality Projects DESCRIPTION———————————————————————————————————————————————————————— Develop single-use biking/hiking trails, complete Ridge Trail gaps and develop trail system leading to parking area ———————————————————————————————————————————————————————— Restore damaged trails to improve water quality ———————————————————————————————————————————————————————— Preserve additional open space as available ———————————————————————————————————————————————————————— Portfolio Allocation: $8,376,000 Portfolio Expenditures Through 6/30/2019: $886,868 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA04-002 El Corte de Madera Creek Watershed Protection Final Phase Prior Years———————————————————————————————————————————————————————— Completed watershed protection program. ———————————————————————————————————————————————————————— MAA04-003 El Corte de Madera Creek Watershed Protection Reassessment Prior Years———————————————————————————————————————————————————————— Trails reassessment and reprioritization of erosional sites. ———————————————————————————————————————————————————————— MAA04-004 El Corte de Madera Oljon Trail Implementation Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed Oljon Trail construction, which included bridge construction, puncheon installation, road-to-trail conversion and trail construction to open additional public recreational opportunities within El Corte de Madera Creek Preserve.———————————————————————————————————————————————————————— Completed majority of closure and restoration of upper segment of the Steam Donkey Trail.———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Removed and restored existing deteriorating roads and trails to eliminate potential sources of sedimentation within the watershed. ———————————————————————————————————————————————————————— 24 Measure AA Bond Annual Accountability Report FY2018-19 El Corte de Madera Creek Open Space Preserve by David Medeiros In Support of MAA04 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed first year of sediment and stream monitoring and data collection. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Pursued completion of Ridge Trail gaps between El Corte de Madera Creek and La Honda Creek preserves by working with partners and meeting with land owners to convey interest in possible land or trail easement purchases. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Land acquisition to complete gaps in the Bay Area Ridge Trail requires willing seller.———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Complete second year of sediment and stream monitoring and data collection. Analyze data and publish results and/or present at professional conference.———————————————————————————————————————————————————————— 25Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $8,376,000 04-002—El Corte de Madera Creek Watershed Protection Final Phase $235,934 $235,934 04-003—El Corte de Madera Creek Watershed Protection Reassessment $83,956 $83,956 04-004—El Corte de Madera Creek Oljon Trail Implementation $260,068 $306,910 $566,978 Grand Total $8,376,000 $579,958 $306,910 $886,868 $7,489,132 10.59% Portfolio 4: El Corte de Madera Creek—Bike Trail and Water Quality Projects 10.59% OF FUNDS USED Total Life-to-Date Through 6/30/19 $886,868 Expenditure Plan Remaining $7,489,132 Portfolio 5 La Honda Creek Upper Area Recreation, Habitat Restoration and Conservation Grazing Projects DESCRIPTION———————————————————————————————————————————————————————— Open upper half of the preserve to public; provide biking/hiking/equestrian trails, dog access and staging areas ———————————————————————————————————————————————————————— Provide loop and connector trails ———————————————————————————————————————————————————————— Restore habitat for rare species ———————————————————————————————————————————————————————— Improve fencing, corrals and water systems to reintroduce conservation grazing ———————————————————————————————————————————————————————— Portfolio Allocation: $11,733,000 Portfolio Expenditures Through 6/30/2019: $2,428,759 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA05-001 La Honda Creek Land Conservation Opportunities Prior Years———————————————————————————————————————————————————————— Purchased the 38.14-acre Toepfer property to facilitate a future Ridge Trail opportunity between La Honda Creek Preserve (LHC) and El Corte de Madera Creek Preserve (ECDM). ———————————————————————————————————————————————————————— Purchased the 5-acre Ashworth property to facilitate a future Ridge Trail extension opportunity between LHC and ECDM. ———————————————————————————————————————————————————————— MAA05-002 Upper La Honda Creek Grazing Infrastructure Prior Years———————————————————————————————————————————————————————— Installed riparian protection fencing to resume conservation grazing, as well as water pipe and new water troughs at Lone Madrone (formerly McDonald) Ranch. ———————————————————————————————————————————————————————— 26 Measure AA Bond Annual Accountability Report FY2018-19 La Honda Creek Open Space Preserve by Frances Freyburg MAA05-005 La Honda Creek Red Barn Parking Area and Easy-Access Trail Prior Years———————————————————————————————————————————————————————— Began feasibility studies for the Red Barn site plan, including conducting traffic counts, site evaluations of a new driveway for a new parking lot and the evaluation of historic features to ensure new improvements do not impact the historic landscape of the site.———————————————————————————————————————————————————————— Completed nine preliminary technical site investigation studies and conducted an iterative design development process resulting in two conceptual parking and staging area design alternatives. ———————————————————————————————————————————————————————— Conducted focused stakeholder outreach to support concept design development. Held Planning and Natural Resources Committee meeting and community open house to solicit public input on the Red Barn public access area concept design alternatives. ———————————————————————————————————————————————————————— Conducted preliminary trail scouting from the proposed new parking location.———————————————————————————————————————————————————————— Completed a third design alternative based on public input received in May 2017. Presented design alternative and additional technical information at three public meetings. On June 12, 2018, the board of directors directed staff to propose a process to form an advisory committee and assess alternative locations for a new parking area that meets project goals and objectives. ———————————————————————————————————————————————————————— 27Measure AA Bond Annual Accountability Report FY2018-19 La Honda Creek Open Space Preserve by Emily Tucker MAA05-008 La Honda Creek White Barn Structural Rehabilitation Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Started the design and additional assessment for the La Honda Creek White Barn project.———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Completed historic and structural assessments for the La Honda Creek White Barn. ———————————————————————————————————————————————————————— MAA05-009 La Honda Creek Redwood Cabin Stabilization and Assessment Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Started the design and assessment for the La Honda Creek Redwood Cabin project.———————————————————————————————————————————————————————— In Support of MAA05 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed preliminary site investigations of Sears Ranch Road parking lot and Driscoll Ranch parking area. ———————————————————————————————————————————————————————— Developed process for and formation of a new Public Access Working Group for the La Honda Creek Parking and Trailhead Access Feasibility Study. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Pursued trail connections to La Honda Creek Preserve’s McDonald/Dyer Ranch area by meeting several times with landowner to convey interest in possible land or trail easement purchases as part of efforts to design and implement phase II trails of the La Honda Creek Preserve Master Plan. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Acquisition of trail easement requires willing sellers to complete connections. ———————————————————————————————————————————————————————— MAA05-005 La Honda Creek Red Barn Parking Area and Easy-Access Trail ———————————————————————————————————————————————————————— Reevaluation of alternative parking sites to address community concerns regarding traffic safety and potential visual/historic impacts. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Work with the Public Access Working Group to evaluate parking location alternatives and recommend a preferred parking and trailhead location(s) for Board Committee review and full Board consideration to incorporate as part of the project description to inform the preparation of schematic designs and completion of the CEQA review. ———————————————————————————————————————————————————————— Develop phase II trail designs for planned trail connection between central La Honda Creek Preserve and existing Sears Ranch Road parking lot (lower La Honda).———————————————————————————————————————————————————————— 28 Measure AA Bond Annual Accountability Report FY2018-19 29Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $11,733,000 05-001—La Honda Creek Land Conservation Opportunities $1,756,093 $1,756,093 05-002—Upper La Honda Creek Grazing Infrastructure $209,765 $209,765 05-004—La Honda Creek Sears Ranch Interim Parking $5,074 $5,074 05-005—La Honda Creek Red Barn Parking Area and Easy- Access Trail $327,514 $327,514 05-006—La Honda Creek Sears Ranch Road Repair $98,559 $98,559 05-008—La Honda Creek White Barn Structural Rehabilitation $14,699 $13,834 $28,533 05-009—La Honda Creek Redwood Cabin Stabilization and Assessment $3,221 $3,221 Grand Total $11,733,000 $2,411,704 $17,055 $2,428,759 $9,304,242 20.70% Portfolio 5: La Honda Creek—Upper Area Recreation, Habitat Restoration and Conservation Grazing Projects 20.70% OF FUNDS USED Total Life-to-Date Through 6/30/19 $2,428,759 Expenditure Plan Remaining $9,304,242 La Honda Creek Open Space Preserve by Frances Freyburg Portfolio 6 Windy Hill Trail Improvements, Preservation and Hawthorns Area Historic Partnership DESCRIPTION———————————————————————————————————————————————————————— Improve trails; complete pond facilities ———————————————————————————————————————————————————————— Increase multiuse trails; study possible improvements to increase dog use ———————————————————————————————————————————————————————— Open Hawthorns Area; develop trails connecting to Portola Valley and Palo Alto trails ———————————————————————————————————————————————————————— Partner to protect, restore and interpret historic buildings ———————————————————————————————————————————————————————— Improve habitat conditions in Los Trancos Creek ———————————————————————————————————————————————————————— Preserve additional scenic open space as available ———————————————————————————————————————————————————————— Portfolio Allocation: $12,740,000 Portfolio Expenditures Through 6/30/2019: $26,602 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA06-001 Hawthorns Parking Lot Concept Design Prior Years ———————————————————————————————————————————————————————— Conducted initial evaluation of potential public access programming and feasibility for new parking area and trail. ———————————————————————————————————————————————————————— MAA06-002 Hawthorns Public Access Site Plan and CEQA Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Conducted a parking study to assess site feasibility for a proposed parking area and driveway location. ———————————————————————————————————————————————————————— Completed a cultural resources field survey and assessment report. ———————————————————————————————————————————————————————— Initiated development of public outreach and stakeholder engagement process for site plan project to review with board committee and Town of Portola Valley.———————————————————————————————————————————————————————— PROJECT CHALLENGES———————————————————————————————————————————————————————— Historic complex of structures, including the main residence and garage, are in significant disrepair. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS———————————————————————————————————————————————————————— To facilitate future public access improvements in support of MAA, develop a site-specific plan for new public access trails and parking area including the town’s request for a realignment of the Alpine Road Trail at the Hawthorns property, in coordination with the town and stakeholders.———————————————————————————————————————————————————————— 30 Measure AA Bond Annual Accountability Report FY2018-19 Windy Hill Open Space Preserve by R. Goldthwaite 31Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $12,740,000 06-001—Hawthorns Parking Lot Concept Design $8,490 $8,490 06-002—Hawthorns Public Access Site Plan and CEQA $18,112 $18,112 Grand Total $12,740,000 $8,490 $18,112 $26,602 $12,713,398 0.21% Portfolio 6: Windy Hill—Trail Improvements, Preservation and Hawthorns Area Historic Partnership 0.21% OF FUNDS USED Total Life-to-Date Through 6/30/19 $26,602 Expenditure Plan Remaining $12,713,398 Windy Hill Open Space Preserve by Jeffrey Schwegman Portfolio 7 La Honda Creek Driscoll Ranch Public Access, Endangered Wildlife Protection and Conservation Grazing DESCRIPTION———————————————————————————————————————————————————————— Open Driscoll Ranch Area; provide biking/hiking/equestrian trails, limited dog access, parking areas and interpretive displays ———————————————————————————————————————————————————————— Develop loop and connector trails———————————————————————————————————————————————————————— Restore habitat for endangered species ———————————————————————————————————————————————————————— Restore La Honda Creek; remove fish migration barriers ———————————————————————————————————————————————————————— Portfolio Allocation: $14,825,000 Portfolio Expenditures Through 6/30/2019: $11,930,464 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA07-001 Event Center and Apple Orchard Purchase Prior Years———————————————————————————————————————————————————————— Purchased the 307.64-acre Apple Orchard and Event Center property, as well as a 3-acre conservation easement from POST to protect and further restore redwood, coho salmon and steelhead habitat along San Gregorio Creek. ———————————————————————————————————————————————————————— Completed invasive weed control work at the Apple Orchard and Driscoll Ranch properties of La Honda Creek Preserve. ———————————————————————————————————————————————————————— MAA07-002 Fisheries Restoration, Design and Permitting Prior Years———————————————————————————————————————————————————————— Project was partially funded by CDFW Fisheries Restoration Grant Program. Completed road and trail upgrades and drainage improvements along nearly 5 miles of road to address priority erosion control sites to reduce sediment delivery to San Gregorio Creek and tributaries.———————————————————————————————————————————————————————— MAA07-003 Fisheries Enhancement, Apple Orchard Prior Years———————————————————————————————————————————————————————— Completed fisheries habitat enhancement project at the Apple Orchard parcel of lower La Honda Creek, installing 13 in-stream, large woody debris structures, in partnership with the San Mateo Resource Conservation District and CDFW Fisheries Restoration Grant Program. ———————————————————————————————————————————————————————— 32 Measure AA Bond Annual Accountability Report FY2018-19 La Honda Creek Open Space Preserve by Cindy Roessler MAA07-004 Fisheries Enhancement, Event Center Prior Years———————————————————————————————————————————————————————— Completed fisheries restoration project at the Event Center, installing large woody debris habitat within San Gregorio Creek to improve salmonid habitat. ———————————————————————————————————————————————————————— MAA07-005 Grazing and Water Systems Infrastructure Prior Years———————————————————————————————————————————————————————— Completed pond reconstruction to enhance breeding habitat for California red-legged frog and to improve the water source as a cattle stock pond. ———————————————————————————————————————————————————————— Constructed a new corral system at the previous site of the Wool Ranch house to support the conservation grazing program. ———————————————————————————————————————————————————————— Installed riparian protection fencing, water pipe and new water troughs at Driscoll Ranch to support conservation grazing.———————————————————————————————————————————————————————— MAA07-006 Cunha Land Purchase Prior Years———————————————————————————————————————————————————————— Purchased the 30-acre Cunha Trust property at the end of Sears Ranch Road to secure ownership of the private road that now serves as the driveway entrance into the Sears Ranch parking lot. ———————————————————————————————————————————————————————— MAA07-007 Demolitions, Wool Ranch House/Sears Ranch Rd Prior Years———————————————————————————————————————————————————————— Completed site clean-up and demolition of numerous dilapidated structures, including photography documentation of the structures prior to demolition, to prepare the preserve for public access. ———————————————————————————————————————————————————————— MAA07-009 Sears Ranch Parking Area Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Finalized deck replacement and installed new rails on the Harrington Creek Bridge, allowing trail users to safely cross a major creek. ———————————————————————————————————————————————————————— Prior Years ———————————————————————————————————————————————————————— Constructed the new Sears Ranch parking area, providing 22 vehicle spaces, a restroom, signage and the main trailhead to access the trails in the southern area of the preserve. ———————————————————————————————————————————————————————— Completed phase I trail and road repairs in preparation for the opening of La Honda Creek Preserve, including installation of signage and self-closing gates.———————————————————————————————————————————————————————— Completed permit-only equestrian parking area and equestrian-only trail segment connecting to the new Folger Ranch Loop Trail. ———————————————————————————————————————————————————————— MAA07-010 Sears Ranch Road Repair Prior Years———————————————————————————————————————————————————————— Completed over three miles of ranch road repairs, including culvert replacements, to the main ranch road in the lower La Honda Creek Preserve. These were critical for opening the roads to public access; maintaining safe passage for patrol, maintenance and emergency vehicle use; and providing ranch access to support the ongoing conservation grazing program.———————————————————————————————————————————————————————— 33Measure AA Bond Annual Accountability Report FY2018-19 MAA07-011 La Honda Creek Loop Trails Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Submitted County of San Mateo permits.———————————————————————————————————————————————————————— Completed trail design at 90% (contracted with Fall Creek Engineering to design and engineer the LHC Loop Trail).———————————————————————————————————————————————————————— Completed rare plant survey and wetland delineations.———————————————————————————————————————————————————————— In Support of MAA07 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed installation of new water line, storage tank and water trough.———————————————————————————————————————————————————————— Received Board direction to repair an existing housing facility and to designate the residence as Agricultural Workforce Housing.———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Completed a housing structures assessment for the Driscoll Ranch area of La Honda Creek Preserve and secured board approval to build/repair agricultural workforce housing in partnership with the County of San Mateo. ———————————————————————————————————————————————————————— Hosted groundbreaking ceremony and grand opening celebration at La Honda Creek Preserve. ———————————————————————————————————————————————————————— PROJECT CHALLENGES———————————————————————————————————————————————————————— No project challenges identified at this time. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS———————————————————————————————————————————————————————— Develop plans for and construct phase II roads and trails that will connect the new Sears Ranch Road parking area (lower La Honda) with the central La Honda area (upper La Honda). ———————————————————————————————————————————————————————— 34 Measure AA Bond Annual Accountability Report FY2018-19 La Honda Creek Open Space Preserve by Kimberly Wong 35Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $14,825,000 07-001—Event Center and Apple Orchard Purchase $6,007,601 $6,007,601 07-002—Fisheries Restoration, Design and Permitting $727,716 $727,716 07-003—Fisheries Enhancement, Apple Orchard $16,152 $16,152 07-004—Fisheries Enhancement, Event Center $50,000 $50,000 07-005—Grazing and Water Systems Infrastructure $189,422 $189,422 07-006—Cunha Land Purchase $3,080,705 $3,080,705 07-007—Demolitions, Wool Ranch House/Sears Ranch Road $357,803 $357,803 07-009—Sears Ranch Parking Areas $1,124,545 $17,937 $1,142,482 07-010—Sears Ranch Road Repair $458,484 $458,484 07-011—La Honda Creek Loop Trails $27,058 $104,012 $131,070 Subtotal $14,825,000 $12,039,486 $121,948 $12,161,434 $2,663,566 82.03% 07-002—Fisheries Restoration, Design and Permitting Grant Income ($230,970)($230,970) Grand Total $14,825,000 $11,808,516 $121,948 $11,930,464 $2,894,536 80.48% Portfolio 7: La Honda Creek—Driscoll Ranch Public Access, Endangered Wildlife Protection and Conservation Grazing 80.48% OF FUNDS USED Total Life-to-Date Through 6/30/19 $11,930,464 Expenditure Plan Remaining $2,894,536 Portfolio 8 La Honda Creek/ Russian Ridge Preservation of Upper San Gregorio Watershed and Ridge Trail Completion DESCRIPTION———————————————————————————————————————————————————————— Preserve Upper San Gregorio watershed; restore endangered species habitats ———————————————————————————————————————————————————————— Support opportunities to provide additional water for fisheries———————————————————————————————————————————————————————— Complete Bay Area Ridge Trail multiuse connections and gaps———————————————————————————————————————————————————————— Provide additional public use facilities ———————————————————————————————————————————————————————— Portfolio Allocation: $15,347,000 Portfolio Expenditures Through 6/30/2019: $2,153,910 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA08-001 Folger Property Purchase Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Purchased the 190-acre Woodruff Redwoods property as an addition to La Honda Creek Preserve.———————————————————————————————————————————————————————— PROJECT CHALLENGES———————————————————————————————————————————————————————— No project challenges identified at this time.———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS———————————————————————————————————————————————————————— Continue to pursue opportunities for Bay Area Ridge Trail connection.———————————————————————————————————————————————————————— 36 Measure AA Bond Annual Accountability Report FY2018-19 La Honda Creek Open Space Preserve by Karl Gohl 37Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $15,347,000 08-001—Folger Property Purchase $2,153,910 $2,153,910 Grand Total $15,347,000 $0 $2,153,910 $2,153,910 $13,193,090 14.03% Portfolio 8: La Honda Creek/Russian Ridge—Preservation of Upper San Gregorio Watershed and Ridge Trail Completion Russian Ridge Open Space Preserve by Matt McLean 14.03% OF FUNDS USED Total Life-to-Date Through 6/30/19 $2,153,910 Expenditure Plan Remaining $13,193,090 Portfolio 9 Russian Ridge Public Recreation, Grazing and Wildlife Protection Projects DESCRIPTION———————————————————————————————————————————————————————— Open currently closed areas of preserve———————————————————————————————————————————————————————— Construct and extend trails ———————————————————————————————————————————————————————— Improve fencing, corrals and water systems to reintroduce conservation grazing———————————————————————————————————————————————————————— Improve habitat for sensitive species; implement pond enhancement projects for garter snakes and red-legged frogs———————————————————————————————————————————————————————— Portfolio Allocation: $5,560,000 Portfolio Expenditures Through 6/30/2019: $319,467 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA09-001 Russian Ridge Grazing Infrastructure Prior Years———————————————————————————————————————————————————————— Upgraded corral and water system at Mindego Ranch, installing two 5,000-gallon water storage tanks, 11,000 feet of buried pipe, six water troughs, and solar-powered water pump for storage tanks. Selected grazing tenant to manage grazing operation.———————————————————————————————————————————————————————— Completed brush management of south pasture at Mindego Ranch. ———————————————————————————————————————————————————————— MAA09-003 Russian Ridge Mindego Pond Improvement Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Selected a design-build firm to improve the ponds to support endangered species’ habitat. Began project survey, assessment, design and permitting. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Began pre-bid work on the first design-build project to be implemented by Midpen. The project will enhance and restore habitat for the California red-legged frog and San Francisco garter snake at two ponds at Mindego Ranch. ———————————————————————————————————————————————————————— MAA09-004 Mindego Hill Trail Construction Prior Years———————————————————————————————————————————————————————— Constructed and opened an extension of Mindego Hill Trail to the top of the prominent Mindego Hill with 360-degree panoramic views. ———————————————————————————————————————————————————————— Completed remediation of the Mindego Ranch area. ———————————————————————————————————————————————————————— 38 Measure AA Bond Annual Accountability Report FY2018-19 Russian Ridge Open Space Preserve by David Henry In Support of MAA09 Prior Years———————————————————————————————————————————————————————— Completed year four of the San Francisco garter snake field study and ongoing bullfrog eradication work at Mindego Ranch in Russian Ridge Preserve. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— No project challenges identified at this time.———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Complete Mindego pond improvement projects for California red-legged frog and San Francisco garter snake.———————————————————————————————————————————————————————— 39Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $5,560,000 09-001—Russian Ridge Mindego Grazing Infrastructure $174,416 $174,416 09-003—Russian Ridge Mindego Pond Improvement $136 $77,512 $77,648 09-004—Mindego Hill Trail Construction $67,403 $67,403 Grand Total $5,560,000 $241,955 $77,512 $319,467 $5,240,533 5.75% Portfolio 9: Russian Ridge—Public Recreation, Grazing and Wildlife Protection Projects 5.75% OF FUNDS USED Total Life-to-Date Through 6/30/19 $319,467 Expenditure Plan Remaining $5,240,533 Portfolio 10 Coal Creek Reopen Alpine Road for Trail Use DESCRIPTION———————————————————————————————————————————————————————— Reopen Alpine Road as trail connection between Portola Valley and Skyline Boulevard ———————————————————————————————————————————————————————— Reroute trails to reduce erosion and improve visitor experience ———————————————————————————————————————————————————————— Portfolio Allocation: $8,017,000 Portfolio Expenditures Through 6/30/2019: $166,122 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA10-001 Alpine Road Regional Trail, Coal Creek Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Began assessment of trail conditions and developed recommendations/alternatives and cost analysis for repairs. Developed agreement with the County of San Mateo for long-term repairs. ———————————————————————————————————————————————————————— Prior Years ———————————————————————————————————————————————————————— Updated the road and trail inventory and completed preliminary conceptual design alternatives for two large failures on Alpine Road. Presented options for repairs and improvements to the board, which selected the approach of repairing failures to trail width (6-foot-wide standard). Coordinated the project with County of San Mateo Public Works. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— The County of San Mateo has determined that they are unable to lead the repair due to other higher priority repair issues stemming from the 2016-17 winter storms; Midpen is now the lead. ———————————————————————————————————————————————————————— Alpine Road Trail is owned in fee and easement by the County of San Mateo; repairs will require careful coordination and approval from the county.———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Receive and review the road design and third-party cost estimations with the County of San Mateo for concurrence. ———————————————————————————————————————————————————————— Finalize construction plans. ———————————————————————————————————————————————————————— Secure permits and complete CEQA review. ———————————————————————————————————————————————————————— Enter into negotiations with the County of San Mateo regarding funding contribution and long-term maintenance. ———————————————————————————————————————————————————————— 40 Measure AA Bond Annual Accountability Report FY2018-19 Coal Creek Open Space Preserve by David Smernoff 41Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $8,017,000 10-001—Alpine Road Regional Trail, Coal Creek $21,949 $144,173 $166,122 Grand Total $8,017,000 $21,949 $144,173 $166,122 $7,850,878 2.07% Portfolio 10: Coal Creek—Reopen Alpine Road for Trail Use 2.07% OF FUNDS USED Total Life-to-Date Through 6/30/19 $166,122 Expenditure Plan Remaining $7,850,878 Coal Creek Open Space Preserve by Asha Kulkarni Portfolio 11 Rancho San Antonio Interpretive Improvements, Refurbishing and Transit Solutions DESCRIPTION———————————————————————————————————————————————————————— Add welcome center———————————————————————————————————————————————————————— Refurbish and add interpretive exhibits to Deer Hollow Farm ———————————————————————————————————————————————————————— Support of transit improvement options such as bike trails, bike share station, bus service or additional parking———————————————————————————————————————————————————————— Portfolio Allocation: $10,811,000 Portfolio Expenditures Through 6/30/2019: $33,264 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA11-001 New Trails to Connect Quarry Trail to Black Mountain Trail Prior Years———————————————————————————————————————————————————————— Accepted two trail easements, two rights of first offer and rights of first refusal, and a conditional grant deed conveyance, to properties adjacent to Monte Bello and Rancho San Antonio preserves. ———————————————————————————————————————————————————————— MAA11-002 Rancho San Antonio, Deer Hollow Farm: White Barn Rehabilitation Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Selected consultant for the design and assessment of the Rancho San Antonio White Barn to improve building access, structural stability and public safety. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— With MAA and other funding, completed historic and structural assessments for the Deer Hollow Farm White Barn; obtained Legislative, Funding, And Public Affairs Committee confirmation of partnership agreements to fund project. ———————————————————————————————————————————————————————— In Support of MAA11 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed draft scope for parking and transportation demand analysis (Multimodal Access Study), and met with Santa Clara County Parks on project scope review and coordination. ———————————————————————————————————————————————————————— Presented the draft Multimodal Access Study scope and potential short-, medium- and long-term measures to address parking challenges at Rancho San Antonio Preserve to board committee. Received Board approval of the Multimodal Access Study scope to proceed with a Request of Proposals, and Board approval to implement the short-term measures.———————————————————————————————————————————————————————— 42 Measure AA Bond Annual Accountability Report FY2018-19 Rancho San Antonio Open Space Preserve by Joseph Ventimiglia Prior Years———————————————————————————————————————————————————————— Restored the Deer Hollow Farm White Barn milk room at Rancho San Antonio Preserve, facilitating ongoing environmental interpretation and animal husbandry at the popular farm site. ———————————————————————————————————————————————————————— Completed 69 days of vehicle occupancy counts to understand the parking use patterns at Rancho San Antonio Preserve. ———————————————————————————————————————————————————————— Initiated stakeholder agency engagement in identifying opportunities for parking and transit improvement options. ———————————————————————————————————————————————————————— Conducted a one week tabling campaign for mountain lion awareness at Rancho San Antonio Preserve.———————————————————————————————————————————————————————— Coordinated with the City of Mountain View and Friends of Deer Hollow Farm to prepare for a historic and structural assessment of the White Barn at Rancho San Antonio Preserve that was conducted during fiscal year 2017-18. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Depending on potential parking solutions, coordination, agreement and co-implementation with other agencies may be required. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— To facilitate future MAA-eligible improvements, continue to engage stakeholder agencies and community in evaluating parking and transit improvement options. ———————————————————————————————————————————————————————— Complete Rancho San Antonio Multimodal Access Study, which includes parking and transportation demand analyses and recommendations to address traffic congestion. ———————————————————————————————————————————————————————— To facilitate future MAA-eligible improvements, continue to collaborate with City of Mountain View and stakeholders on the rehabilitation of the Deer Hollow Farm White Barn. ———————————————————————————————————————————————————————— 43Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $10,811,000 11-001—New Trails to Connect Quarry Trail to Black Mountain Trail $728 $728 11-002—Rancho San Antonio, Deer Hollow Farm: White Barn Rehabilitation $29,511 $3,025 $32,536 Grand Total $10,811,000 $30,239 $3,025 $33,264 $10,777,736 0.31% Portfolio 11: Rancho San Antonio—Interpretive Improvements, Refurbishing and Transit Solutions 0.31% OF FUNDS USED Total Life-to-Date Through 6/30/19 $33,264 Expenditure Plan Remaining $10,777,736 Portfolio 12 Peninsula/South Bay Cities Partner to Complete Middle Stevens Creek Trail DESCRIPTION———————————————————————————————————————————————————————— Support work by cities to develop the middle section of the Stevens Creek Trail and enhance neighborhood connections ———————————————————————————————————————————————————————— Support work by partners to complete stream corridor restoration and Steelhead habitat enhancement below dam ———————————————————————————————————————————————————————— Develop and install interpretive signage———————————————————————————————————————————————————————— Portfolio Allocation: $1,038,000 Portfolio Expenditures Through 6/30/2019: $0 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS In Support of MAA12 Prior Years———————————————————————————————————————————————————————— Supported work by partners to complete stream corridor restoration and steelhead habitat enhancement below Stevens Creek Dam. Coordinated with partners, reviewed technical reports, held site visit to Deep Cliff site and produced letter of funding support. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— No project challenges identified at this time. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Coordinate with cities, Santa Clara County Parks, Friends of Stevens Creek Trail and other stakeholders on new signage for the Stevens Creek Trail through preserves, parkland and other jurisdictional lands.———————————————————————————————————————————————————————— 44 Measure AA Bond Annual Accountability Report FY2018-19 Los Gatos Creek Trail by Dan Debold 45Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $1,038,000 Grand Total $1,038,000 $0 $0 $0 $1,038,000 0.00% Portfolio 12: Peninsula/South Bay Cities—Partner to Complete Middle Stevens Creek Trail 0.00% OF FUNDS USED Total Life-to-Date Through 6/30/19 $0 Expenditure Plan Remaining $1,038,000 Portfolio 13 Cloverdale Ranch Wildlife Protection, Grazing and Trail Connections DESCRIPTION———————————————————————————————————————————————————————— Improve fencing, corrals and water systems to increase conservation grazing and sustain large contiguous grasslands ———————————————————————————————————————————————————————— Restore habitat for endangered species———————————————————————————————————————————————————————— Provide trail connections to nearby state parks———————————————————————————————————————————————————————— Portfolio Allocation: $15,712,000 Portfolio Expenditures Through 6/30/2019: $0 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS In Support of MAA13 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Initiated bimonthly meetings and conducted staff site tours of Cloverdale Ranch with POST. ———————————————————————————————————————————————————————— Prior Years ———————————————————————————————————————————————————————— Conducted ongoing due diligence investigation to evaluate site resources and obligations of a potential future land purchase and subsequent management of POST’s 6,500-acre Cloverdale Ranch. Worked with POST to conduct an introductory site tour for board members and key management staff to learn more about the property. Added Cloverdale Ranch to the Capital Improvement and Action Plan for FY2018-19. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— No project challenges identified at this time. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Collate past site investigations, restoration work, and ongoing ranch management operations by POST into an existing conditions report. ———————————————————————————————————————————————————————— Conduct additional field trips for staff to become familiar with site. ———————————————————————————————————————————————————————— Identify additional site investigations to be conducted.———————————————————————————————————————————————————————— 46 Measure AA Bond Annual Accountability Report FY2018-19 Cloverdale Ranch by Carol Daniels 47Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $15,712,000 Grand Total $15,712,000 $0 $0 $0 $15,712,000 0.00% Portfolio 13: Cloverdale Ranch—Wildlife Protection, Grazing and Trail Connections 0.00% OF FUNDS USED Total Life-to-Date Through 6/30/19 $0 Expenditure Plan Remaining $15,712,000 Portfolio 14 Regional Trail Connections and Campgrounds DESCRIPTION———————————————————————————————————————————————————————— Develop trails between Butano, Pescadero County Park and Russian Ridge, and between Skyline, Portola Redwoods and Big Basin State Park ———————————————————————————————————————————————————————— Partner with county and state parks to improve existing campgrounds ———————————————————————————————————————————————————————— Portfolio Allocation: $3,966,000 Portfolio Expenditures Through 6/30/2019: $0 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS In Support of MAA14 Prior Years ———————————————————————————————————————————————————————— Acquired a conservation easement from POST covering the 353-acre Alpine Ranch property to protect redwood forests, watershed and habitat values (expensed in MAA15 portfolio). Supports MAA14 for future trail connections and campgrounds to San Mateo County’s Pescadero Creek Park Complex. ———————————————————————————————————————————————————————— 48 Measure AA Bond Annual Accountability Report FY2018-19 Russian Ridge Open Space Preserve by Strether Smith 49Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $3,966,000 Grand Total $3,966,000 $0 $0 $0 $3,966,000 0.00% Portfolio 14: Regional—Trail Connections and Campgrounds 0.00% OF FUNDS USED Total Life-to-Date Through 6/30/19 $0 Expenditure Plan Remaining $3,966,000 Skyline Ridge Open Space Preserve by Charles Tu Portfolio 15 Regional Redwood Protection and Salmon Fishery Conservation DESCRIPTION———————————————————————————————————————————————————————— Preserve additional open space as available ———————————————————————————————————————————————————————— Protect and enhance redwood stands, mountain scenery, various habitats and steelhead ———————————————————————————————————————————————————————— Portfolio Allocation: $50,728,000 Portfolio Expenditures Through 6/30/2019: $3,033,050 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA15-001 Conservation Easement Upper Alpine Ranch Area Prior Years———————————————————————————————————————————————————————— Acquired a conservation easement from POST covering the 353-acre Alpine Ranch property to protect redwood forests, watershed and habitat values. ———————————————————————————————————————————————————————— MAA15-002 Conley Property Purchase Prior Years———————————————————————————————————————————————————————— Purchased the 191-acre Conley property from POST as an addition to Long Ridge Preserve to protect redwood forest and the upper Pescadero Creek watershed. ———————————————————————————————————————————————————————— MAA15-003 Long Ridge Property Addition Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Appraisal and offer made. Offer was rejected. Negotiations may continue. ———————————————————————————————————————————————————————— In Support of MAA15 and other MAA Portfolios Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Purchased 190-acre Woodruff Redwoods property as an addition to La Honda Creek Preserve (expensed in MAA08 portfolio); purchase includes 51 acres of old-growth redwood forest that support MAA15 priority actions.———————————————————————————————————————————————————————— Contracted with consulting professionals to develop the La Honda forest management plan to evaluate restoration and management priorities in the watershed.———————————————————————————————————————————————————————— Real property staff and executive staff held several meetings with SJWC executive staff concerning the potential purchase of their CPUC regulated utility lands in addition to the potential purchase of their 182-acre non-CPUC regulated property near El Sereno Preserve.———————————————————————————————————————————————————————— 50 Measure AA Bond Annual Accountability Report FY2018-19 Long Ridge Open Space Preserve by Deane Little Prior Years———————————————————————————————————————————————————————— After state legislation created the opportunity to purchase land governed by the California Public Utility Commission, pursued watershed protection opportunities at Sierra Azul and El Sereno preserves. Established initial contact with site owners, toured the property with site managers and Midpen board members, and conveyed Midpen goals for a working partnership to negotiate a mutually beneficial transaction. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Land acquisition requires willing seller. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Real property is continuing to communicate and work towards the purchase of SJWC’s utility property, but the deal is contingent on a willing seller. ———————————————————————————————————————————————————————— 51Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $50,728,000 15-001—Conservation Easement Upper Alpine Ranch Area $2,508,695 $2,508,695 15-002—Conley Property Purchase $509,855 $509,855 15-003—Long Ridge Property Addition $14,500 $14,500 Grand Total $50,728,000 $3,018,550 $14,500 $3,033,050 $47,694,950 5.98% Portfolio 15: Regional—Redwood Protection and Salmon Fishery Conservation 5.98% OF FUNDS USED Total Life-to-Date Through 6/30/19 $3,033,050 Expenditure Plan Remaining $47,694,950 Portfolio 16 Long Ridge Trail, Conservation and Habitat Restoration Projects (Saratoga) DESCRIPTION———————————————————————————————————————————————————————— Improve roadside parking and provide restrooms ———————————————————————————————————————————————————————— Develop new trail connections to Eagle Rock and Devils Canyon———————————————————————————————————————————————————————— Repair trails for year-round, multiuse access———————————————————————————————————————————————————————— Protect watersheds for steelhead———————————————————————————————————————————————————————— Preserve additional open space as available———————————————————————————————————————————————————————— Implement pond and habitat enhancement restoration projects to benefit rare species———————————————————————————————————————————————————————— Portfolio Allocation: $5,140,000 Portfolio Expenditures Through 6/30/2019: $0 ———————————————————————————————————————————————————————— MAA funds have not been expended on this portfolio through the reporting period, therefore there are no funds in this portfolio for the Bond Oversight Committee to validate at this time. This does not necessarily mean that work is not underway in this portfolio. If there is work in process, other funding sources are being utilized and either the scope is not what was contemplated as part of this MAA portfolio, or the scope is not currently eligible for MAA funding. 52 Measure AA Bond Annual Accountability Report FY2018-19 Long Ridge Open Space Preserve by Denise Lawrence 53Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $5,140,000 Grand Total $5,140,000 $0 $0 $0 $5,140,000 0.00% Portfolio 16: Long Ridge—Trail, Conservation and Habitat Restoration Projects (Saratoga) 0.00% OF FUNDS USED Total Life-to-Date Through 6/30/19 $0 Expenditure Plan Remaining $5,140,000 Long Ridge Open Space Preserve by Charles Tu Portfolio 17 Regional Complete Upper Stevens Creek Trail DESCRIPTION———————————————————————————————————————————————————————— Complete multiuse connection between the Bay Trail and Bay Area Ridge Trail above the reservoir through Picchetti Ranch Open Space Preserve and Lower/Upper Stevens Creek County parks ———————————————————————————————————————————————————————— Improve preserve trails and neighborhood connections ———————————————————————————————————————————————————————— Preserve additional open space as available———————————————————————————————————————————————————————— Portfolio Allocation: $7,760,000 Portfolio Expenditures Through 6/30/2019: $1,315,333 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA17-001 Land Conservation: Last Piece Upper Stevens Creek Prior Years———————————————————————————————————————————————————————— Purchased the 60-acre Lysons property, securing land to facilitate the Upper Stevens Creek regional trail. Leveraged partnership funds to match the MAA funds expended for this purchase. ———————————————————————————————————————————————————————— MAA17-002 Demolition & Restoration: Lobner/Lysons Fiscal Year 2018-19———————————————————————————————————————————————————————— Completed design and contractor bidding process to demolish existing structures for site restoration and future public access. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Evaluated the Lysons property for demolition and restoration. ———————————————————————————————————————————————————————— MAA17-004 Stevens Creek Nature Trail Bridges, Monte Bello Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Constructed two new pedestrian bridges on the Stevens Creek Nature Trail and removed one old bridge. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Coordination with Santa Clara County Parks to consider multiuse trail designation for Upper Stevens Creek Trail. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Prepare demolition bid package and permits for Lysons property structures demolition and site restoration. ———————————————————————————————————————————————————————— Continue to coordinate with Santa Clara County Parks regarding consideration of multiuse trail designation.———————————————————————————————————————————————————————— 54 Measure AA Bond Annual Accountability Report FY2018-19 Pichetti Ranch Open Space Preserve by Kristi Corely 55Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $7,760,000 17-001—Land Conservation: Last Piece Upper Stevens Creek $1,494,552 $1,494,552 17-002—Demolition & Restoration: Lobner/Lysons $138,060 $9,869 $147,929 17-004—Stevens Creek Nature Trail Bridges, Monte Bello $147,635 $265,218 $412,853 Subtotal $7,760,000 $1,780,247 $275,086 $2,055,333 $5,704,667 26.49% 17-002—Lysons Property Purchase Grant Income (50% of purchase price) ($740,000)($740,000) Grand Total $7,760,000 $1,040,247 $275,086 $1,315,333 $6,444,667 16.95% Portfolio 17: Regional—Complete Upper Stevens Creek Trail 16.95% OF FUNDS USED Total Life-to-Date Through 6/30/19 $1,315,333 Expenditure Plan Remaining $6,444,667 Pichetti Ranch Open Space Preserve by Curt Bianchi Portfolio 18 South Bay Foothills Saratoga-to-the-Sea Trail and Wildlife Corridor DESCRIPTION———————————————————————————————————————————————————————— Protect wildlife corridor along Highway 9 ———————————————————————————————————————————————————————— Connect trail to Saratoga-to-the-Sea Trail and Skyline-to-the-Sea Trail ———————————————————————————————————————————————————————— Portfolio Allocation: $1,365,000 Portfolio Expenditures Through 6/30/2019: $3,850 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS In Support of MAA18 Fiscal Year 2018-19———————————————————————————————————————————————————————— City of Saratoga completed engineering design and environmental review and initiated permitting for the proposed Saratoga-to-the-Sea regional trail connection within city’s easement area on San Jose Water Company lands. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Finalized partnership agreement with the City of Saratoga and obtained board approval for a funding contribution of the final design and environmental review for the Saratoga-to-the-Sea Trail. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— No project challenges identified at this time. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Provide additional partnership funding and/or technical staff support to City of Saratoga to complete the trail design plans, environmental review and permitting of the approximately 3-mile Saratoga-to-the-Sea Trail connection from Saratoga Quarry Park and Sanborn County Park. ———————————————————————————————————————————————————————— 56 Measure AA Bond Annual Accountability Report FY2018-19 Saratoga Gap Open Space Preserve by Midpen Staff 57Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $1,365,000 18-001—San Jose Water Land Purchase $3,850 $3,850 Grand Total $1,365,000 $0 $3,850 $3,850 $1,361,150 0.28% Portfolio 18: South Bay Foothills—Saratoga-to-the-Sea Trail and Wildlife Corridor Total Life-to-Date Through 6/30/19 $3,850 Expenditure Plan Remaining $1,361,150 0.28% OF FUNDS USED Portfolio 19 El Sereno Dog Trails and Connections DESCRIPTION———————————————————————————————————————————————————————— Provide infrastructure to open trails to dogs ———————————————————————————————————————————————————————— Develop connections to Skyline, Sanborn County Park and Lexington Reservoir ———————————————————————————————————————————————————————— Portfolio Allocation: $2,254,000 Portfolio Expenditures Through 6/30/2019: $480,242 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA19-001 Gupta/Khan Property Purchase Prior Years———————————————————————————————————————————————————————— Purchased a 9.37-acre fee property and a 1.97-acre floating trail easement from Gupta-Khan to improve opportunities for wildlife corridor and trail connectivity. ———————————————————————————————————————————————————————— MAA19-002 Dunham-Bohlman Easement Prior Years———————————————————————————————————————————————————————— Purchased a 0.33-acre public trail and patrol easement from a private land owner ($15,000 purchase). These purchases fill a gap in the Bay Area Ridge Trail between El Sereno Preserve and Sanborn County Park (one property acquisition remains). ———————————————————————————————————————————————————————— MAA19-003 Haight-Peery LV Land Acquisition Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Purchased the 1.87-acre Haight-Peery property, including a portion of the Aquinas Trail, as an addition to El Sereno Preserve.———————————————————————————————————————————————————————— In Support of MAA19 Prior Years———————————————————————————————————————————————————————— Completed CEQA review and a use and management plan amendment for board approval to open existing trails to dogs on-leash and added on-leash dog use to 6 miles of existing trail. ———————————————————————————————————————————————————————— To facilitate future MAA trail projects, initiated site investigations for regional trail connections between Sanborn County Park, El Sereno Preserve and a potential Highway 17 Bay Area Ridge Trail crossing. ———————————————————————————————————————————————————————— 58 Measure AA Bond Annual Accountability Report FY2018-19 El Sereno Open Space Preserve by Claire Dawkins PROJECT CHALLENGES ———————————————————————————————————————————————————————— Need to secure additional property rights to provide contiguous access through El Sereno Preserve to the adjacent Sanborn County Park. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Continue seeking property rights required for a trail connection from Highway 17 through El Sereno Preserve to Sanborn County Park. ———————————————————————————————————————————————————————— Continue analysis of regional trail connections between Sanborn County Park, El Sereno Preserve and a potential Highway 17 Bay Area Ridge Trail crossing.———————————————————————————————————————————————————————— 59Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $2,254,000 $715 $715 19-001—Gupta/Khan Property Purchase $406,553 $406,553 19-002—Dunham-Bohlman Easement $19,997 $19,997 19-003—Haight-Perry LV Land Acquisition $52,977 $52,977 Grand Total $2,254,000 $427,265 $52,977 $480,242 $1,773,759 21.31% Portfolio 19: El Sereno—Dog Trails and Connections 21.31% OF FUNDS USED Total Life-to-Date Through 6/30/19 $480,242 Expenditure Plan Remaining $1,773,759 Portfolio 20 South Bay Foothills Wildlife Passage and Ridge Trail Improvements DESCRIPTION———————————————————————————————————————————————————————— Establish safe corridors for mountain lions across Highway 17 ———————————————————————————————————————————————————————— Establish Bay Area Ridge Trail crossing ———————————————————————————————————————————————————————— Portfolio Allocation: $13,966,000 Portfolio Expenditures Through 6/30/2019: $390,203 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA20-001 Wildlife Corridor: Highway 17 Crossing and MAA20-002 Bay Area Ridge Trail: Highway 17 Crossing Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Draft project study report submitted to Caltrans and initial comments received. Held additional meetings with project partners and stakeholders (Caltrans, SJWC, CGF, NWF), as well as a second public meeting to continue to advance a proposed wildlife crossing.———————————————————————————————————————————————————————— Conducted preplanning, trail scouting and preliminary conceptual-level design and cost estimates for a proposed regional trail crossing over Highway 17. Completed a pre-permitting coordination meeting with Caltrans. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— In coordination with a consultant team, completed a draft project preliminary alternatives report for both the wildlife corridor and regional trails crossing at Highway 17 for agency review. ———————————————————————————————————————————————————————— Engaged public and stakeholders for input on proposed draft alternatives and received agency comments on draft report. ———————————————————————————————————————————————————————— Released draft recommended alternatives report for both the wildlife corridor and regional trails crossing at Highway 17 and received agency comments. ———————————————————————————————————————————————————————— Developed a cooperative agreement with Caltrans and developed a Caltrans project initiation document. ———————————————————————————————————————————————————————— Continued evaluation of the Highway 17 wildlife crossing and regional trail crossing through identification and analysis of additional crossing alternatives in response to partner, stakeholder and public comment on initial drafts.———————————————————————————————————————————————————————— Collaborated with partner agencies (Santa Clara County Parks, Valley Water, Ridge Trail, etc.) to identify best opportunities for a public access crossing at Highway 17, including trail connections. Crossing will close a major gap in the regionwide trail system and connect open space areas for multiple regional trails. ———————————————————————————————————————————————————————— 60 Measure AA Bond Annual Accountability Report FY2018-19 Russian Ridge Open Space Preserve by Midpen Staff In Support of MAA20 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed preplanning and site investigations to identify potential trail routes to connect trail crossings. Worked with consultants to develop preliminary trail design and completed draft trail connections report. Shared draft report with stakeholders (Caltrans, SJWC, Santa Clara County Parks, etc.) for review prior to public presentations. Scheduled public informational meeting on trail connections. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Conducted numerous field investigations and trail route evaluations for a potential future regional trail crossing over Highway 17 that would become part of the Bay Area Ridge Trail near the El Sereno, St. Joseph’s Hill and Bear Creek Redwoods preserves. ———————————————————————————————————————————————————————— Co-hosted with POST a free screening of “The Cat that Saved America” and panel discussion on wildlife corridors and the Highway 17 wildlife crossing attended by 325 guests on April 7, 2018. ———————————————————————————————————————————————————————— Conducted additional ground-truthing and analysis on potential trail alignments that support the potential trail crossing locations to include in a feasibility study. Identified eight trail alignments to include in the project study report for Caltrans. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Complex Caltrans process and coordination with numerous project partners and stakeholders with Midpen as the project lead despite not owning or managing any of the underlying land or immediate trail connections. ———————————————————————————————————————————————————————— Additional studies and coordination needed to identify feasible trail connections linking to a regional trail crossing at Highway 17, evaluating multiple scenarios for trail connections on either side of Highway 17. ———————————————————————————————————————————————————————— Requires negotiations with multiple property owners to secure property rights. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Complete recommended alternatives report. ———————————————————————————————————————————————————————— Complete project study report with Caltrans. ———————————————————————————————————————————————————————— Continue to secure permission to access private properties for studies and to negotiate for property rights.———————————————————————————————————————————————————————— 61Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $13,966,000 20-001—Wildlife Corridor: Highway 17 Crossing $196,519 $129,262 $325,781 20-002—Bay Area Ridge Trail: Highway 17 Crossing $317 $64,105 $64,422 Grand Total $13,966,000 $196,836 $193,367 $390,203 $13,575,798 2.79% Portfolio 20: South Bay Foothills—Wildlife Passage and Ridge Trail Improvements 2.79% OF FUNDS USED Total Life-to-Date Through 6/30/19 $390,203 Expenditure Plan Remaining $13,575,798 Portfolio 21 Bear Creek Redwoods Public Recreation and Interpretation Projects DESCRIPTION———————————————————————————————————————————————————————— Open for hiking, equestrian activities ———————————————————————————————————————————————————————— Provide parking areas, trails; upgrade stables ———————————————————————————————————————————————————————— Restore and protect habitats for various species———————————————————————————————————————————————————————— Repair roads and trails to reduce sediment———————————————————————————————————————————————————————— Rehabilitate Alma College site———————————————————————————————————————————————————————— Portfolio Allocation: $17,478,000 Portfolio Expenditures Through 6/30/2019: $7,978,762 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA21-003 Bear Creek Redwoods Water System Prior Years———————————————————————————————————————————————————————— Completed an assessment of water source options and associated cost estimates for the preserve, concluding that the most cost effective and secure option is execute an agreement with SJWC to complete the water line installation from their main line as the new source of water for the preserve and Bear Creek Stables. ———————————————————————————————————————————————————————— Established and filed pre-1914 water rights for the preserve, installed meters, and completed required annual reporting.———————————————————————————————————————————————————————— Started the design of water main extension at gate BC01 to provide water access to staff and provide initial connection to water system for stables. ———————————————————————————————————————————————————————— MAA21-004 Bear Creek Stables Site Plan Implementation Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Met with Santa Clara County planning staff and fire marshal office to discuss the type of repair and maintenance work that would be permissible under the existing legal, nonconforming use.———————————————————————————————————————————————————————— Completed a fundraising pre-feasibility assessment.———————————————————————————————————————————————————————— The board directed staff to move forward with maintenance and repairs in the near-term and the Stables site plan as a long-term solution.———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Developed the stables site plan alternatives and secured board selection of the preferred alternative for CEQA review purposes. ———————————————————————————————————————————————————————— 62 Measure AA Bond Annual Accountability Report FY2018-19 Bear Creek Redwoods Open Space Preserve by Mike Kahn/Midpen MAA21-005 Bear Creek Redwoods Public Access Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed construction of a new parking lot, bridge, retaining wall improvements, vault toilet restroom, ADA pathway, and road/trail improvements, opening 6 miles of new trail to public access.———————————————————————————————————————————————————————— Completed second (final) year of cultural resource evaluations for 19 sites within the preserve. Final report completed. Provided archaeological monitoring for parking lot and trail construction. ———————————————————————————————————————————————————————— Completed installation of two interpretive signs for the new main parking area at Upper Lake. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Completed an archaeological resources curation guidelines report.———————————————————————————————————————————————————————— Completed archaeological studies in advance of ground disturbance activities.———————————————————————————————————————————————————————— Conducted an engineering feasibility study to identify the preferred location for a Bear Creek Road trail undercrossing as an option for connecting visitors between the new parking area and the western area of the preserve.———————————————————————————————————————————————————————— Completed geologic assessment, geotechnical drilling and fault trenching. Completed regulatory/code assessment.———————————————————————————————————————————————————————— Completed cultural resource assessments. Prepared RFPQ, selected and contracted with consultant to complete a final survey/ assessment reports for 10 sites, parking lot area and Mud Lake improvements. ———————————————————————————————————————————————————————— Completed phase I public access road and trail construction, upgrades, and drainage improvement, including constructing two segments of new trail to complete the westside loop.———————————————————————————————————————————————————————— Investigated a legacy landfill at BCR to determine size and potential constituents of concern. Scoped project, prepared RFPQ, and selected consultant.———————————————————————————————————————————————————————— MAA21-006 Bear Creek Redwoods Alma College Cleanup and Stabilization Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Presented Alma College cultural landscape plan to Santa Clara County Historic Heritage Commission for a landmark alteration permit. Santa Clara County planning department issued a landmark alteration permit for the rehabilitation project.———————————————————————————————————————————————————————— Completed 90% of plans and specifications and prepared permit package for submission to the County of Santa Clara Department of Planning and Development. Completed conversion of mansion ruins to bat habitat.———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Conducted a recreation planning analysis for potential reuse of the Alma College chapel. ———————————————————————————————————————————————————————— Completed an earthquake fault rupture hazard study to determine if the Alma College chapel could be occupied. ———————————————————————————————————————————————————————— Constructed two structures to provide alternative bat roosting habitat in anticipation of demolition work at Alma College.———————————————————————————————————————————————————————— MAA21-007 Bear Creek Redwoods Preserve Plan Invasive Weed Treatment Fiscal Year 2018-19———————————————————————————————————————————————————————— Completed treatments as planned and selected contractor for final two years of project through RFP process. ———————————————————————————————————————————————————————— Completed all work under a task order with Valley Water for the implementation of grant-funded invasive species work. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Implemented the first year of a targeted invasive species treatment to restore native habitat throughout the preserve. ———————————————————————————————————————————————————————— Received a grant from Valley Water for $200,000 per year for five years with a possible five-year extension for another $1 million. ———————————————————————————————————————————————————————— 63Measure AA Bond Annual Accountability Report FY2018-19 MAA21-008 Bear Creek Redwoods Ponds Restoration and Water Rights Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed construction documents and began the permitting process to improve drainage from Mud Lake to Briggs Creek.———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Completed a pond assessment and management plan to determine the water needs for wildlife and habitat values at aquatic sites. ———————————————————————————————————————————————————————— Began the first year of the western pond turtle population study and developed a western pond turtle management plan. ———————————————————————————————————————————————————————— Completed the Mud Lake drainage improvement project plans to 60%, which allowed for pre-permitting meetings to be held with the U.S. Army Corp of Engineers, RWQCB and CDFW to determine the permit and review timeframe required before construction. The project will improve the stormwater drainage system for Mud Lake.———————————————————————————————————————————————————————— MAA21-009 Bear Creek Redwoods Webb Creek Bridge Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed the removal of an existing bridge and installation of a new bridge to provide safe public access and patrol route.———————————————————————————————————————————————————————— Prior Years ———————————————————————————————————————————————————————— Designed the Webb Creek Bridge replacement foundation. ———————————————————————————————————————————————————————— Submitted CDFW and RWQCB permits for the Webb Creek Bridge replacement. ———————————————————————————————————————————————————————— MAA21-010 Bear Creek Redwoods Landfill Characterization and Remediation Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed a landfill characterization and developed the project remedial approach.———————————————————————————————————————————————————————— In Support of MAA21 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed the Bear Creek Redwoods online story map. ———————————————————————————————————————————————————————— Celebrated completion of phase I public access improvements and progress on natural resources restoration projects with partner ribbon-cutting and tours, media outreach and open weekends public educational outreach. ———————————————————————————————————————————————————————— Hired a consultant for feasibility studies, design engineering, and permitting to implement the phase II trails.———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Received board approval of the Bear Creek Redwoods Preserve Plan and certification of the accompanying EIR. ———————————————————————————————————————————————————————— Hosted a groundbreaking for the preserve parking area project on May 1, 2018.———————————————————————————————————————————————————————— Completed construction of Alma College site fencing in April 2018 to improve site safety and security.———————————————————————————————————————————————————————— PROJECT CHALLENGES———————————————————————————————————————————————————————— MAA21-004: Stable’s legal nonconforming status raises concerns regarding use permit requirements and code upgrades that may raise costs substantially.———————————————————————————————————————————————————————— MAA21-008: Permitting agencies unexpectedly asked that Upper and Mud Lake projects be combined, requiring staff to pull two consultant teams together to complete permit applications. ———————————————————————————————————————————————————————— Land acquisition requires a willing seller. ———————————————————————————————————————————————————————— 64 Measure AA Bond Annual Accountability Report FY2018-19 POTENTIAL NEXT STEPS———————————————————————————————————————————————————————— Continue design development of allowable repairs of existing stables site within legal, nonconforming status.———————————————————————————————————————————————————————— Continue integrated pest management implementation on roads and trails, and in shaded fuel break.———————————————————————————————————————————————————————— Complete permitting and construction of pond improvement projects.———————————————————————————————————————————————————————— 65Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $17,478,000 21-001—Moody Gulch Fence & Gate Improvements $847 $847 21-002—Bear Creek Redwoods Preserve Plan ($12,954)($1,415)($14,369) 21-003—Bear Creek Redwoods Stables Water System $191,149 $794 $191,943 21-004—Bear Creek Stables Site Plan Implementation $282,075 $2,270 $284,345 21-005—Bear Creek Redwoods Public Access $1,505,935 $3,748,293 $5,254,228 21-006—Bear Creek Redwoods Alma College Cleanup and Stabilization $692,822 $332,396 $1,025,218 21-007—Bear Creek Redwoods Preserve Plan Invasive Weed Treatment $501,679 $319,050 $820,729 21-008—Bear Creek Redwoods Ponds Restoration and Water Rights $126,676 $62,201 $188,877 21-009—Bear Creek Redwoods Webb Creek Bridge $138,876 $348,616 $487,492 21-010—Bear Creek Redwoods Landfill Characterization and Remediation $36,375 $36,375 Subtotal $17,478,000 $3,427,105 $4,848,581 $8,275,686 $9,202,314 47.35% 21-007—Bear Creek Redwoods Preserve Plan Invasive Weed Treatment Grant Income ($107,042)($189,882)($296,924) Grand Total $17,478,000 $3,320,063 $4,658,699 $7,978,762 $9,499,238 45.65% Portfolio 21: Bear Creek Redwoods—Public Recreation and Interpretive Projects 45.65% OF FUNDS USED Total Life-to-Date Through 6/30/19 $7,978,762 Expenditure Plan Remaining $9,499,238 Portfolio 22 Sierra Azul Cathedral Oaks Public Access and Conservation Projects DESCRIPTION———————————————————————————————————————————————————————— Develop multiuse trail and plan future trails as land is available ———————————————————————————————————————————————————————— Develop parking———————————————————————————————————————————————————————— Restore plant communities and soils ———————————————————————————————————————————————————————— Install trailside amenities———————————————————————————————————————————————————————— Preserve additional open space and complete wildlife corridor in upper Los Gatos Creek watershed ———————————————————————————————————————————————————————— Portfolio Allocation: $6,714,000 Portfolio Expenditures Through 6/30/2019: $1,010,784 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA22-001 Hendrys Creek Property Land Restoration Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Removed culverts that impeded the creek and restored natural creek flow.———————————————————————————————————————————————————————— Completed annual monitoring and submitted annual report to Valley Water and CDFW, as required by the long-term management plan and CDFW permit conditions. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Received partnership funds to purchase the 117-acre Hendrys Creek property to protect wildlife corridors and watershed lands. No MAA funds were used on this purchase.———————————————————————————————————————————————————————— Completed fifth year of the coordinated monitoring effort to reduce mercury within the Guadalupe River watershed. ———————————————————————————————————————————————————————— Completed first phase of invasive plant removal and developed a partnership with the San Jose Conservation Corps for the Hendrys Creek watershed restoration effort. ———————————————————————————————————————————————————————— Negotiated with resource agencies, including CDFW, RWQCB and USACE to finalize permits to perform the Hendrys Creek restoration project. Rare opportunity to perform environmental restoration to benefit wildlife and water quality. ———————————————————————————————————————————————————————— 66 Measure AA Bond Annual Accountability Report FY2018-19 Sierra Azul Open Space Preserve by Tian Lin MAA22-003 Freudenberg Land Purchase Prior Years———————————————————————————————————————————————————————— Purchased the 24.41-acre Freudenberg property to protect wildlife and watershed lands. ———————————————————————————————————————————————————————— MAA22-004 Beatty Parking Area and Trail Connections Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Issued RFPs and selected consultants for site surveys, traffic, hazardous material assessments and environmental and biological services to support the implementation of the Beatty Parking Area. ———————————————————————————————————————————————————————— Initiated traffic counts and line of sight analysis, phase I environmental assessments, and completed topographic surveys. Initiated conceptual parking area design.———————————————————————————————————————————————————————— Awarded a $149,906 grant from Valley Water for the Beatty Trail connection project (grant income will be included in FY2019-20).———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Permit monitoring requires up to 10 years of tracking and reporting, which is cumulative for every project requiring a resource agency permit. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Complete Hendrys Creek land restoration and project mitigation. Continue monitoring for up to 10 years. ———————————————————————————————————————————————————————— 67Measure AA Bond Annual Accountability Report FY2018-19 Portfolio 22: Sierra Azul—Cathedral Oaks Public Access and Conservation Projects 15.05% OF FUNDS USED Total Life-to-Date Through 6/30/19 $1,010,784 Expenditure Plan Remaining $5,703,216 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $6,714,000 22-001—Hendrys Creek Property Land Restoration $168,316 $304,668 $472,984 22-003—Freudenberg Land Purchase $540,587 $540,587 22-004—Beatty Parking Area and Trail Connections $64,325 $64,325 Subtotal $6,714,000 $708,903 $368,992 $1,077,895 $5,636,105 16.05% 22-001—Hendrys Creek Property Land Restoration Grant Income ($67,111)($67,111) Grand Total $6,714,000 $641,792 $368,992 $1,010,784 $5,703,216 15.05% Portfolio 23 Sierra Azul Mount Umunhum Public Access and Interpretation Projects DESCRIPTION———————————————————————————————————————————————————————— Open Mount Umunhum for multiuse public access to summit via road and trail ———————————————————————————————————————————————————————— Open Bay Area Ridge Trail and nearby trail connections———————————————————————————————————————————————————————— Preserve additional open space and complete wildlife corridor ———————————————————————————————————————————————————————— Portfolio Allocation: $27,972,000 Portfolio Expenditures Through 6/30/2019: $21,614,442 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA23-001 Mt. Um Road and Trail Property Rights Prior Years———————————————————————————————————————————————————————— Purchased the 38.97-acre Meyer/Connolly property to protect additional open space and wildlife corridors.———————————————————————————————————————————————————————— In support of MAA improvements, purchased the 28-acre Rossetta property to secure public access rights along Mt. Umunhum Road and the Woods Trail in the Mount Umunhum area of Sierra Azul Preserve. ———————————————————————————————————————————————————————— MAA23-002 Mt. Um Trail Prior Years———————————————————————————————————————————————————————— Completed nearly 4 miles of the new Mt. Umunhum Trail to connect people to the summit. ———————————————————————————————————————————————————————— Completed major construction milestones on the Mt. Umunhum Trail, including the construction of an additional 0.5-mile trail segment, the narrowing of old, abandoned road cuts into a trail, and the installation of three new pedestrian bridges and signage. ———————————————————————————————————————————————————————— Completed final preparations for opening Mount Umunhum, installing fencing, signs, horse trough, trail construction and new bridges.———————————————————————————————————————————————————————— 68 Measure AA Bond Annual Accountability Report FY2018-19 Sierra Azul Open Space Preserve by Erin Ashford MAA23-004 Mt. Um Summit Restoration, Parking and Landing Zone Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed phase II plant restoration and sign installation. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Created a new contract with Grassroots Ecology Native Plant Nursery to grow approximately 1,900 native plants and 5 pounds of native grass and forb seed for phase I of the Mount Umunhum revegetation project. ———————————————————————————————————————————————————————— Developed a habitat restoration plan for the Mount Umunhum summit to enhance the native plant recolonization of the restored mountaintop, incorporating input from the Amah Mutsun tribal group on Native American restoration techniques. ———————————————————————————————————————————————————————— Surveyed and mapped rare plant populations and collected native plant seeds in support of the restoration planting plan. ———————————————————————————————————————————————————————— Completed the construction of the Mount Umunhum summit restoration project, including a new parking lot, summit shelters, turnaround area, ceremonial circle, ADA pathways, stairs, trail steps and other site amenities. Project opened Mount Umunhum summit area to the public in September 2017. ———————————————————————————————————————————————————————— Developed and created broad interpretive displays for the Mount Umunhum summit project, providing visitors with a substantially greater understanding of the site’s rich history.———————————————————————————————————————————————————————— Continued restoration planting at Mount Umunhum to restore native vegetation at the summit.———————————————————————————————————————————————————————— MAA23-005 Mt. Um Guadalupe Creek Overlook and Bridges Prior Years———————————————————————————————————————————————————————— Completed the design, permitting and construction for the Guadalupe Creek overlook (a featured overlook along Mount Umunhum Trail), including permitting and construction of three new trail bridges along the trail.———————————————————————————————————————————————————————— Installed the Guadalupe Creek overlook railings and mitigation planting, and removed trail debris to open the Woods Trail to the public. ———————————————————————————————————————————————————————— MAA23-006 Mt. Um Road Design/Permitting/Construction Prior Years———————————————————————————————————————————————————————— Completed the construction of the Mt. Umunhum Road improvement project, including the installation of new culverts, asphalt concrete paving, drainage structures, gabion retaining walls, guardrail, mass grading and off haul, striping and other road safety improvements. Completion of the project opened public vehicular access to the Mount Umunhum summit area. ———————————————————————————————————————————————————————— MAA23-007 Twin Creeks Land Conservation Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Completed site cleanup and demolition of structures to support land preservation and riparian habitat restoration. ———————————————————————————————————————————————————————— Prior Years———————————————————————————————————————————————————————— Purchased the 153.59-acre Twin Creeks property providing water quality protection within the Los Alamitos Creek watershed, continuity of wildlife habitat corridors and the potential for a future trail connection with Rancho Cañada del Oro Preserve. The Gordon and Betty Moore Foundation provided grant funding in the amount of $750,000 toward the purchase of $2,800,000.———————————————————————————————————————————————————————— MAA23-008 Twin Creeks Restoration Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Started a botanical survey at the Twin Creeks property. ———————————————————————————————————————————————————————— 69Measure AA Bond Annual Accountability Report FY2018-19 In Support of MAA23 Fiscal Year 2018-19 ———————————————————————————————————————————————————————— Selected a consultant to complete a radar tower assessment and develop repair alternatives with costs estimates that protect public safety and implement the Board’s Retain and Seal decision for the structure.———————————————————————————————————————————————————————— Prior Years ———————————————————————————————————————————————————————— Completed interim repairs on the radar tower to open the Mount Umunhum summit to public access.———————————————————————————————————————————————————————— Finalized and recorded the Mount Umunhum public access easement, drainage easements, fee property and patrol/maintenance easement to Mount Thayer, ensuring legal access to these areas of the preserve.———————————————————————————————————————————————————————— Continued to respond to wildlife entrapment issues at the Mount Umunhum radar tower. ———————————————————————————————————————————————————————— Submitted an application nominating Mount Umunhum as one of the 2018 Great Places in California, an award program under the American Planning Association California Chapter in March 2018. The APA Great Places jury selected Mount Umunhum as one of three Great Places in California for 2018. ———————————————————————————————————————————————————————— Stayed in communication with Mount Umunhum neighbors for the summit and road projects before, during, and after the grand opening.———————————————————————————————————————————————————————— Produced a “Stories of Mount Umunhum” audio tour app and made it available for free download on iTunes and Google Play. The app offers a virtual guided tour of the summit. ———————————————————————————————————————————————————————— Held the Mount Umunhum grand opening on September 17, 2017, with extensive media coverage.———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Mount Umunhum summit: potential ongoing wildlife entrapment at the tower. ———————————————————————————————————————————————————————— Twin Creeks: restoration of the creek and banks. ———————————————————————————————————————————————————————— Land acquisition: property rights required from potential unwilling seller. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Continue monitoring for potential entrapped wildlife. ———————————————————————————————————————————————————————— Continue native plant restoration of summit.———————————————————————————————————————————————————————— 70 Measure AA Bond Annual Accountability Report FY2018-19 71Measure AA Bond Annual Accountability Report FY2018-19 Portfolio 23: Sierra Azul—Mount Umunhum Public Access and Interpretation Projects 77.27% OF FUNDS USED Total Life-to-Date Through 6/30/19 $21,614,442 Expenditure Plan Remaining $6,357,558 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $27,972,000 23-001—Mt. Um Road and Trail Property Rights $1,271,318 $1,271,318 23-002—Mt. Um Trail $959,548 $959,548 23-004—Mt. Um Summit Restoration, Parking and Landing Zone $10,398,273 $29,853 $10,428,126 23-005—Mt. Um Guadalupe Creek Overlook and Bridges $259,311 $259,311 23-006—Mt. Um Road Design/ Permitting/Construction $6,280,251 $6,280,251 23-007—Twin Creeks Land Conservation $2,913,372 $812,554 $3,725,926 23-008—Twin Creeks Restoration $9,963 $9,963 Subtotal $27,972,000 $22,082,073 $852,369 $22,934,442 $5,037,558 81.99% 23-004—Mt. Um Summit Restoration, Parking and Landing Zone Grant Income ($570,000)($570,000) 23-007—Twin Creeks Land Conservation Grant Income ($750,000)($750,000) Grand Total $27,972,000 $20,762,073 $852,369 $21,614,442 $6,357,558 77.27% Portfolio 24 Sierra Azul Rancho de Guadalupe Family Recreation DESCRIPTION———————————————————————————————————————————————————————— Open Rancho de Guadalupe to public access ———————————————————————————————————————————————————————— Develop accessible multiuse trails with amenities such as parking and family recreation ———————————————————————————————————————————————————————— Restore habitat for rare species ———————————————————————————————————————————————————————— Protect cultural and natural resources———————————————————————————————————————————————————————— Portfolio Allocation: $10,078,000 Portfolio Expenditures Through 6/30/2019: $1,591,996 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA24-001 Barth Property Purchase Prior Years———————————————————————————————————————————————————————— Purchased 4 acres of the Barth property improving access into the preserve from Hicks Road. ———————————————————————————————————————————————————————— MAA24-002 Petersen Property Acquisition Prior Years———————————————————————————————————————————————————————— Purchased the 23.41-acre Petersen property to protect grassland habitat and water quality in the Guadalupe Creek watershed. ———————————————————————————————————————————————————————— MAA24-003 Property Exchange Navid/Bagher Prior Years———————————————————————————————————————————————————————— Negotiated a property exchange with Navid/Bagher covering 3.42 acres, further improving access from Hicks Road to the preserve. ———————————————————————————————————————————————————————— MAA24-004 Kahn Property Acquisition Prior Years———————————————————————————————————————————————————————— Purchased the 24.01-acre Kahn property for open space and watershed protection. ———————————————————————————————————————————————————————— In Support of MAA24 Prior Years———————————————————————————————————————————————————————— Pursued land conservation opportunities by continuing to work with a landowner and consulting with Santa Clara County planning department about possible lot line adjustments or remainder lot legalization along Pheasant Creek. ———————————————————————————————————————————————————————— Continued to negotiate with Valley Water about a land exchange to facilitate widening of Hicks Road near Guadalupe Reservoir and construction of a potential new parking area for the preserve. ———————————————————————————————————————————————————————— 72 Measure AA Bond Annual Accountability Report FY2018-19 Sierra Azul Open Space Preserve by Dale Grogan PROJECT CHALLENGES ———————————————————————————————————————————————————————— Land acquisition requires a willing seller. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— Continue negotiations for potential land acquisition. ———————————————————————————————————————————————————————— Complete western pond turtle studies. ———————————————————————————————————————————————————————— 73Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $10,078,000 24-001—Barth Property Purchase $300,035 $300,035 24-002—Petersen Property Acquisition $700,603 $700,603 24-003—Property Exchange Navid/Bagher $39,184 $39,184 24-004—Kahn Property Acquisition $552,174 $552,174 24-005—Morales Property Acquisition* $14,900 ($14,900)$0 Grand Total $10,078,000 $1,606,896 ($14,900)$1,591,996 $8,486,004 15.80% * Project expenditures were transferred from MAA funding to the general fund since acquisition of this property is not expected to materialize in the near future. Portfolio 24: Sierra Azul—Rancho de Guadalupe Family Recreation 15.80% OF FUNDS USED Total Life-to-Date Through 6/30/19 $1,591,996 Expenditure Plan Remaining $8,486,004 Portfolio 25 Sierra Azul Loma Prieta Area Public Access, Regional Trails and Habitat Projects DESCRIPTION———————————————————————————————————————————————————————— Provide public access and recreation, including small campground ———————————————————————————————————————————————————————— Develop, improve and connect regional multiuse trails to Forest of Nisene Marks State Park, to protected land to the east, and to Mount Umunhum———————————————————————————————————————————————————————— Protect steelhead habitat, rare plants and grasslands, and restore knob cone pine stands———————————————————————————————————————————————————————— Portfolio Allocation: $7,986,000 Portfolio Expenditures Through 6/30/2019: $410,150 ———————————————————————————————————————————————————————— NOTABLE ACCOMPLISHMENTS MAA25-001 Land Conservation Opportunities Prior Years———————————————————————————————————————————————————————— Purchased the 40-acre Burton/Robinson property to protect additional habitat within the Loma Prieta area. ———————————————————————————————————————————————————————— PROJECT CHALLENGES ———————————————————————————————————————————————————————— Land acquisition requires a willing seller. ———————————————————————————————————————————————————————— POTENTIAL NEXT STEPS ———————————————————————————————————————————————————————— No project next steps identified at this time. ———————————————————————————————————————————————————————— 74 Measure AA Bond Annual Accountability Report FY2018-19 Sierra Azul Open Space Preserve by Midpen Staff 75Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Total Portfolio Allocation $7,986,000 25-001—Land Conservation Opportunities $410,150 $410,150 Grand Total $7,986,000 $410,150 $0 $410,150 $7,575,850 5.14% Portfolio 25: Sierra Azul—Loma Prieta Area Public Access, Regional Trails and Habitat Projects 5.14% OF FUNDS USED Total Life-to-Date Through 6/30/19 $410,150 Expenditure Plan Remaining $7,575,850 Sierra Azul Open Space Preserve by Xun Li 76 Measure AA Bond Annual Accountability Report FY2018-19 Financial Report by Project Measure AA Expenditures Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Portfolio 1: Miramontes Ridge—Gateway to the Coast Public Access, Stream Restoration and Agriculture Enhancement Total Portfolio Allocation $27,774,000 01-003—Zions Property Purchase $52,915 ($52,915)$0 01 Total $27,774,000 $52,915 ($52,915)$0 $27,774,000 0.00% Portfolio 2: Regional—Bayfront Habitat Protection and Public Access Partnerships Total Portfolio Allocation $5,052,000 02-001—Cooley Landing Interpretive Facilities Design and Implementation $200,686 $973,076 $1,173,762 02-002—Ravenswood Bay Trail Design and Implementation $518,977 $353,932 $872,909 Subtotal $5,052,000 $719,663 $1,327,008 $2,046,671 $3,005,329 40.51% 02-002—Ravenswood Bay Trail Design and Implementation Grant Income ($229,621)($430,987) ($660,608) 02 Total $5,052,000 $490,042 $896,021 $1,386,063 $3,665,937 27.44% Portfolio 3: Purisima Creek Redwoods—Purisima-to-the-Sea Trail, Watershed Protection and Conservation Grazing Total Portfolio Allocation $7,608,000 03-001—Purisima Uplands Lot Line Adjustment and Property Transfer $409,711 $11,558 $421,269 03-002—Purisima Uplands Site Clean up and Soil Remediation Assessment $69,155 $21,704 $90,859 03-003—Purisima Creek Fence Construction $85,501 $85,501 03-004—Harkins Bridge Replacement $475,374 $41,543 $516,917 03-005RP—Purisima Uplands Parking Area and Trail Connections $156,130 $156,130 03 Total $7,608,000 $1,110,370 $160,306 $1,270,676 $6,337,324 16.70% 77Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Portfolio 4: El Corte de Madera Creek—Bike Trail and Water Quality Projects Total Portfolio Allocation $8,376,000 04-002—El Corte de Madera Creek Watershed Protection Final Phase $235,934 $235,934 04-003—El Corte de Madera Creek Watershed Protection Reassessment $83,956 $83,956 04-004—El Corte de Madera Creek Oljon Trail Implementation $260,068 $306,910 $566,978 04 Total $8,376,000 $579,958 $306,910 $886,868 $7,489,132 10.59% Portfolio 5: La Honda Creek—Upper Area Recreation, Habitat Restoration and Conservation Grazing Projects Total Portfolio Allocation $11,733,000 05-001—La Honda Creek Land Conservation Opportunities $1,756,093 $1,756,093 05-002—Upper La Honda Creek Grazing Infrastructure $209,765 $209,765 05-004—La Honda Creek Sears Ranch Interim Parking $5,074 $5,074 05-005—La Honda Creek Red Barn Parking Area and Easy-Access Trail $327,514 $327,514 05-006—La Honda Creek Sears Ranch Road Repair $98,559 $98,559 05-008—La Honda Creek White Barn Structural Rehabilitation $14,699 $13,834 $28,533 05-009—La Honda Creek Redwood Cabin Stabilization and Assessment $3,221 $3,221 05 Total $11,733,000 $2,411,704 $17,055 $2,428,759 $9,304,242 20.70% Portfolio 6: Windy Hill—Trail Improvements, Preservation and Hawthorns Area Historic Partnership Total Portfolio Allocation $12,740,000 06-001 —Hawthorns Parking Lot Concept Design $8,490 $8,490 06-002 —Hawthorns Public Access Site Plan and CEQA $18,112 $18,112 06 Total $12,740,000 $8,490 $18,112 $26,602 $12,713,398 0.21% 78 Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Portfolio 7: La Honda Creek—Driscoll Ranch Public Access, Endangered Wildlife Protection and Conservation Grazing Total Portfolio Allocation $14,825,000 07-001—Event Center and Apple Orchard Purchase $6,007,601 $6,007,601 07-002—Fisheries Restoration, Design and Permitting $727,716 $727,716 07-003—Fisheries Enhancement, Apple Orchard $16,152 $16,152 07-004—Fisheries Enhancement, Event Center $50,000 $50,000 07-005—Grazing and Water Systems Infrastructure $189,422 $189,422 07-006—Cunha Land Purchase $3,080,705 $3,080,705 07-007—Demolitions, Wool Ranch House/Sears Ranch Road $357,803 $357,803 07-009—Sears Ranch Parking Areas $1,124,545 $17,937 $1,142,482 07-010—Sears Ranch Road Repair $458,484 $458,484 07-011—La Honda Creek Loop Trails $27,058 $104,012 $131,070 Subtotal $14,825,000 $12,039,486 $121,948 $12,161,434 $2,663,566 82.03% 07-002—Fisheries Restoration, Design and Permitting Grant Income ($230,970)($230,970) 07 Total $14,825,000 $11,808,516 $121,948 $11,930,464 $2,894,536 80.48% Portfolio 8: La Honda Creek/Russian Ridge—Preservation of Upper San Gregorio Watershed and Ridge Trail Completion Total Portfolio Allocation $15,347,000 08-001—Folger Property Purchase $2,153,910 $2,153,910 08 Total $15,347,000 $0 $2,153,910 $2,153,910 $13,193,090 14.03% Portfolio 9: Russian Ridge—Public Recreation, Grazing and Wildlife Protection Projects Total Portfolio Allocation $5,560,000 09-001—Russian Ridge Mindego Grazing Infrastructure $174,416 $174,416 09-003—Russian Ridge Mindego Pond Improvement $136 $77,512 $77,648 09-004—Mindego Hill Trail Construction $67,403 $67,403 09 Total $5,560,000 $241,955 $77,512 $319,467 $5,240,533 5.75% 79Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Portfolio 10: Coal Creek—Reopen Alpine Road for Trail Use Total Portfolio Allocation $8,017,000 10-001—Alpine Road Regional Trail, Coal Creek $21,949 $144,173 $166,122 10 Total $8,017,000 $21,949 $144,173 $166,122 $7,850,878 2.07% Portfolio 11: Rancho San Antonio—Interpretive Improvements, Refurbishing and Transit Solutions Total Portfolio Allocation $10,811,000 11-001—New Trails to Connect Quarry Trail to Black Mountain Trail $728 $728 11-002—Rancho San Antonio, Deer Hollow Farm: White Barn Rehabilitation $29,511 $3,025 $32,536 11 Total $10,811,000 $30,239 $3,025 $33,264 $10,777,736 0.31% Portfolio 12: Peninsula/South Bay Cities—Partner to Complete Middle Stevens Creek Trail Total Portfolio Allocation $1,038,000 12 Total $1,038,000 $0 $0 $0 $1,038,000 0.00% Portfolio 13: Cloverdale Ranch—Wildlife Protection, Grazing and Trail Connections Total Portfolio Allocation $15,712,000 13 Total $15,712,000 $0 $0 $0 $15,712,000 0.00% Portfolio 14: Regional—Trail Connections and Campgrounds Total Portfolio Allocation $3,966,000 14 Total $3,966,000 $0 $0 $0 $3,966,000 0.00% Portfolio 15: Regional—Redwood Protection and Salmon Fishery Conservation Total Portfolio Allocation $50,728,000 15-001—Conservation Easement Upper Alpine Ranch Area $2,508,695 $2,508,695 15-002—Conley Property Purchase $509,855 $509,855 15-003—Long Ridge Property Addition $14,500 $14,500 15 Total $50,728,000 $3,018,550 $14,500 $3,033,050 $47,694,950 5.98% Portfolio 16: Long Ridge—Trail, Conservation and Habitat Restoration Projects (Saratoga) Total Portfolio Allocation $5,140,000 16 Total $5,140,000 $0 $0 $0 $5,140,000 0.00% 80 Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Portfolio 17: Regional—Complete Upper Stevens Creek Trail Total Portfolio Allocation $7,760,000 17-001—Land Conservation: Last Piece Upper Stevens Creek $1,494,552 $1,494,552 17-002—Demolition & Restoration: Lobner/Lysons $138,060 $9,869 $147,929 17-004—Stevens Creek Nature Trail Bridges, Monte Bello $147,635 $265,218 $412,853 Subtotal $7,760,000 $1,780,247 $275,086 $2,055,333 $5,704,667 26.49% 17-002—Lysons Property Purchase Grant Income (50% of purchase price) ($740,000)($740,000) 17 Total $7,760,000 $1,040,247 $275,086 $1,315,333 $6,444,667 16.95% Portfolio 18: South Bay Foothills—Saratoga-to-the-Sea Trail and Wildlife Corridor Total Portfolio Allocation $1,365,000 18-001—San Jose Water Land Purchase $3,850 $3,850 18 Total $1,365,000 $0 $3,850 $3,850 $1,361,150 0.28% Portfolio 19: El Sereno—Dog Trails and Connections Total Portfolio Allocation $2,254,000 $715 $715 19-001—Gupta/Khan Property Purchase $406,553 $406,553 19-002—Dunham-Bohlman Easement $19,997 $19,997 19-003—Haight-Perry LV Land Acquisition $52,977 $52,977 19 Total $2,254,000 $427,265 $52,977 $480,242 $1,773,759 21.31% Portfolio 20: South Bay Foothills—Wildlife Passage and Ridge Trail Improvements Total Portfolio Allocation $13,966,000 20-001—Wildlife Corridor: Highway 17 Crossing $196,519 $129,262 $325,781 20-002—Bay Area Ridge Trail: Highway 17 Crossing $317 $64,105 $64,422 20 Total $13,966,000 $196,836 $193,367 $390,203 $13,575,798 2.79% 81Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Portfolio 21: Bear Creek Redwoods—Public Recreation and Interpretive Projects Total Portfolio Allocation $17,478,000 21-001—Moody Gulch Fence & Gate Improvements $847 $847 21-002—Bear Creek Redwoods Preserve Plan ($12,954)($1,415)($14,369) 21-003—Bear Creek Redwoods Stables Water System $191,149 $794 $191,943 21-004—Bear Creek Stables Site Plan Implementation $282,075 $2,270 $284,345 21-005—Bear Creek Redwoods Public Access $1,505,935 $3,748,293 $5,254,228 21-006—Bear Creek Redwoods Alma College Cleanup and Stabilization $692,822 $332,396 $1,025,218 21-007—Bear Creek Redwoods Preserve Plan Invasive Weed Treatment $501,679 $319,050 $820,729 21-008—Bear Creek Redwoods Ponds Restoration and Water Rights $126,676 $62,201 $188,877 21-009—Bear Creek Redwoods Webb Creek Bridge $138,876 $348,616 $487,492 21-010—Bear Creek Redwoods Landfill Characterization and Remediation $36,375 $36,375 Subtotal $17,478,000 $3,427,105 $4,848,581 $8,275,686 $9,202,314 47.35% 21-007—Bear Creek Redwoods Preserve Plan Invasive Weed Treatment Grant Income ($107,042)($189,882)($296,924) 21 Total $17,478,000 $3,320,063 $4,658,699 $7,978,762 $9,499,238 45.65% Portfolio 22: Sierra Azul—Cathedral Oaks Public Access and Conservation Projects Total Portfolio Allocation $6,714,000 22-001—Hendrys Creek Property Land Restoration $168,316 $304,668 $472,984 22-003—Freudenberg Land Purchase $540,587 $540,587 22-004—Beatty Parking Area and Trail Connections $64,325 $64,325 Subtotal $6,714,000 $708,903 $368,992 $1,077,895 $5,636,105 16.05% 22-001—Hendrys Creek Property Land Restoration Grant Income ($67,111)($67,111) 22 Total $6,714,000 $641,792 $368,992 $1,010,784 $5,703,216 15.05% 82 Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Portfolio 23: Sierra Azul—Mount Umunhum Public Access and Interpretation Projects Total Portfolio Allocation $27,972,000 23-001—Mt. Um Road and Trail Property Rights $1,271,318 $1,271,318 23-002—Mt. Um Trail $959,548 $959,548 23-004—Mt. Um Summit Restoration, Parking and Landing Zone $10,398,273 $29,853 $10,428,126 23-005—Mt. Um Guadalupe Creek Overlook and Bridges $259,311 $259,311 23-006—Mt. Um Road Design/ Permitting/Construction $6,280,251 $6,280,251 23-007—Twin Creeks Land Conservation $2,913,372 $812,554 $3,725,926 23-008—Twin Creeks Restoration $9,963 $9,963 Subtotal $27,972,000 $22,082,073 $852,369 $22,934,442 $5,037,558 81.99% 23-004—Mt. Umunhum Summit Restoration, Parking and Landing Zone Grant Income ($570,000)($570,000) 23-007—Twin Creeks Land Conservation Grant Income ($750,000)($750,000) 23 Total $27,972,000 $20,762,073 $852,369 $21,614,442 $6,357,558 77.27% Portfolio 24: Sierra Azul—Rancho de Guadalupe Family Recreation Total Portfolio Allocation $10,078,000 24-001—Barth Property Purchase $300,035 $300,035 24-002—Petersen Property Acquisition $700,603 $700,603 24-003—Property Exchange Navid/ Bagher $39,184 $39,184 24-004—Kahn Property Acquisition $552,174 $552,174 24-005—Morales Property Acquisition $14,900 ($14,900)$0 24 Total $10,078,000 $1,606,896 ($14,900)$1,591,996 $8,486,004 15.80% 83Measure AA Bond Annual Accountability Report FY2018-19 Project Expenditure Plan Total Through Prior Period 6/30/18 Current Period 7/1/18 Through 6/30/19 Total Life-to- Date Through 6/30/19 Expenditure Plan Remaining Percent Expended Portfolio 25: Sierra Azul—Loma Prieta Area Public Access, Regional Trails and Habitat Projects Total Portfolio Allocation $7,986,000 25-001—Land Conservation Opportunities $410,150 $410,150 25 Total $7,986,000 $410,150 $0 $410,150 $7,575,850 5.14% Subtotal $300,000,000 $50,874,754 $10,871,866 $61,746,620 $238,253,380 20.58% Reimbursements from Grants and Other Contributions ($2,694,744) ($620,869) ($3,315,613) GRAND TOTAL $300,000,000 $48,180,010 $10,250,997 $58,431,007 $241,568,993 19.48% EXHIBIT A Expenditure Plan TITLE: To improve access to hiking and biking opportunities, protect and preserve redwood forests, natural open spaces, the scenic beauty of the region and coastline, critical wildlife habitat, restore creeks to protect water quality, and reduce forest fire risk. 1. SUMMARY Founded by voters in 1972, the Midpeninsula Regional Open Space District (“District”) has protected, in perpetuity, 62,000 acres of open space containing 26 preserves and more than 220 miles of trails that serve Santa Clara, San Mateo, and a portion of Santa Cruz counties. The District’s preserves provide a scenic backdrop to the region offering residents places for hiking, biking, horseback riding, or simply connecting with nature, close to home. Throughout its 41-year history the District has used taxpayer dollars wisely, leveraging funds to bring in state, federal, and private grant money, and providing annual audits in a transparent public process. The District is governed by a publicly elected board of directors. Over the years, the number of acres and miles of trails the District owns and maintains have steadily increased, as have the number of visitors and the cost of land. Expanding public access, restoring sensitive environments and purchasing land are costly, yet are high priorities for the public. To reinforce and expand these types of services and resources, the Board of Directors is placing this funding measure on the June 3, 2014 ballot. $300 million in General Obligation Bonds will be sold. The bond repayment would be financed by an annual property tax override based on a tax rate not to exceed $3.18 per $100,000 of assessed value of property owned per year. This Expenditure Plan outlines priority actions identified by the public and proposed by the District to be funded with bond proceeds. Part B describes each priority action and describes what goals it will achieve. Part C of the Expenditure Plan describes the establishment of an independent Citizen Oversight Committee. Measure AA Ballot Language, as approved by voters on June 3, 2014 84 2.PRIORITY ACTIONS The priority actions listed below are the result of a process that combined scientific analysis with broad public engagement to create a shared vision for the future of the District and the region’s open space. Each priority action may address one or more of the following as more specifically described in the table Priority Actions, By Region attached to this Expenditure Plan: •Improved hiking, biking, and equestrian opportunities •Protection and preservation of redwoods, natural open spaces, the scenic beauty of the region and coastline, critical habitats •Restoration of creeks to protect water quality •Reduction of forest fire risk Priority actions are distributed throughout the District as depicted on the map attached to this Expenditure Plan. If approved, the bond proceeds would be allocated to fund the capital improvements necessary to implement the priority actions listed below. Note: the number associated with each priority action does not denote its priority level, but is only used for identification purposes to correlate with the locations depicted on the map. The estimates associated with each priority action are in 2014 dollars. These are estimates only, and the actual costs may change in implementation. The District may annually review and propose amendments to the Expenditure Plan to provide for the use of additional federal, state and local funds, to account for unexpected revenues, or to take into consideration unforeseen circumstances. The District shall act on no more than one package of amendments each fiscal year. The District shall establish a process for proposed Expenditure Plan amendment(s) which ensures that the Citizen Oversight Committee is included in the development. Upon completion of this process, amendments(s) to the Expenditure Plan must be passed by a two-thirds majority of the District Board in a publicly noticed meeting. Measure AA Ballot Language, as approved by voters on June 3, 2014 85 PRIORITY ACTIONS, BY REGION South Bay Foothills (Los Gatos, Monte Sereno, Saratoga, and Santa Cruz Mountains) 18 South Bay Foothills: Saratoga-to-Sea Trail and Wildlife Corridor Protect wildlife corridor along Highway 9. Connect trail to Saratoga-to-Sea Trail and Skyline-to-Sea Trail. $1,365,000 19 El Sereno: Dog Trails and Connections Provide infrastructure to open trails to dogs. Develop connections to Skyline, Sanborn County Park, & Lexington Reservoir. $2,254,000 20 South Bay Foothills: Wildlife Passage and Ridge Trail Improvements Establish safe corridors for mountain lions across Highway 17. Establish Bay Area Ridge Trail crossing. $13,966,000 21 Bear Creek Redwoods: Public Recreation and Interpretive Projects Open for hiking, equestrian activities. Provide parking areas, trails; upgrade stables. Restore & protect habitats for various species. Repair roads & trails to reduce sediment. Rehabilitate Alma College site. $17,478,000 22 Sierra Azul: Cathedral Oaks Public Access and Conservation Projects Develop multi-use trail & plan future trails as land is available. Develop parking. Restore plant communities and soils. Install trailside amenities. Preserve additional open space and complete wildlife corridor in upper Los Gatos Creek watershed. $6,714,000 23 Sierra Azul: Mt. Umunhum Public Access and Interpretation Projects Open Mt. Umunhum for multi-use public access to summit via road and trail. Open Bay Area Ridge Trail and nearby trail connections. Preserve additional open space and complete wildlife corridor. $27,972,000 24 Sierra Azul: Rancho de Guadalupe Family Recreation Open Rancho de Guadalupe to public access. Develop accessible multi-use trails with amenities such as parking and family recreation. Restore habitat for rare species. Protect cultural and natural resources. $10,078,000 25 Sierra Azul: Loma Prieta Area Public Access, Regional Trails and Habitat Projects Provide public access and recreation, including small campground. Develop, improve, connect regional multi-use trails to Forest of Nisene Marks State Park, to protected land to east, and to Mt. Umunhum. Protect Steelhead habitat, rare plants and grasslands, restore Knobcone Pine stands. $7,986,000 Measure AA Ballot Language, as approved by voters on June 3, 2014 86 Peninsula Foothills and Bay (Cupertino, Los Altos, Los Altos Hills, Sunnyvale, Mountain View, Palo Alto, East Palo Alto, Menlo Park, Atherton, Redwood City, San Carlos, Woodside, Portola Valley, Skyline 2 Regional: Bayfront Habitat Protection and Public Access Partnerships Partner to complete gaps in Bay Trail and develop city-to-bay trails. Support wetland restoration and associated interpretive facilities. Preserve additional bayfront open space. $5,052,000 4 El Corte de Madera Creek: Bike Trail and Water Quality Projects Develop single-use biking/hiking trails, complete Ridge Trail gaps, and develop trail system leading to parking area. Restore damaged trails to improve water quality. Preserve additional open space as available. $8,376,000 5 La Honda Creek: Upper Area Recreation, Habitat Restoration and Conservation Grazing Projects Open upper half of the preserve to public; provide biking/hiking/equestrian trails, dog access, and staging areas. Provide loop & connector trails. Restore habitat for rare species. Improve fencing, corrals, and water systems to reintroduce conservation grazing. $11,733,000 6 Windy Hill: Trail Improvements, Preservation and Hawthorns Area Historic Partnership Improve trails, complete pond facilities. Increase multi-use trails, study possible improvements to increase dog use. Open Hawthorns Area; develop trails connecting to Portola Valley and Palo Alto trails. Partner to protect, restore, and interpret historic buildings. Improve habitat conditions in Los Trancos Creek. Preserve additional scenic open space as available. $12,740,000 8 La Honda Creek/Russian Ridge: Preservation of Upper San Gregorio Watershed & Ridge Trail Completion Preserve upper San Gregorio watershed; restore endangered species habitats. Support opportunities to provide additional water for fisheries. Complete Bay Area Ridge Trail multi-use connections and gaps. Provide additional public use facilities. $15,347,000 9 Russian Ridge: Public Recreation, Grazing and Wildlife Protection Projects Open currently closed areas of preserve. Construct and extend trails. Improve fencing, corrals, and water systems to reintroduce conservation grazing. Improve habitat for sensitive species, implement pond enhancement projects for garter snakes and red-legged frogs. $5,560,000 10 Coal Creek: Reopen Alpine Road for Trail Use Reopen Alpine Road as trail connection between Portola Valley & Skyline Blvd. Reroute trails to reduce erosion and improve visitor experience. $8,017,000 11 Rancho San Antonio: Interpretive Improvements, Refurbishing, and Transit Solutions Add welcome center, refurbish and add interpretive exhibits to Deer Hollow Farm. Support of transit improvement options such as bike trails, bikeshare station, bus service, or additional parking. $10,811,000 12 Peninsula/South Bay Cities: Partner to Complete Middle Stevens Creek Trail Support work by cities to develop the middle section of the Stevens Creek Trail and enhance neighborhood connections. Support work by partners to complete stream corridor restoration and steelhead habitat enhancement below dam. Develop and install interpretive signage. $1,038,000 16 Long Ridge: Trail, Conservation and Habitat Restoration Projects (Saratoga) Improve roadside parking and provide restrooms. Develop new trail connections to Eagle Rock and Devils Canyon. Repair trails for year-round multi-use access. Protect watersheds for steelhead. Preserve additional open space as available. Implement pond and habitat enhancement restoration projects to benefit rare species. $5,140,000 17 Regional: Complete Upper Stevens Creek Trail Complete multi-use connection between the Bay Trail & Bay Area Ridge Trail above the reservoir through Picchetti Ranch Open Space Preserve & Lower/Upper Stevens Creek County Parks. Improve Preserve trails and neighborhood connections. Preserve additional open space as available. $7,760,000 Measure AA Ballot Language, as approved by voters on June 3, 2014 87 Coast (Half Moon Bay, San Gregorio, Pescadero, La Honda,) 1 Miramontes Ridge: Gateway to the Coast Public Access, Stream Restoration and Agriculture Enhancement Preserve scenic open space land as available, and establish wildlife corridor. Restore fish and red-legged frog habitats in Madonna Creek watershed. Partner to enhance water availability for agriculture and fish. Develop trail loop system, including Ridge Trail and neighborhood access points. Develop staging area, repair bridges. $27,774,000 3 Purisima Creek Redwoods: Purisima-to-Sea Trail, Watershed Protection and Conservation Grazing Complete and open multi-use Purisima-to-Sea trail connection between Ridge Trail and Coastal Trail, and new parking areas. Preserve additional open space as available. Remove fish barriers and restore Lobitos Creek. Restore ponds for endangered species. $7,608,000 7 La Honda Creek: Driscoll Ranch Public Access, Endangered Wildlife Protection and Conservation Grazing Open Driscoll Ranch Area; provide biking/hiking/equestrian trails, limited dog access, parking areas, and interpretive displays. Develop loop & connector trails. Restore habitat for endangered species. Restore La Honda Creek; remove fish migration barriers. $14,825,000 13 Cloverdale Ranch: Wildlife Protection, Grazing and Trail Connections Improve fencing, corrals, and water systems to increase conservation grazing and sustain large contiguous grasslands. Restore habitat for endangered species. Provide trail connections to nearby State parks. $15,712,000 14 Regional: Trail Connections and Campgrounds Develop trails between Butano, Pescadero County Park, Pescadero, Russian Ridge, and between Skyline and Portola Redwoods, Big Basin State Park. Partner with County and State Parks to improve existing campgrounds. $3,966,000 15 Regional: Redwood Protection and Salmon Fishery Conservation Preserve additional open space as available. Protect and enhance redwood stands, mountain scenery, various habitats and steelhead salmon. $50,728,000 Measure AA Ballot Language, as approved by voters on June 3, 2014 88 Measure AA Ballot Language, as approved by voters on June 3, 2014 89 3.INDEPENDENT CITIZEN OVERSIGHT COMMITTEE An Independent Citizen Oversight Committee will be formed to verify expenditures of bond proceeds. The Independent Citizen Oversight Committee will consist of seven at-large members, all of whom shall be District residents. The Citizen Oversight Committee will be selected by the Board and interviewed and approved in open session, and will be subject to the conflict of interest constraints of the California Political Reform Act. The responsibilities of the Committee include: •Review Plan expenditures on an annual basis to verify conformity with the Expenditure Plan. •Review District’s Annual Audit and Annual Accountability report and present the Committee’s findings to the Board at a public meeting. •Review any proposed amendments to the Expenditure Plan. Measure AA Ballot Language, as approved by voters on June 3, 2014 90 EXHIBIT B TAX RATE STATEMENT An election will be held in the Midpeninsula Regional Open Space District (the "District") on June 3, 2014, to authorize the sale of up to $300 million in bonds of the District to provide public access and acquire, restore, and preserve open space throughout the District as described in the ballot measure. If the bonds are approved, the District expects to sell the bonds in several series over time. Principal and interest on the bonds will be payable from the proceeds of tax levies made upon the taxable property in the District. The information contained in numbered paragraphs 1 - 3 below is provided in compliance with sections 9400-9404 of the Elections Code of the State of California. 1. The best estimate of the tax which would be required to be levied to fund this bond issue during the first fiscal year after the sale of the first series of bonds, based on estimated assessed valuations available at the time of filing of this statement, is $1.00 per $100,000 of assessed valuation in fiscal year 2015-16. 2. The best estimate of the tax rate which would be required to be levied to fund this bond issue during the first fiscal year after the sale of the last series of bonds, based on estimated assessed valuations available at the time of filing of this statement, is $2.90 per $100,000 of assessed valuation in fiscal year 2044-45. 3. The best estimate of the highest tax rate which would be required to be levied to fund this bond issue, based on estimated assessed valuations available at the time of filing of this statement, is $3.18 per $100,000 of assessed valuation in fiscal year 2034-35. Voters should note that the estimated tax rates are based on the estimated ASSESSED VALUE of taxable property on the respective County's official tax rolls, not on a property's market value. Property owners should consult their own property tax bills to determine their property's assessed value and any applicable tax exemptions. Attention of all voters is directed to the fact that the foregoing information is based upon the District's projections and estimates only, which are not binding upon the District. The actual tax rates and the years in which they will apply may vary from those presently estimated, due to variations from these estimates in the timing of bond sales, the amount of bonds sold and market interest rates at the time of each sale, and actual assessed valuations over the term of repayment of the bonds. The dates of sale and the amount of bonds sold at any given time will be determined by the District based on its needs for funds and other factors. The actual interest rates at which the bonds will be sold will depend on the bond market at the time of each sale. Actual future assessed valuation will depend upon the amount and value of taxable property within the District as determined by the respective County Assessor in the annual property value assessment process. Dated: _______, 2014. _________________________ General Manager Midpeninsula Regional Open Space District Measure AA Ballot Language, as approved by voters on June 3, 2014 91 Expenditures Expenditures from from July 1, 2018 Inception through through Project No.Project Description June 30, 2019 June 30, 2019 20005 New Trail Easement - SFPUC, Ravenswood (MAA 2-2)(22,603)$ A -$ -$ 20088 POST Hendry's Creek Restoration (MAA 22-1)(41,330) B -- 20101 Lysons Property ( 17-1 MAA )(27,059) C -- 20102 Lobner Demolition (MAA 17-2)(128,760)C -- 20109 Riggs Property Appraisal - (3-1 MAA)(6,500) D -- 20110 Purisima Creek Uplands Lot line Adjustment (3-1 MAA)(13,000) D -- 20112 Conservation Easement Upper Alpine Ranch Area (15-1 MAA)(8,695) E -- 20113 Preservation of Upper Los Gatos Creek Watershed (22-1 MAA)(5,000) B -- 20114 Land Conservation Opportunities MAA 25-1 (Burtons )(150)F -- 30503 ECDM Trail Improvements (MAA 4-4)(3,930) G -- 30904 Mindego Area - Mindego Hill Trail (MAA 9-4)(34,196) H -- 31309 Mt Um Bald Mtn Staging to Summit Trail (MAA 23-2)(17,646) I -- 31310 Mt Um Summit Restor & Improv (MAA 23-4)(79,491) I -- 31311 Mt Um Trail Overlook & Bridges (MAA 23-5)(243)I -- 31500 Measure AA Project 11-1 (728)J -- 65101 PCR Harkins Bridge Replacement (MAA 3-4)(108,788)D -- 65201 Lower Stevens Canyon Hiking Bridge (MAA 17-4)(103,187)C -- 80016 ECdM Creek Watershed Protection Program (MAA 4-3)(45,507) G -- 80029 Pond DR05 Repair (MAA 7-5)(150,682)K -- 80037 Mindego Grazing Infrastructure (MAA 9-1)(135,748)H -- 80038 LHC Grazing Infrastructure - McDonald Ranch Fencing (MAA 5-2)(178,850)L -- AA01 Miramontes Ridge - Gateway to San Mateo Coast -(52,915.00)- AA02 Bayfront Habitat Protection & Public Access Partnerships 22,603 A 1,327,008.00 2,046,671 AA03 Purisima Creek Redwoods: Purisma-to Sea Trail, Watershed/Graze 128,288 D 160,306.00 1,270,676 AA04 El Corte de Madera Creek: Bike Trail & Water Quality 49,437 G 306,910.00 886,868 AA05 La Honda Creek - Upper Recreation Area 178,850 L 17,055.00 2,428,759 AA06 Hawthorn Public Access Improvements -18,112.00 26,602 AA07 Driscoll Ranch Public Access, Wildlife Protection, Grazing 150,682 K 121,948.00 12,161,434 AA08 La Honda/Russian Ridge: Upper San Gregorio Watershed -2,153,910.00 2,153,910 AA09 Russian Ridge: Public Recreation, Grazing & Wildlife Protection 169,944 H 77,512.00 319,467 AA10 Coal Creek: Reopen Alpine Road for Trail Use -144,173.00 166,122 AA11 Rancho San Antonio: Interpretive Improvements, Refurbishing 728 J 3,025.00 33,264 AA15 Regional: Redwood Protection & Salmon Fishery Conservation 8,695 E 14,500.00 3,033,050 AA17 Regional: Complete Upper Stevens Creek Trail 259,006 C 275,086.00 2,055,333 AA18 South Bay Foothills: Saratoga-to-Sea Trail & Wildlife Corridor -3,850.00 3,850 AA19 El Sereno Dog Park & Connections -52,977.00 480,242 AA20 South Bay Foothills: Wildlife Passage/Ridge Trail Improvements -193,367.00 390,203 AA21 CR:Pub Recreation Proj -4,848,581.00 8,275,686 AA22 Cathedral Oaks Public Access & Conservation 46,330 B 368,992.00 1,077,895 AA23 Mt Um Pub Access/Intrep 97,380 I 852,369.00 22,934,442 AA24 Rancho de Guadalupe Family Recreation -(14,900.00)1,591,996 AA25 Loma Prieta Area Public Access 150 F -410,150 Total MAA Bond Project Expenditures -10,871,866 61,746,620 Reimbursements from Grants, Contributions, and Other Funds -(620,869)(3,315,613) Total MAA Bond Project Expenditures - Net Reimbursements -$ 10,250,997$ 58,431,007$ During fiscal ye ar ending June 30, 2019,the District realigned pre-existing project numbers eligible for Measure AA (MAA)funding with the Measure AA projects numbers (MAA)for ease of project review.Letters in adjustment column indicate the transfer of expenses between project numbers.Prior expenditure balances related to appraisals and land surveys in MAA01 "Miramontes Ridge -Gateway to San Mateo Coast"and MAA24 “Sierra Azul:Rancho de Guadalupe Family Recreation Projects”were removed as the transactions failed to materialize. Adjustments Midpeninsula Regional Open Space District Measure AA Bond Program Schedule of Program Expenditures June 30, 2019 This page is an excerpt from the Consolidated Annual Financial Statement for fiscal year ended June 30, 2019, page 85. Annual audited financial statements can be found at openspace.org/financials. MIDPENINSULA REGIONAL OPEN SPACE DISTRICT 330 Distel Circle Los Altos, California 94022-1404 650-691-1200 info@openspace.org openspace.org PRINTED ON POST CONSUMER WASTE PAPER Sierra Azul Open Space Preserve by C. Schell