HomeMy Public PortalAboutThree Week Look Ahead Watertown Phase 1 and 2ONYX - Three Week Look Ahead 9-14-20 through 10-2-20
Watertown Rehab Phase 1 and 2
CREWS:
A. Onyx Crew
B. Lazaro Pulverizing and Grading
C. Lazaro Paving
D. Jimenez
E. DaPonte
F. F & C Concrete
Week Of
TASK
CREW
9/14/20
through
9/18/2
A. Crew: Continue curb and sidewalk on Bellevue St.
A. Onyx Crew
Peters Crew: Remove and Pour new sidewalks on Everett and Malden St.
Onyx (Peters crew)
F: Continue curb and sidewalk on Bellevue St. / Then curb on Kimball on friday
F. F & C Concrete
C. Lazaro Paving to pave Kimball, Nichols, Frank and Louise, downey, and then
finish pave Everett, Bartlett, and Avon St.
C. Lazaro Paving
9/21 /20
through
9/25/20
A. Crew: Continue curb and sidewalk on Bellevue St.
A. Onyx Crew
Peters Crew: Continue curb and sidewalk on Kimball St.
Onyx (Peters crew)
F: Continue curb and sidewalk on Bellevue St. / continue curb and sidewalk on
Kimball on friday
F. F & C Concrete
9/28/20
through
10/2/20
A. Crew: Continue curb and sidewalk on Bellevue St.
A. Onyx Crew
Peters Crew: Finish curb and sidewalk on Kimball St./Loam back of sidewalk then
mobilize to Frank and Louise St.
Onyx (Peters crew)
F: Continue curb and sidewalk on Bellevue St. / continue curb and sidewalk on
Kimball on friday
IF. F & C Concrete
Notes: Primier fence is awaiting some revisions to the guardrail to schedule. They are not on the schedule but would like to have them in the