HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2ONYX - Three Week Look Ahead 9-14-20 through 10-2-20 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. Lazaro Pulverizing and Grading C. Lazaro Paving D. Jimenez E. DaPonte F. F & C Concrete Week Of TASK CREW 9/14/20 through 9/18/2 A. Crew: Continue curb and sidewalk on Bellevue St. A. Onyx Crew Peters Crew: Remove and Pour new sidewalks on Everett and Malden St. Onyx (Peters crew) F: Continue curb and sidewalk on Bellevue St. / Then curb on Kimball on friday F. F & C Concrete C. Lazaro Paving to pave Kimball, Nichols, Frank and Louise, downey, and then finish pave Everett, Bartlett, and Avon St. C. Lazaro Paving 9/21 /20 through 9/25/20 A. Crew: Continue curb and sidewalk on Bellevue St. A. Onyx Crew Peters Crew: Continue curb and sidewalk on Kimball St. Onyx (Peters crew) F: Continue curb and sidewalk on Bellevue St. / continue curb and sidewalk on Kimball on friday F. F & C Concrete 9/28/20 through 10/2/20 A. Crew: Continue curb and sidewalk on Bellevue St. A. Onyx Crew Peters Crew: Finish curb and sidewalk on Kimball St./Loam back of sidewalk then mobilize to Frank and Louise St. Onyx (Peters crew) F: Continue curb and sidewalk on Bellevue St. / continue curb and sidewalk on Kimball on friday IF. F & C Concrete Notes: Primier fence is awaiting some revisions to the guardrail to schedule. They are not on the schedule but would like to have them in the