Loading...
HomeMy Public PortalAboutWatertown Phase 1 and 2 Three week look aheadONYX - Three Week Look Ahead 9-25-20 through 10-9-20 Watertown Rehab Phase 1 and 2 CREWS: A. Onyx Crew B. Onyx Crew C. Onyx Crew B. Lazaro Pulverizing and Grading C. Lazaro Paving D. Jimenez E. DaPonte F. F & C Concrete Week Of TASK CREW 9/21 /20 through 9/25/20 A. Onyx Crew: Continue to install curb and sidewalk on Bellevue St. A. Onyx Crew B. Onyx Crew: Continue to install curb and sidewalk Kimball St. B. Onyx Crew C. Onyx Crew: Continue removing panels and replacing them on Everett St. C. Onyx Crew 9/28/20 through 10/2/20 A. Onyx Crew: Continue to install curb and sidewalk on Bellevue St. A. Onyx Crew B. Onyx Crew: Continue to install curb and sidewalk Kimball St. B. Onyx Crew C. Onyx Crew: Finish removing panels and replacing them on Everett St. C. Onyx Crew 10/5/20 through through A. Onyx Crew: Continue to install curb and sidewalk on Bellevue St. A. Onyx Crew B. Onyx Crew: Continue to install curb and sidewalk Kimball St. B. Onyx Crew